CN202539501U - Split type water jacket with river diversion water groove - Google Patents

Split type water jacket with river diversion water groove Download PDF

Info

Publication number
CN202539501U
CN202539501U CN2012200090019U CN201220009001U CN202539501U CN 202539501 U CN202539501 U CN 202539501U CN 2012200090019 U CN2012200090019 U CN 2012200090019U CN 201220009001 U CN201220009001 U CN 201220009001U CN 202539501 U CN202539501 U CN 202539501U
Authority
CN
China
Prior art keywords
water jacket
crystallizer
arc half
split type
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2012200090019U
Other languages
Chinese (zh)
Inventor
李富帅
陶金明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongye Continuous Casting Technology Engineering Co Ltd
CCTec Engineering Co Ltd
Original Assignee
Zhongye Continuous Casting Technology Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongye Continuous Casting Technology Engineering Co Ltd filed Critical Zhongye Continuous Casting Technology Engineering Co Ltd
Priority to CN2012200090019U priority Critical patent/CN202539501U/en
Application granted granted Critical
Publication of CN202539501U publication Critical patent/CN202539501U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The utility model provides a split type water jacket with a river diversion water groove, which is a river diversion water jacket surrounding outside a crystallizer copper pipe. The split type water jacket with the river diversion water groove comprises an inner arc half water sleeve, an outer arc half water sleeve, sealing elements, a fastening piece and a positioning pin; a gap between the split type water jacket with the river diversion water groove and a crystallizer barrel is sealed by one sealing element; a water inlet tank and a water outlet tank of the crystallizer barrel are separated by another sealing element; a clamping ring is arranged at the upper end of the crystallizer copper pipe; and a crystallizer upper cover is arranged at the upper part of a clamping ring. The split type water jacket with the river diversion water groove is characterized in that the inner arc half water sleeve and the outer arc half water sleeve are two separated bodies by taking a center line of the crystallizer barrel as a dividing line; the inner arc half water sleeve and the outer arc half water sleeve are fixedly connected with each other through a fastening piece and a positioning pin; and the sealing element is arranged between the split type water jacket with the river diversion water groove and the crystallizer copper pipe. According to the split type water jacket with the river diversion water groove provided by the utility model, the manufacturing precision of a crystallizer of a continuous casting machine is ensured on a mechanical structure, so that the problem that an arc circular center of the copper pipe and the center of the casting machine are bias is avoided; and meanwhile, the purpose of cooling control can be realized.

Description

The water jacket of split type band diversion flume
Technical field
The utility model relates to a kind of water jacket of split type band diversion flume, is specially the water jacket that is used for efficient billet caster crystallizer of metallurgy industry, belongs to the metallurgical continuous casting technical field.
Background technology
Crystallizer is the critical component of conticaster; By copper pipe, be coated on parts such as the outside water conservancy diversion water sleeve of copper pipe magnetic stirrer and form; The crystallizer of billet caster for guaranteeing molten steel even shape shell in crystallizer, and reaches certain shell thickness in the crystallizer exit position under the condition of high pulling rate; Require to reach the bight cooling evenly around the crystallizer, and have enough cooling effectiveness.In the known crystallizer; Its copper pipe is to be formed through specially designed plug and external mold extruding drawing by the heavy wall copper pipe; After the completion of extruding drawing procedure, withdrawing from plug, the residual stress reason of crystallizer copper pipe because of eliminating causes arc radius to change; Even the copper pipe that same set of die production goes out, its arc diameter changes difference even reaches more than 1 meter.
On the other hand, existing crystallizer copper pipe is directly to link to each other with the crystallizer cylindrical shell, and the upper surface of junction crystallizer and draw-in groove are to locate through the profile circular arc of copper pipe; The variation of copper pipe radian after moulding is often ignored by manufacturer, and being defaulted as is the circular arc of design, therefore; In case big variation takes place circular arc, will cause the center of circle of copper pipe circular arc and casting machine center that bigger deviation takes place, when casting machine is produced with high pulling rate; Be easy to cause base shell growth inhomogeneous, even problem such as bleed-out.
After known crystallizer water conservancy diversion water jacket is the corrosion resistant plate punch forming; Be welded; Because dimensional accuracy is difficult to guarantee in the process, the water seam non-uniform phenomenon in the work between water conservancy diversion water jacket and the crystallizer copper pipe very easily takes place, and directly causes the growth of base shell inhomogeneous.Chinese invention patent " cooling water forms the method and the crystallizer of turbulent flow in a kind of continuous cast mold " (application number: 200810079470.6 applyings date: 2008-09-25) disclosed turbulence type cooling water continuous cast mold; Forming rough water seam in the work between water jacket and the crystallizer outer surface makes cooling water flow with turbulence form; Strengthened the cooling water heat exchange effect; Its weak point is the uniformity consistency that this structure can not be guaranteed water seam between water jacket and the copper pipe, thereby the turbulent flow inequality occurs; (application number: 200920105634.8 applyings date: 2009-02-04) disclosed is to be provided with a plurality of gap adjustment parts between inner water sleeve and the copper pipe to utility model patent " arc tube type mold "; Its weak point is in the actual use; When water seam inequality occurring; Regulate difficulty, the adjusting of passing through that can not be strict realizes water seam uniformity.
Summary of the invention
The purpose of the utility model is the problem to background technology proposed; A kind of water jacket of split type band diversion flume is provided; Be assembled into by inside and outside arc half water sleeve seal, securing member, alignment pin, water jacket is to be two splits of cut-off rule with crystallizer cylindrical shell center line, and what separate simultaneously is water jacket inner lead, bight water channel, side and cambered surface water channel; Guaranteed the controllability of cooling water seam from frame for movement; Can avoid the center of circle and the casting machine center of copper pipe circular arc that deviation takes place, help improving water seam heat exchange effect, reduce the production run cost.
The technical scheme of the utility model is: the water jacket of split type band diversion flume is to be enclosed in the outside water conservancy diversion water jacket of crystallizer copper pipe, comprises inner arc half water jacket, outer arc half water jacket, seal, securing member and alignment pin; There is the seal sealing in gap between the water jacket of described split type band diversion flume and the crystallizer cylindrical shell; Also there is seal to separate between the inlet water tank of crystallizer cylindrical shell and the water tank; There is snap ring the crystallizer copper pipe upper end; Snap ring top is the crystallizer loam cake, it is characterized in that: described inner arc half water jacket and outer arc half water jacket are to be two splits of cut-off rule with crystallizer cylindrical shell center line, are connected through securing member and alignment pin between inner arc half water jacket and outer arc half water jacket; Between the water jacket of split type band diversion flume and the crystallizer copper pipe seal is arranged.Its beneficial effect is: through seal the inlet water tank and the water tank of crystallizer cylindrical shell are cut apart; The crystallizer copper pipe upper end is through snap ring and crystallizer loam cake restriction upper and lower displacement; Crystallizer copper pipe is circumferentially surrounded by split type band tank water conservancy diversion water jacket and through fastener bolt crystallizer copper pipe and split type band tank water conservancy diversion water jacket is fitted tightly, and guarantees the consistent of crystallizer copper pipe profile radian and water jacket inner chamber groove face radian from structure.
The water jacket of aforesaid split type band diversion flume is characterized in that: on the inner chamber of described inner arc half water jacket and outer arc half water jacket, being processed with five given depths and equally distributed vertical rib at least, promptly is diversion flume between adjacent two ribs.Its beneficial effect is: described rib will be separated along the cooling-water duct of the circumferential diverse location of water jacket inner chamber; Form a plurality of diversion flumes; And bight aquaporin and side and cambered surface aquaporin also separated, help cooling water and flow by set path, improve water seam heat exchange effect.
The water jacket of aforesaid split type band diversion flume is characterized in that: the upper end of described inner arc half water jacket and outer arc half water jacket has delivery port, two ends have water inlet down.Its beneficial effect is: through control intake-outlet flow size, reach the effect of scalable cooling water inflow.
The water jacket of aforesaid split type band diversion flume is characterized in that: described inner arc half water jacket and the outer arc half water jacket outside are evenly distributed with crisscross gusset.Its beneficial effect is: can guarantee that split type band tank water conservancy diversion water jacket itself has enough big rigidity with respect to the thin-walled mould copper pipe, can control the distortion of copper pipe on the structure.
The beneficial effect of the utility model is: (1) can guarantee the accuracy of manufacture of conticaster crystallizer from frame for movement; Avoid occurring the center of circle and the casting machine centre deviation problem of copper pipe circular arc; Simultaneously can reach the control cooling purpose, thereby guarantee casting machine steady production under high pulling rate; (2) can make the crystallizer copper pipe of thin-walled press close to solidified shell through regulating hydraulic pressure, reduce the air gap between base shell and the copper pipe, increase the heat exchange effect of crystallizer; (3) because frame for movement has guaranteed the controllability of cooling water seam, can design narrower water seam and improve the heat exchange effect, perhaps reduce the crystallizer water yield, reduce the production run cost; (4) reduced the wall thickness of crystallizer copper pipe significantly; Not only reduced the manufacturing cost of single copper pipe; Because the assurance of dimensional accuracy has reduced the wearing and tearing of copper pipe, can also improve the service life of single copper pipe simultaneously; Thereby reduce the maintenance cost of spare part significantly, and can improve the production efficiency of casting machine and the stability of product quality effectively.
Description of drawings
Accompanying drawing 1 is the utility model example structure sketch map;
Accompanying drawing 2 is the vertical view of accompanying drawing 1;
Accompanying drawing 3 be in the accompanying drawing 1 B-B to cutaway view;
Accompanying drawing 4 is a C place enlarged drawing in the accompanying drawing 3;
Accompanying drawing 5 is accompanying drawing 1 left side and half sectional view;
Accompanying drawing 6 is accompanying drawing 1 cutaway view;
The typical component assembling sketch map of accompanying drawing 7 for being associated with the utility model water jacket on the conticaster crystallizer;
Accompanying drawing 8 is an A place enlarged drawing in the accompanying drawing 7.
The specific embodiment
The utility model embodiment is further specified the mark in the accompanying drawing below in conjunction with accompanying drawing: in accompanying drawing 1~accompanying drawing 4,1-inner arc, half water jacket, 2-outer arc, half water jacket, 3-seal, 4-securing member, 5-alignment pin; 6-tank, 7-water inlet, 8-delivery port, 9-gusset.10-draw-in groove, 11-positioning step; In accompanying drawing 7~accompanying drawing 8,12-seal I, 13-crystallizer cylindrical shell, 14-water jacket, 15-crystallizer copper pipe, 16-securing member, 17-loam cake, 18-snap ring I, 19-seal II, 20-seal III, 21-snap ring II, 22-seal IV.
With reference to accompanying drawing 1~accompanying drawing 4 and accompanying drawing 7 and accompanying drawing 8, the water jacket 14 of the split type band diversion flume of the utility model is to be enclosed in the outside water conservancy diversion water jacket 14 of crystallizer copper pipe 15, comprises inner arc half water jacket 1, outer arc half water jacket 2, seal, securing member and alignment pin 5; There are 19 sealings of seal II in gap between water jacket 14 and the crystallizer cylindrical shell 13; Also there is the seal I to open in 12 minutes between the inlet water tank of crystallizer cylindrical shell 13 and the water tank; There is snap ring II 21 crystallizer copper pipe 15 upper ends; The cylindrical of snap ring II 21 is positioned at water jacket 14 upper end positioning steps 11 places, water jacket 14, crystallizer copper pipe, between loam cake 17 threes on copper pipe top, seal III 20 is arranged, and inner arc half water jacket 1 is cut-off rule with outer arc half water jacket 2 with crystallizer cylindrical shell center line; Form two arc splits, be connected through securing member 4 and alignment pin 5 between inner arc half water jacket 1 and outer arc half water jacket 2; But snap ring II 21 and 15 upper and lower displacements of crystallizer loam cake 17 limiting crystal device copper pipes; Crystallizer copper pipe 15 is circumferentially surrounded by water jacket 14 and through fastener bolt 4 crystallizer copper pipe 15 and water jacket 14 is fitted tightly, and guarantees the consistent of crystallizer copper pipe 15 profile radians and water jacket 14 inner chamber groove face radians from structure.
Shown in accompanying drawing 1~accompanying drawing 6, the outside of inner arc half water jacket 1 and outer arc half water jacket 2 is evenly distributed with crisscross gusset 9; On the inner chamber of inner arc half water jacket 1 and outer arc half water jacket 2, being processed with a plurality of given depths and equally distributed vertical rib, promptly is diversion flume 6 between adjacent two ribs; The upper end of inner arc half water jacket 1 and outer arc half water jacket 2 has delivery port 8, two ends have water inlet 7 down; Because rib will be separated along the cooling-water duct of the circumferential diverse location of water jacket inner chamber, form a plurality of diversion flumes, and bight aquaporin and side and cambered surface aquaporin are also separated; Therefore help cooling water and flow, improve water seam heat exchange effect by set path.On the other hand, can also reach the effect of scalable cooling water inflow through the flow size of control water inlet 7 and delivery port 8.Be evenly distributed with crisscross gusset, can guarantee that split type band tank water conservancy diversion water jacket itself has enough big rigidity with respect to the thin-walled mould copper pipe, can control the distortion of copper pipe on the structure.
The water jacket assemble method of the split type band diversion flume of the utility model is:
(1) inner arc half water jacket and outer arc half water jacket are made up by inner cavity size that designs and appearance and size; During combination between inner arc half water jacket and outer arc half water jacket on the faying face; Add the pad of setting thickness in advance; Make the water jacket inner chamber be combined into to cooperate with given crystallizer copper pipe appearance and size in the design drawing, water jacket upper outside draw-in groove cooperates with the crystallizer cylindrical shell through snap ring I 18, locatees through snap ring II 21 between water jacket positioning step 11 and the crystallizer copper pipe 15 to cooperate;
(2) the water jacket integral body that combines is processed, remove pad after processing;
(3) inner arc that processes half water sleeve outer arc half water jacket is assembled in the crystallizer, place sealing strip 3 between inner arc half water jacket 1 and outer arc half water jacket 2 faying faces after, again with alignment pin 5 location, and to pass through fastener bolt 4 fastening.
Can find out that from the utility model embodiment crystallizer copper pipe is directly with after water jacket is connected to link to each other with the crystallizer cylindrical shell again, between copper pipe and the water jacket snap ring is arranged; Snap ring is also arranged between water jacket and the cylindrical shell, also have the seal sealing, because there is the reinforcement gusset water jacket outside; Two and half arcs are removable 3 when processing and installation; Sufficient intensity is arranged after the assembling, can guarantee that crystallizer copper pipe can not be out of shape, the water seam between water jacket and the copper pipe is because of the directional guide effect of diversion flume; Make the even directed flow of cooling water, thereby guarantee casting machine steady production under high pulling rate; Can also make the crystallizer copper pipe of thin-walled press close to solidified shell through regulating hydraulic pressure, reduce the air gap between base shell and the copper pipe, increase the heat exchange effect of crystallizer; Or the narrower water seam raising heat exchange effect of design, also can adopt more thin-wall copper pipe, reduce the copper pipe manufacturing cost, improve the service life of copper pipe, reduce the maintenance cost of spare part, the safety in production when helping casting machine with high pulling rate.

Claims (4)

1. the water jacket of split type band diversion flume is to be enclosed in the outside water conservancy diversion water jacket of crystallizer copper pipe, comprises inner arc half water jacket, outer arc half water jacket, seal, securing member and alignment pin; There is the seal sealing in gap between the water jacket of described split type band diversion flume and the crystallizer cylindrical shell; Also there is seal to separate between the inlet water tank of crystallizer cylindrical shell and the water tank; There is snap ring the crystallizer copper pipe upper end; Snap ring top is the crystallizer loam cake, it is characterized in that: described inner arc half water jacket and outer arc half water jacket are to be two splits of cut-off rule with crystallizer cylindrical shell center line, are connected through securing member and alignment pin between inner arc half water jacket and outer arc half water jacket; Between the water jacket of split type band diversion flume and the crystallizer copper pipe seal is arranged.
2. the water jacket of split type band diversion flume as claimed in claim 1; It is characterized in that: on the inner chamber of described inner arc half water jacket and outer arc half water jacket; At least being processed with five given depths and equally distributed vertical rib, promptly is diversion flume between adjacent two ribs.
3. the water jacket of split type band diversion flume as claimed in claim 1 is characterized in that: the upper end of described inner arc half water jacket and outer arc half water jacket has delivery port, two ends have water inlet down.
4. the water jacket of split type band diversion flume as claimed in claim 1 is characterized in that: described inner arc half water jacket and the outer arc half water jacket outside are evenly distributed with crisscross gusset.
CN2012200090019U 2012-01-06 2012-01-06 Split type water jacket with river diversion water groove Expired - Lifetime CN202539501U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012200090019U CN202539501U (en) 2012-01-06 2012-01-06 Split type water jacket with river diversion water groove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012200090019U CN202539501U (en) 2012-01-06 2012-01-06 Split type water jacket with river diversion water groove

Publications (1)

Publication Number Publication Date
CN202539501U true CN202539501U (en) 2012-11-21

Family

ID=47160191

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012200090019U Expired - Lifetime CN202539501U (en) 2012-01-06 2012-01-06 Split type water jacket with river diversion water groove

Country Status (1)

Country Link
CN (1) CN202539501U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102554153A (en) * 2012-01-06 2012-07-11 中冶连铸技术工程股份有限公司 Split type water jacket with diversion water tank and assembly method
CN109894584A (en) * 2019-03-14 2019-06-18 佛山市科立天源冶金技术有限公司 A kind of aluminium alloy pole casting and forming device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102554153A (en) * 2012-01-06 2012-07-11 中冶连铸技术工程股份有限公司 Split type water jacket with diversion water tank and assembly method
CN109894584A (en) * 2019-03-14 2019-06-18 佛山市科立天源冶金技术有限公司 A kind of aluminium alloy pole casting and forming device
CN109894584B (en) * 2019-03-14 2024-04-19 广东科立工业技术股份有限公司 Aluminum alloy round bar casting forming device

Similar Documents

Publication Publication Date Title
CN102554153A (en) Split type water jacket with diversion water tank and assembly method
CN202539501U (en) Split type water jacket with river diversion water groove
CN202291315U (en) Fixed water slot type continuous casting mold
CN105499535A (en) Pouring system for die casting of tensioning wheels
CN201982524U (en) Water-cooling bearing base
CN202667576U (en) Crystallizer with spilt type water jacket
CN201702333U (en) Cast tube crystallizer
CN105081230A (en) Annular casting mold
CN201906804U (en) Continuous-casting tube type crystallizer
CN106424614B (en) A kind of fourplatemold water jacket processing method
CN214133926U (en) Special-shaped structural part casting die
CN211334414U (en) Mold for producing funnel
CN202479471U (en) Die-casting mould with whole charging barrel
CN201552746U (en) Film cooling water ring provided with ring-shaped groove
CN215786619U (en) Copper casting blank crystallizer
CN215879809U (en) Electric chafing dish aluminium die casting die
CN211334382U (en) Runner plate waterway system of thermosetting material mold
CN214867166U (en) Cooling insert
KR100738997B1 (en) Mold cooling device
CN108380840A (en) The fast cooling shaping of copper-base catalyst alloy is circumferentially positioned to pour mold
CN213559750U (en) Water-through mold assembly
CN102615505A (en) Method and device for pneumatic bulging after head casting
CN209753977U (en) Die-casting die adopting central cooling mandrel
CN216126528U (en) Large-flow high-speed crystallizer device for horizontal continuous casting copper pipe blank
CN202155492U (en) Precise high-accuracy cast large round blank water jacket

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20121121

CX01 Expiry of patent term