Prior art keywords
test
frequency converter
cabinet
load motor
testing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201220259804XU
Other languages
Chinese (zh)
Inventor
陈汉平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Warner Technologies (shenzhen) Ltd
Original Assignee
Warner Technologies (shenzhen) Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Warner Technologies (shenzhen) Ltd filed Critical Warner Technologies (shenzhen) Ltd
Priority to CN201220259804XU priority Critical patent/CN202583372U/en
Application granted granted Critical
Publication of CN202583372U publication Critical patent/CN202583372U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Testing Of Individual Semiconductor Devices (AREA)

Abstract

Complete machine testing equipment of a frequency converter is provided. The equipment comprises a testing clamp, a testing cabinet, a control computer, a display screen, a load motor and a load motor testing device; the testing clamp is provided with a testing clamp main body for placing a frequency converter, one end of the testing clamp main body is provided with a plug, the plug is connected with a plurality of conducting wires for connecting a frequency converter terminal row; the testing cabinet is a box-shaped structure with one side open, the open side is provided with a cabinet door for enclosing an internal cavity of the testing cabinet, the inner wall of the testing cabinet, which is opposite to the cabinet door, is provided with a socket, the socket is respectively connected with an external power supply and the load motor, the socket is also provided with a slot coupled and plugged with a pin of the socket, the load motor is connected with the load motor testing device, and the load motor testing device and the display screen are all connected with the control computer. By adopting the equipment, the test connection trouble of repeatedly replacing frequency converters during the complete machine testing process of the frequency converter can be avoided, and working efficiency can be enhanced.

Description

A kind of system test equipment of frequency converter
Technical field
The utility model relates to a kind of system test equipment, relates in particular to the system test equipment of frequency converter.
Background technology
The system test of frequency converter generally needs through several test links such as vdct, alternating voltage test and functional tests.Vdct need connect DC voltage to frequency converter, and the alternating voltage test need connect alternating voltage to frequency converter, and functional test need connect motor to frequency converter.Because can not carry out above-mentioned several kinds of tests simultaneously, therefore, whenever once to test, frequency converter all need carry out different connections to realize test.The connection of change frequency converter that so just must be frequent has caused the low of work efficiency.
The utility model content
The technical matters that the utility model will solve is that the system test link that overcomes owing to frequency converter needs the frequent connected mode that changes to cause the low problem of work efficiency, and proposes a kind of system test equipment of frequency converter.
For solving the problems of the technologies described above, the utility model proposes a kind of system test equipment of frequency converter, comprises a test fixture, a test cabinet, a controlling computer, a display screen, a load motor and a load motor proving installation; Test fixture be provided with one be used to place frequency converter the test fixture main body, test fixture main body one end is provided with a plug, plug is connected with the terminal row of frequency converter through multiple conducting wires, also is provided with many contact pins on the plug; The test cabinet is the box like structure of a side opening; Its open side is provided with the cabinet door of closed test cabinet internal cavities; The inwall of test cabinet relative cabinet door is provided with a socket, and socket links to each other with load motor with external power source respectively, also be provided with on the socket with plug on contact pin mate the slot of grafting; Load motor connects the load motor proving installation, and the load motor proving installation all links to each other with controlling computer with display screen.
Preferably; Controlling computer comprise a primary controller, in order to the data acquisition unit, of the test data of gathering frequency converter in order to the storer of store test data and the dispensing device that test data is outwards sent; Data acquisition unit, storer and dispensing device all link to each other with primary controller, and test socket cashier's office in a shop links to each other with data acquisition unit.
Preferably, the bottom surface of test fixture main body is provided with guided way, and the diapire inside surface of test cabinet is provided with the guide chute that cooperates guided way.
Compared with prior art; The beneficial effect of the utility model comprises: the setting of the utility model test clamp and test cabinet; Only need to change being connected of test cabinet and outside input and output; And the connection that does not need the frequent change frequency converter just can realize the test of different links, has improved work efficiency.
Description of drawings
Fig. 1 is the system test equipment principle block diagram of the utility model frequency converter.
Embodiment
For principle and the structure that further specifies the utility model, combine accompanying drawing that the preferred embodiment of the utility model is elaborated at present.
Consult Fig. 1, the system test equipment of the utility model frequency converter comprises a test fixture 2, a test cabinet 3, a controlling computer 4, a display screen 5, a load motor 6, a load motor proving installation 7 and external power source 8.
Test fixture 2 be provided with one be used to place frequency converter 1 the test fixture main body, test fixture main body one end is provided with a plug, plug connects the terminal row of frequency converter 1 through multiple conducting wires.Also be provided with many contact pins on this plug.
Test cabinet 3 is the box like structure of a side opening, and its open side is provided with the cabinet door of closed test cabinet 3 internal cavities.The cabinet door is provided with the test button, and this test button is used to control the beginning and the end of test.The inwall of test cabinet 3 relative cabinet doors is provided with a socket, socket be provided with plug on the slot of contact pin coupling grafting.The diapire inside surface of test cabinet 3 is provided with the guide chute that cooperates guided way.The setting of guiding cabinet and guide chute makes test fixture 2 be convenient to push in the test cabinet 3 along guide chute.Need not adjust the position of test fixture 2 like this, just can be so that the plug insertion socket on the test fixture 2, frequency converter 1 is connected through the input and output of this socket with the outside.
Controlling computer 4 comprise a primary controller, in order to the data acquisition unit, of the test data of gathering frequency converter 1 in order to the storer of store test data and the dispensing device that test data is outwards sent.Data acquisition unit, storer and dispensing device all link to each other with primary controller, and data acquisition unit also links to each other with the socket of test on the cabinet 3.
Load motor 6 is connected on the socket of testing cabinet 3 and through this socket and links to each other with test cabinet 3 inner frequency converters 1, and load motor proving installation 7 links to each other with the data acquisition unit of controlling computer 4.Display screen 5 links to each other with controlling computer 4, and it is used to show the ruuning situation of frequency converter 1 in test cabinet 3 the insides.
Test cabinet 3 can be used as the vdct cabinet of test frequency converter's DC break down voltage, also can be used as the alternating voltage test cabinet of test frequency converter's ac voltage withstanding, also can be used as the functional test cabinet of test frequency converter's operation function.
When test cabinet 3 is used as the vdct cabinet; The external power source 8 that links to each other with socket is DC voltage; Whether the set-point that changes DC voltage can be used for test frequency converter 1 and under the DC voltage of certain limit, works normally, and the operational data under the given voltage of difference is stored in the storer of controlling computer through data acquisition unit.
When test cabinet 3 is tested cabinet as alternating voltage; The external power source 8 that links to each other with socket is alternating voltage; Whether the set-point that changes alternating voltage can be used for test frequency converter 1 and under the alternating voltage of certain limit, works normally, and the operational data under the given voltage of difference is stored in the storer of controlling computer through data acquisition unit.
When test cabinet 3 is used as the functional test cabinet; Push the test button on the test cabinet 3 cabinet doors; May command frequency converter 1 drive load motor 6 is realized just changeing, reversing or is stopped and function such as stop; Whether load motor proving installation 7 is realized just changeing, reverses, is stopped and stop etc. according to the instruction of test button in order to detect load motor, and testing result is transferred to controlling computer 4.
After the test of above-mentioned each test cabinet was accomplished, the data acquisition unit of controlling computer 4 was gathered the test data of frequency converter 1, and is stored in the storer, and then, in the time of setting, controlling computer 4 control dispensing devices send to test data on the server.
Compared with prior art; Adopt a kind of system test equipment of frequency converter, the setting of test clamp and test cabinet only needs to change being connected of test cabinet and outside input and output; And do not need just can realize the test of different links to the connection of frequent change frequency converter, improved work efficiency.
The above is merely the preferable possible embodiments of the utility model, and the protection domain of unrestricted the utility model.The equivalent structure that all utilization the utility model instructionss and accompanying drawing content have been done changes, and all is included in the protection domain of the utility model.

Claims (3)

1. the system test equipment of a frequency converter is characterized in that, comprises a test fixture, a test cabinet, a controlling computer, a display screen, a load motor and a load motor proving installation;
Said test fixture be provided with one be used to place said frequency converter the test fixture main body, said test fixture main body one end is provided with a plug, said plug is connected with the terminal row of frequency converter through multiple conducting wires, also is provided with many contact pins on the said plug;
Said test cabinet is the box like structure of a side opening; Its open side is provided with the cabinet door of closed test cabinet internal cavities; The inwall of the said relatively cabinet door of said test cabinet is provided with a socket, and said socket links to each other with said load motor with external power source respectively, also be provided with on the said socket with said plug on the contact pin coupling slot of pegging graft; Said load motor connects said load motor proving installation, and said load motor proving installation all links to each other with said controlling computer with said display screen.
2. the system test equipment of frequency converter as claimed in claim 1; It is characterized in that; Said controlling computer comprises that a primary controller, a data acquisition unit in order to the test data of gathering said frequency converter, are in order to the storer of storing said test data and the dispensing device that said test data is outwards sent; Said data acquisition unit, said storer and said dispensing device all link to each other with said primary controller, and said test socket cashier's office in a shop links to each other with said data acquisition unit.
3. the system test equipment of frequency converter as claimed in claim 1 is characterized in that, the bottom surface of said test fixture main body is provided with guided way, and the diapire inside surface of said test cabinet is provided with the guide chute that cooperates said guided way.
CN201220259804XU 2012-06-04 2012-06-04 Complete machine testing equipment of frequency converter Expired - Fee Related CN202583372U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220259804XU CN202583372U (en) 2012-06-04 2012-06-04 Complete machine testing equipment of frequency converter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220259804XU CN202583372U (en) 2012-06-04 2012-06-04 Complete machine testing equipment of frequency converter

Publications (1)

Publication Number Publication Date
CN202583372U true CN202583372U (en) 2012-12-05

Family

ID=47252773

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220259804XU Expired - Fee Related CN202583372U (en) 2012-06-04 2012-06-04 Complete machine testing equipment of frequency converter

Country Status (1)

Country Link
CN (1) CN202583372U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104375017A (en) * 2014-05-26 2015-02-25 深圳市佛斯特科技有限公司 Frequency changer whole machine test device
CN106338669A (en) * 2016-09-22 2017-01-18 全球能源互联网研究院 Variable frequency speed governor electric energy quality characteristic test cabinet, test system and test method thereof
CN114217178A (en) * 2021-11-04 2022-03-22 深圳市海浦蒙特科技有限公司 Method and system for voltage withstand test of frequency converter and computer readable storage medium

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104375017A (en) * 2014-05-26 2015-02-25 深圳市佛斯特科技有限公司 Frequency changer whole machine test device
CN106338669A (en) * 2016-09-22 2017-01-18 全球能源互联网研究院 Variable frequency speed governor electric energy quality characteristic test cabinet, test system and test method thereof
CN114217178A (en) * 2021-11-04 2022-03-22 深圳市海浦蒙特科技有限公司 Method and system for voltage withstand test of frequency converter and computer readable storage medium

Similar Documents

Publication Publication Date Title
CN202583372U (en) Complete machine testing equipment of frequency converter
CN104933928A (en) Practical training device capable of detecting wiring correctness of circuit automatically
CN102545550A (en) Control device for auxiliary current transformer and auxiliary current transformer system
CN104155887B (en) Multifunctional fault-signal simulating device
CN201514450U (en) Drawer module testing device and drawer module testing system
CN205304290U (en) Novel mobile power supply
CN202916307U (en) Signal switching device for debugging and detection of electrical equipment
CN208272150U (en) A kind of portable rapid wiring device of maintenance power supply
US11557225B1 (en) Portable and interconnectable trainers
CN101778334A (en) Simple electric automobile horn durability tester
CN203084101U (en) Light control valve switch box for converter valve operation test system for DC power transmission project
CN202583374U (en) Frequency converter quality monitoring system
CN202093129U (en) Overpressure resistant machine used in test
CN203616410U (en) Thermistor converter test device
CN102263514A (en) Direct current regulated power supply apparatus
CN105045187B (en) A kind of control method for USB charging port controllers
CN203522641U (en) Improved structure of photovoltaic-assembly testing device
CN205070251U (en) Cubical switchboard dolly error detection handles auxiliary device
CN207703983U (en) Test the adapter of intelligent power module
CN220650823U (en) Energy storage ATE testing arrangement
CN204855060U (en) Torque wrench life test machine
CN209364672U (en) Mechanical arm test equipment
CN102901935A (en) Method for monitoring working condition of intelligent sequential power supplies and device thereof
CN205091613U (en) Controller debugging testing equipment
CN221351977U (en) Switch cabinet control simulation testing device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121205

Termination date: 20150604