CN202578753U - Gas draining pipe for coal mining - Google Patents
Gas draining pipe for coal mining Download PDFInfo
- Publication number
- CN202578753U CN202578753U CN 201220138838 CN201220138838U CN202578753U CN 202578753 U CN202578753 U CN 202578753U CN 201220138838 CN201220138838 CN 201220138838 CN 201220138838 U CN201220138838 U CN 201220138838U CN 202578753 U CN202578753 U CN 202578753U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- spiral steel
- spiral
- pipe
- gas
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Sink And Installation For Waste Water (AREA)
Abstract
The utility model relates to a gas draining pipe for coal mining. A thin-wall steel belt is taken as a raw material; a spiral steel pipe with a reinforcing rib is processed through a spiral duct machine; a seaming weld joint is welded at a seaming joint of the spiral steel pipe; flanges are welded at two ends of the spiral steel pipe; the surfaces of the flanges and the surface of the spiral steel pipe are subjected to rust removal; and anti-flaming anti-static epoxy coatings are coated on the surfaces of the flanges and the surface of the spiral steel pipe. The demands on light weight, gas-tightness and anti-flaming property of the gas draining pipe for coal mining are met; an anticorrosive demand is also met; and the labor intensity of workers is reduced.
Description
Technical field
The utility model relates to the gas drainage under suction pipe of using in a kind of colliery, reaches gas drainage under suction pipe in light weight, air tight, etch-proof.
Background technology
At present, known gas discharge in mine pipe has: the most frequently used common steel tube, in order to guarantee pipeline certain intensity is arranged, and steel pipe must have certain thickness, and steel pipe is heavy, is not easy to construction, and is perishable; Underground mine use glass fiber reinforced plastic gas releasing pipe, underground mine use polyvinyl gas drainage under suction pipe, underground mine use steel frame polyvinyl gas drainage under suction pipe etc.; These several kinds of pipelines not only exist weight heavier, the shortcoming that construction is inconvenient, and have great potential safety hazard, when under the coal mine during breaking out of fire, these several kinds of pipelines self can burn and so receive after can emit a large amount of toxic gases.
Summary of the invention
For the shortcoming that overcomes existing gas discharge in mine pipe Heavy Weight, leaks gas, is easy to corrode, the utility model provides a kind of gas drainage under suction pipe, not only can satisfy in light weight, air tight, self incombustible requirement, and can solve etch-proof requirement.
The utility model solves the technical scheme that its technical problem adopted: the gas drainage under suction pipe that a kind of colliery is used; It is characterized in that: use the thin-walled steel band to be raw material; Seaming forming technique through Spiral ducted unit; Process the spiral steel pipe that has reinforcing rib, reinforcing rib can play the effect of gaining in strength, and can satisfy lightweight requirement; In order to satisfy the gastight requirement of gas drainage under suction pipe, with the seam welding of electric welding machine with the reinforcing rib seaming; The welding flange at the two ends of said spiral steel pipe; With the above spiral steel pipe surface derusting that has welded flange, welded the seaming weld seam, the epoxy coating of surface-coated one deck flame-retardant and anti-static installs layer protecting film additional, plays corrosiveness.
Description of drawings
The gas drainage under suction pipe constructional drawing that Fig. 1 uses in the colliery.
Description of reference numerals
1 flange;
2 spiral steel pipes;
3 seaming weld seams
The specific embodiment
In Fig. 1, the gas drainage under suction pipe that a kind of colliery is used uses the thin-walled steel band to be raw material, through the seaming forming technique of Spiral ducted unit, the thin-walled steel band is processed the spiral steel pipe 2 that has reinforcing rib; Weld through electric welding machine at 2 seaming places with spiral steel pipe, welds out seaming weld seam 3; At spiral steel pipe 2 two ends welding flanges 1, prevent to leak gas in the use of gas drainage under suction pipe negative pressure exhausting; The gas drainage under suction pipe surfaces externally and internally rust cleaning of making above comprises flange 1 surface derusting, and the epoxy coating at surfaces externally and internally coating one deck flame-retardant and anti-static of flange and spiral steel pipe plays corrosiveness.
Technique effect
The beneficial effect of the utility model is that under the abominable condition of work, the gas drainage under suction pipe satisfies the requirement of Safety of Coal Mine Production, accomplishes in light weight, air tight, anticorrosion, reduces working strength of workers simultaneously under coal mine.
Claims (2)
1. the gas drainage under suction pipe that the colliery is used is characterized in that: use the thin-walled steel band to be raw material, have the spiral steel pipe of reinforcing rib through the spiral duct machining; The seaming weld seam is welded out in spiral steel pipe lock joint place;
The welding flange at the two ends of spiral steel pipe; With said flange surface and said spiral steel pipe surface derusting;
Epoxy coating at said flange surface and said spiral steel pipe surface-coated one deck flame-retardant and anti-static.
2. the gas drainage under suction pipe that colliery according to claim 1 is used, wherein the spiral steel pipe surface derusting comprises the inner surface and the external surface rust cleaning of spiral steel pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220138838 CN202578753U (en) | 2012-04-05 | 2012-04-05 | Gas draining pipe for coal mining |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220138838 CN202578753U (en) | 2012-04-05 | 2012-04-05 | Gas draining pipe for coal mining |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202578753U true CN202578753U (en) | 2012-12-05 |
Family
ID=47248174
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220138838 Expired - Fee Related CN202578753U (en) | 2012-04-05 | 2012-04-05 | Gas draining pipe for coal mining |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202578753U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104308475A (en) * | 2014-09-28 | 2015-01-28 | 山东联创管业有限公司 | Novel composite steel pipe manufacturing method for coal mine underground gas drainage |
CN115890153A (en) * | 2022-12-02 | 2023-04-04 | 山东金诚联创管业股份有限公司 | Manufacturing process of anticorrosive steel pipe |
-
2012
- 2012-04-05 CN CN 201220138838 patent/CN202578753U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104308475A (en) * | 2014-09-28 | 2015-01-28 | 山东联创管业有限公司 | Novel composite steel pipe manufacturing method for coal mine underground gas drainage |
CN115890153A (en) * | 2022-12-02 | 2023-04-04 | 山东金诚联创管业股份有限公司 | Manufacturing process of anticorrosive steel pipe |
CN115890153B (en) * | 2022-12-02 | 2024-02-06 | 山东金诚联创管业股份有限公司 | Manufacturing process of anti-corrosion steel pipe |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109084080B (en) | CSP pipeline prefabricating construction method | |
CN104405975A (en) | Steel pipe with bell and spigot joints | |
CN105058055A (en) | Manufacturing and installation method for built-in flange and air hose for building construction | |
CN103195988B (en) | Mineral methane gas drainage pipe and production method thereof | |
CN101694261B (en) | Internal repaired mouth construction process of internal coating pipeline | |
CN205938242U (en) | Double -wall pipe inner tube is to removable outer tube of interface welding seam department | |
CN103343844B (en) | A kind of bimetal composite gas extraction pipeline of coating and manufacture method thereof | |
CN202578753U (en) | Gas draining pipe for coal mining | |
CN105605364B (en) | Sealing clamp for pipe fitting and pipe fitting sealing method thereof | |
CN202195180U (en) | Stainless steel reinforcing rib spiral welded pipe | |
CN203176563U (en) | Enhancing type spiral continuous welding coating composite steel tube for underground coal mine | |
CN111981215A (en) | Large-diameter double-rubber-ring socket anticorrosive steel pipe and mounting method thereof | |
CN204278677U (en) | The wear-resistant reinforcement recovery layer of a kind of section tube | |
CN202152896U (en) | Plastic-pipe welding structure with steel frame | |
CN203336070U (en) | Bi-metal composite gas drainage pipeline with coating | |
CN212537891U (en) | Carbon steel flue/chimney lining stainless steel plate structure | |
CN210860276U (en) | Quick emergency device for pipeline | |
CN204547068U (en) | The hot-melting fixture of multiple tube is manufactured for metal tube plastic lining | |
CN204729797U (en) | High pressure resistant leakage proof metal sealing locked clip device formula major diameter pipeline connecting device | |
CN102853184A (en) | Movable joint type middle-high pressure pipeline connection part | |
CN202532040U (en) | A connecting structure for steel reinforced spirally wound polyethylene pipes used in underground coal mines | |
CN203585598U (en) | Mineral methane gas drainage pipe | |
CN201013402Y (en) | Special gas pumping pipe for coal mine | |
CN206842863U (en) | Vertical pipeline hanging apparatus applied to large-scale resource | |
CN204459499U (en) | Pipeline |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121205 Termination date: 20130405 |