CN202558503U - Rope guide device of tower-type crane hoist steel wire ropes - Google Patents
Rope guide device of tower-type crane hoist steel wire ropes Download PDFInfo
- Publication number
- CN202558503U CN202558503U CN2012202183821U CN201220218382U CN202558503U CN 202558503 U CN202558503 U CN 202558503U CN 2012202183821 U CN2012202183821 U CN 2012202183821U CN 201220218382 U CN201220218382 U CN 201220218382U CN 202558503 U CN202558503 U CN 202558503U
- Authority
- CN
- China
- Prior art keywords
- rope
- steel wire
- rope guide
- tower
- hoist
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model discloses a rope guide device of tower-type crane hoist steel wire ropes, wherein the rope guide device of tower-type crane hoist steel wire ropes comprises a hoist steel wire rope winding drum; the hoist steel wire rope winding drum and two pairs of mutually parallel rear rope guide seats are fixedly installed on an upper chord of a second balanced arm of a tower-type crane at certain intervals; a pulley support on the upper chord of the second balanced arm fxed on the tower-type crane consists of two vertical rods and diagonal draw bars articulated with one ends of the two vertical rods; the hoist steel wire rope winding drum and the rear rope guide seats are positioned between the two vertical rods and the two diagonal draw bars; the top end articulated connecting part of the sliding wheel support is provided with a fixed pulley; and the pulley shafts of the rear rope guide seats are provided with movable pulleys. The rope guide device of tower-type crane hoist steel wire ropes provided by the utility model guaratees the steel wire ropes to be ranked neatly on the winding drum, relieves the mutual extrusion of the steel wire ropes, reduces the abrasion and wire broken degree, prolongs the service life of the steel wire rope, and meanwhile excludes the risk caused by the fact that the steel wire ropes jump out of edges at two ends of the winding cylinder because of unsmooth rope guide maximally.
Description
Technical field
The utility model relates to the tower crane field, especially a kind of rope guide of tower crane hoist rope.
Background technology
Existing tower crane; (horizontal throw as between hoist rope reel and the back row's rope pulley axle is too little because the design of lifting mechanism rope guide is unreasonable; Be generally about 1.0m), the row who does not therefore the solve lifting mechanism well problem of restricting causes the hoist rope ordering of tower crane comparatively disorderly; Steel rope extruding mutually makes it rough sledding such as easy fracture of wire, scratch, distortion, distortion occur, causes steel rope to scrap in advance.This has not only brought economic loss to the user, and more serious is because the damage of steel rope possibly buried potential safety hazard.
The disorderly reason of steel rope ordering: when steel rope involved on reel or rolls out, there were an angle in the line of deflection sheave and reel rope stretching point and the vertical direction of spool axis, are called elevation angle.Elevation angle makes steel rope in row's rope process, except one perpendicular to the spool axis direction, steel rope is involved in or rolls out the effective pulling force, also have a horizontal force that is parallel to the spool axis direction.This horizontal force will act on the steel rope on the reel and the steel rope of waiting to be involved in or rolling out between, make between the steel rope and push, the row who the influences steel rope effect of restricting.This rope stretching angle is big more, and horizontal force is big more, and is big more to the row of the steel rope influence of restricting.In addition, this horizontal force also can act on deflection sheave, and steel rope meeting grazing pulley notch causes steel rope scratch or notch damage even takes off groove.
Summary of the invention
Existing tower crane; (horizontal throw as between hoist rope reel and the back row's rope pulley axle is too little because the design of lifting mechanism rope guide is unreasonable; Be generally about 1.0m), the row who does not therefore the solve lifting mechanism well problem of restricting causes the hoist rope ordering of tower crane comparatively disorderly; Steel rope extruding mutually makes it rough sledding such as easy fracture of wire, scratch, distortion, distortion occur, causes steel rope to scrap in advance.This has not only brought economic loss to the user, and more serious is because the damage of steel rope possibly buried potential safety hazard.
The disorderly reason of steel rope ordering: when steel rope involved on reel or rolls out, there were an angle in the line of deflection sheave and reel rope stretching point and the vertical direction of spool axis, are called elevation angle.Elevation angle makes steel rope in row's rope process, except one perpendicular to the spool axis direction, steel rope is involved in or rolls out the effective pulling force, also have a horizontal force that is parallel to the spool axis direction.This horizontal force will act on the steel rope on the reel and the steel rope of waiting to be involved in or rolling out between, make between the steel rope and push, the row who the influences steel rope effect of restricting.This rope stretching angle is big more, and horizontal force is big more, and is big more to the row of the steel rope influence of restricting.In addition, this horizontal force also can act on deflection sheave, and steel rope meeting grazing pulley notch causes steel rope scratch or notch damage even takes off groove.
Summary of the invention
The utility model technical matters to be solved provides a kind of rope guide of tower crane hoist rope; Guarantee steel rope marshalling on reel; Alleviate steel rope extruding each other; Reduce its wearing and tearing, fracture of wire degree, prolong the service life of steel rope, can not get rid of to greatest extent simultaneously because of row's rope does not freely cause steel rope and jump out the risk that limit, reel two ends flange brings.
For solving the problems of the technologies described above; The technical scheme that the utility model adopted is: a kind of rope guide of tower crane hoist rope; Comprise the hoist rope reel; The hoist rope reel and the two couples of back rows that the are parallel to each other seat of restricting keeps at a certain distance away on the top boom of the second joint equilibrium arm that is fixedly mounted on tower crane; Be fixed on tower crane second the joint equilibrium arm top boom on pulley bracket form by two vertical rods with two vertical rods, one end pivotally attached digonal link; Hoist rope reel and back row's rope seat are positioned between two vertical rods and the digonal link, and the place of being articulated and connected, top of pulley bracket is provided with fixed pulley, and the sheave shaft of back row's rope seat is provided with movable pulley.
Back row's rope seat is by forming through bearing pin bonded assembly U type ears panel seat and connecting panel, and the other end of connecting panel is provided with pin hole and a plurality of bolt hole.
The pin hole of connecting panel is provided with position-limited lever, and there is sheave shaft the end of connecting panel through bolted connection.
Horizontal throw between hoist rope reel and the sheave shaft is 6.5m ± 0.2m.
Owing to receive the restriction of tower machine equilibrium arm length, structure, cat head leading sheave, back deflection sheave, hoisting drum distance each other can not be provided with very greatly, if do not carry out the transformation of structure aspects, elevation angle is inevitable.Solve above-mentioned contradiction, the one, under the situation that the equilibrium arm arrangement condition allows, the distance between hoist rope reel and deflection sheave should be tried one's best greatly, makes elevation angle smaller as far as possible; The 2nd, deflection sheave is designed to traveling sheave, make it make axially reciprocating can be with the involving in or roll out of steel cable the time, further reduce elevation angle.
The rope guide of the tower crane hoist rope that the utility model provides, owing to adopt hoist rope reel, back row's rope seat and pulley bracket to match, on the row's rope seat of back, movable pulley being installed is deflection sheave; Under the situation that tower crane equilibrium arm arrangement condition allows, strengthened the horizontal throw between cable drum and deflection sheave, reduced the rope stretching angle; Make it make axially reciprocating can be with the involving in or roll out of steel cable the time; Also further reduce the rope stretching angle, therefore guaranteed steel rope marshalling on reel, alleviate steel rope extruding each other; Reduce its degree of wear; Prolong the life-span of steel rope, can not get rid of to greatest extent on the other hand because of row's rope does not freely cause steel rope and jump out the risk that limit, reel two ends flange brings, so just reduce the possibility that steel rope is scrapped; Thereby practiced thrift productive costs greatly, and improved equipment, safety of persons.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the utility model is described further:
Fig. 1 is the utility model structural representation;
Fig. 2 is the birds-eye view of the utility model;
Fig. 3 is the scheme drawing of row's rope seat behind the utility model;
Fig. 4 is that the A-A of Fig. 3 is to view.
The specific embodiment
Like Fig. 1, Fig. 2, Fig. 3 and shown in Figure 4; The utility model comprises hoist rope reel 1; The hoist rope reel 1 and the two couples of back rows that the are parallel to each other seat 2 of restricting keeps at a certain distance away on the top boom of the second joint equilibrium arm 9 that is fixedly mounted on tower crane; Be fixed on tower crane second the joint equilibrium arm 9 top boom on pulley bracket 3 form by two vertical rod 3-1 with two vertical rod 3-1, one end pivotally attached digonal link 3-2; Hoist rope reel 1 and back row's rope seat 2 are between two vertical rod 3-1 and digonal link 3-2, and the place of being articulated and connected, top of pulley bracket 3 is provided with fixed pulley 4, and the sheave shaft 7 of back row's rope seat 2 is provided with movable pulley 10.
Back row's rope seat 2 is by forming through bearing pin 2-3 bonded assembly U type ears panel seat 2-1 and connecting panel 2-2, and the other end of connecting panel 2-2 is provided with pin hole 5 and a plurality of bolts hole 6.
The pin hole 5 of connecting panel 2-2 is provided with position-limited lever 5-1, and there is sheave shaft 7 end of connecting panel 2-2 through bolted connection.
Horizontal throw between hoist rope reel 1 and the sheave shaft 7 is 6.5m ± 0.2m.
During work; Steel rope 8 on the hoist rope reel 1 passes movable pulley 10 successively, fixed pulley 4 backs are connected with the lifting hook pulley of first segment equilibrium arm 11 fwd crane arms; Make the front end of steel rope 8 finally be locked in the crane arm front end; Steel rope 8 is involving in or is rolling out in the process, and steel rope 8 advances at each pulley place or retreats, and drives the hoisting crane hook and realizes rising or down maneuver.
Hoist rope reel 1 is fixed on second of tower crane through fastener and saves on the top boom of equilibrium arm 9; The two couples of back rows that the are parallel to each other seat 2 of restricting is fixed on through fastener on the top boom of the second joint equilibrium arm 9 of tower crane; The bottom of pulley bracket 3 is separately fixed at second of tower crane through fastener and saves on the top boom of equilibrium arm 9.
The steel plate materials that back row's rope seat 2 adopts thickness to be not less than 2mm is made, and pulley bracket 3 adopts 20# I-beam section material to process.
Weld from both sides is adopted in the commissure, and the weldering height is not less than 6mm.
Sheave shaft 7 utilizes 4 cover M20 bolts to be installed on the connecting panel 2-2.
Claims (4)
1. the rope guide of a tower crane hoist rope; Comprise hoist rope reel (1); It is characterized in that: the hoist rope reel (1) and the two couples of back rows that the are parallel to each other seat (2) of restricting keeps at a certain distance away on the top boom of the second joint equilibrium arm (9) that is fixedly mounted on tower crane; Be fixed on tower crane second the joint equilibrium arm (9) top boom on pulley bracket (3) form by two vertical rods (3-1) with two vertical rods (3-1) end pivotally attached digonal link (3-2); Hoist rope reel (1) and back row's rope seat (2) are positioned between two vertical rods (3-1) and the digonal link (3-2); The place of being articulated and connected, top of pulley bracket (3) is provided with fixed pulley (4), and the sheave shaft (7) of back row's rope seat (2) is provided with movable pulley (10).
2. the rope guide of tower crane hoist rope according to claim 1; It is characterized in that: back row's rope seat (2) is by forming through bearing pin (2-3) bonded assembly U type ears panel seats (2-1) and connecting panel (2-2), and the other end of connecting panel (2-2) is provided with pin hole (5) and a plurality of bolt hole (6).
3. the rope guide of tower crane hoist rope according to claim 2 is characterized in that: the pin hole (5) of connecting panel (2-2) is provided with position-limited lever (5-1), and there is sheave shaft (7) end of connecting panel (2-2) through bolted connection.
4. the rope guide of tower crane hoist rope according to claim 1 is characterized in that: the horizontal throw between hoist rope reel (1) and the sheave shaft (7) is 6.5m ± 0.2m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012202183821U CN202558503U (en) | 2012-05-16 | 2012-05-16 | Rope guide device of tower-type crane hoist steel wire ropes |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012202183821U CN202558503U (en) | 2012-05-16 | 2012-05-16 | Rope guide device of tower-type crane hoist steel wire ropes |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202558503U true CN202558503U (en) | 2012-11-28 |
Family
ID=47208184
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012202183821U Expired - Fee Related CN202558503U (en) | 2012-05-16 | 2012-05-16 | Rope guide device of tower-type crane hoist steel wire ropes |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202558503U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104326377A (en) * | 2014-10-29 | 2015-02-04 | 徐州建机工程机械有限公司 | Integral-installation lifting rope-arranging structure of movable-arm tower type crane |
CN110713124A (en) * | 2019-11-22 | 2020-01-21 | 江苏徐工工程机械研究院有限公司 | Crane with a movable crane |
CN113998609A (en) * | 2021-10-22 | 2022-02-01 | 中建三局集团有限公司 | Steel frame lifting machine for hoisting plates |
-
2012
- 2012-05-16 CN CN2012202183821U patent/CN202558503U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104326377A (en) * | 2014-10-29 | 2015-02-04 | 徐州建机工程机械有限公司 | Integral-installation lifting rope-arranging structure of movable-arm tower type crane |
CN110713124A (en) * | 2019-11-22 | 2020-01-21 | 江苏徐工工程机械研究院有限公司 | Crane with a movable crane |
CN113998609A (en) * | 2021-10-22 | 2022-02-01 | 中建三局集团有限公司 | Steel frame lifting machine for hoisting plates |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206126684U (en) | Electric installation is got in automation of overhead wiping line | |
CN202558503U (en) | Rope guide device of tower-type crane hoist steel wire ropes | |
CN202379598U (en) | Lifting hook and lifting equipment | |
CN205998638U (en) | Fixture assembly and Material Transportation trailer | |
CN105174070B (en) | A kind of aluminium section bar special purpose crane provided with lift cart | |
CN2855992Y (en) | Towing rope bogie of tower crane | |
CN110386559B (en) | Bidirectional traction self-adaptive horse race system of cable hoisting system | |
CN106044574A (en) | Method for synchronously replacing gantry beam and steel wire ropes of ladle crane | |
CN201284191Y (en) | Rope bracketing trolley of tower crane | |
CN103922152B (en) | A kind of take out device with claw structure | |
CN203716562U (en) | Parking garage elevator | |
CN101920907B (en) | Main trolley of large shipbuilding portal crane | |
CN109132896B (en) | Auxiliary boom lifting device and crane | |
CN204873574U (en) | Hoist girder construction of stretching out and drawing back | |
CN103669940A (en) | Parking garage lifter | |
CN203728439U (en) | Walking gantry crane | |
CN205114879U (en) | Special hoist of aluminium alloy with lift dolly | |
CN109835833A (en) | It is a kind of for replacing the burnt tank repair apparatus of burnt pot bottom liner plate | |
CN102153017B (en) | Bridge crane trolley for mine | |
CN213033290U (en) | Automatic coiling system of blanking machine | |
CN202022668U (en) | Mine bridge crane | |
CN102229408A (en) | Bridge crane for mine | |
CN202343599U (en) | Inverted take-up device | |
CN208265189U (en) | A kind of profile steel stacker trolley cable running gear | |
CN202023178U (en) | Slantingly pulling two-way gantry hoist for dam body gate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121128 Termination date: 20200516 |