CN202520383U - Tunnel crossing construction disturbance grading early warning system in power tunnel - Google Patents

Tunnel crossing construction disturbance grading early warning system in power tunnel Download PDF

Info

Publication number
CN202520383U
CN202520383U CN201220123809XU CN201220123809U CN202520383U CN 202520383 U CN202520383 U CN 202520383U CN 201220123809X U CN201220123809X U CN 201220123809XU CN 201220123809 U CN201220123809 U CN 201220123809U CN 202520383 U CN202520383 U CN 202520383U
Authority
CN
China
Prior art keywords
tunnel
unit
displacement
information
disturbance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201220123809XU
Other languages
Chinese (zh)
Inventor
高小庆
杨文威
陆小龙
何真珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiulong Electric Power Technology Co Ltd
Shanghai Municipal Electric Power Co
Original Assignee
Shanghai Jiulong Electric Power Technology Co Ltd
Shanghai Municipal Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiulong Electric Power Technology Co Ltd, Shanghai Municipal Electric Power Co filed Critical Shanghai Jiulong Electric Power Technology Co Ltd
Priority to CN201220123809XU priority Critical patent/CN202520383U/en
Application granted granted Critical
Publication of CN202520383U publication Critical patent/CN202520383U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model relates to a tunnel crossing construction disturbance grading early warning system in a power tunnel. The tunnel crossing construction disturbance grading early warning system comprises a displacement sensor, a display unit, a processing unit, a value setting unit and a warning unit, the displacement sensor is mounted on the top of the tunnel and used for detecting displacement information of a detected position, the display unit is used for displaying the displacement information, the processing unit is used for forecasting the displacement information of the top of the tunnel and judging a safe state of the top of the tunnel, the value setting unit sets the information, the warning unit is used for giving an alarm for the displacement information and/or a dangerous state, and the processing unit is respectively connected with the displacement sensor, the display unit, the value setting unit and the warning unit. Compared with the prior art, the tunnel crossing construction disturbance grading early warning system has the advantages of convenience, instantaneity, accuracy, reliability and the like.

Description

A kind of electric power tunnel passes through constructing tunnel disturbance grading forewarning system system
Technical field
The utility model relates to a kind of cable and uses support, especially relates to a kind of electric power tunnel and passes through constructing tunnel disturbance grading forewarning system system.
Background technology
Along with the carrying out of China's infrastructure, the underground construction of every profession and trades such as water conservancy, traffic, mine, building is just in the ascendant.Especially the high speed development of the construction of subway all cable need be installed in the tunnel under a lot of situation, and situation is complicated in the tunnel, especially being in complex geological conditions such as zone of fracture and weak band, the landslide accident takes place easily.Shield machine is installed the displacement monitoring on ground and the forecast of landslide seems extremely important to it in without the soft soil layer of reinforcing closely in the traversing operation during subway tunnel.Traditional displacement generally removes to read displacement data through manual regular; Analyze by the technician then; The possibility of on the one hand abominable geological conditions and landslide has very big danger for reading the survey personnel, and the poem of data is got with analysis and had certain hysteresis quality on the other hand.The problems referred to above are unfavorable for guaranteeing tunnel and personnel's safety, cause the accident easily.
Summary of the invention
The purpose of the utility model is exactly to provide a kind of convenience immediately, electric power tunnel passes through constructing tunnel disturbance grading forewarning system system accurately and reliably in order to overcome the defective that above-mentioned prior art exists.
The purpose of the utility model can realize through following technical scheme: a kind of electric power tunnel passes through constructing tunnel disturbance grading forewarning system system, it is characterized in that, comprising:
Be installed in the displacement transducer that tunnel top detects detection position top offset information,
Be used to show the display unit of displacement information,
Be used for processing unit that the tunnel top displacement information is predicted and its safe condition is judged,
The setting value unit of set information,
Be used for caution unit to displacement information and/or precarious position warning;
Described processing unit connects displacement transducer respectively, display unit, setting value unit and caution unit.
Described displacement transducer is through signal transmitting device connection processing unit.
Described caution unit comprises language output unit and warning lamp output unit.
Compared with prior art, the utility model can detect tunnel internal strain data by automatic on-line, and through deformation data is analyzed and calculated, realizes online automatic monitoring forecast, and reaction is instant, accurately and reliably.
Description of drawings
Fig. 1 is the structural representation of the utility model.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the utility model is elaborated.
Embodiment 1
As shown in Figure 1, a kind of electric power tunnel passes through constructing tunnel disturbance grading forewarning system system, comprising:
Be installed in the displacement transducer 1 that tunnel top detects detection position top offset information,
Be used to show the display unit 5 of displacement information,
Be used for processing unit 3 that the tunnel top displacement information is predicted and its safe condition is judged,
The setting value unit 4 of set information,
Be used for the caution unit to displacement information and/or precarious position warning, the caution unit comprises language output unit 6 and warning lamp output unit 7;
Described processing unit connects displacement transducer respectively, display unit 5, setting value unit 4 and caution unit.Described displacement transducer 1 is through signal transmitting device 2 connection processing unit 3.
Shield machine in without the soft soil layer of reinforcing closely in the traversing operation during subway tunnel line security normally run requirement:
The horizontal discrepancy in elevation≤the 2mm of two tracks in a, the tunnel
B, rail are to deviation and difference of height<2mm/10m (being lateral variation sedimentation<1.4 ‰)
C, malformation control require: vertical sedimentation of tunnel structure and protuberance≤± 5mm
D, the displacement of tunnel structure vertical equity :≤± 5mm
E, tunnel convergence value<20mm
Report to the police when monitor value surpasses total deformation 1/2, and take emergency measures.

Claims (3)

1. an electric power tunnel passes through constructing tunnel disturbance grading forewarning system system, it is characterized in that, comprising:
Be installed in the displacement transducer that tunnel top detects detection position top offset information,
Be used to show the display unit of displacement information,
Be used for processing unit that the tunnel top displacement information is predicted and its safe condition is judged,
The setting value unit of set information,
Be used for caution unit to displacement information and/or precarious position warning;
Described processing unit connects displacement transducer respectively, display unit, setting value unit and caution unit.
2. a kind of electric power tunnel according to claim 1 passes through constructing tunnel disturbance grading forewarning system system, it is characterized in that, described displacement transducer is through signal transmitting device connection processing unit.
3. a kind of electric power tunnel according to claim 1 passes through constructing tunnel disturbance grading forewarning system system, it is characterized in that, described caution unit comprises language output unit and warning lamp output unit.
CN201220123809XU 2012-03-28 2012-03-28 Tunnel crossing construction disturbance grading early warning system in power tunnel Expired - Lifetime CN202520383U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220123809XU CN202520383U (en) 2012-03-28 2012-03-28 Tunnel crossing construction disturbance grading early warning system in power tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220123809XU CN202520383U (en) 2012-03-28 2012-03-28 Tunnel crossing construction disturbance grading early warning system in power tunnel

Publications (1)

Publication Number Publication Date
CN202520383U true CN202520383U (en) 2012-11-07

Family

ID=47103336

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220123809XU Expired - Lifetime CN202520383U (en) 2012-03-28 2012-03-28 Tunnel crossing construction disturbance grading early warning system in power tunnel

Country Status (1)

Country Link
CN (1) CN202520383U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103422867A (en) * 2013-08-21 2013-12-04 国家电网公司 Tunnel construction perturbation control method based on digitization
CN109278053A (en) * 2018-09-30 2019-01-29 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of railway tunnel detection method
CN112983441A (en) * 2021-02-24 2021-06-18 中铁六局集团有限公司交通工程分公司 Construction method for super-close side-crossing existing operation subway line

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103422867A (en) * 2013-08-21 2013-12-04 国家电网公司 Tunnel construction perturbation control method based on digitization
CN103422867B (en) * 2013-08-21 2016-08-31 国家电网公司 A kind of based on digitized tunnel construction perturbation control method
CN109278053A (en) * 2018-09-30 2019-01-29 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of railway tunnel detection method
CN109278053B (en) * 2018-09-30 2022-02-08 中国铁道科学研究院集团有限公司铁道建筑研究所 Railway tunnel operation state detection and monitoring method
CN112983441A (en) * 2021-02-24 2021-06-18 中铁六局集团有限公司交通工程分公司 Construction method for super-close side-crossing existing operation subway line

Similar Documents

Publication Publication Date Title
RU2630334C2 (en) System of dynamic controlling roof-based separation based on fiber grating and method of preliminary alert
CN103528530B (en) A kind of mining optical fiber grating roof abscission layer monitoring device and monitoring method
CN203283810U (en) Underground belt conveyor detecting system based on image processing technique
CN101363824B (en) Device for real time monitoring mine roof rock formation or concrete structure stability
CN202520383U (en) Tunnel crossing construction disturbance grading early warning system in power tunnel
CN103257009A (en) Working face mine pressure on-line monitoring system based on fiber grating sensing
CN103453892A (en) Bridge crack real-time monitoring and quick pre-warning device
CN202560325U (en) Underground multiple-data monitor system for coal mine
CN104374466B (en) Optical fiber vibration real-time monitoring and alarming system for roadbed collapse
CN205076726U (en) Tower machine lifting hook height measurement system and have its tower machine
CN104216365A (en) Cloud-based remote tunnel surrounding rock displacement monitoring and warning system
CN204368189U (en) Based on the railway foreign body intrusion monitoring system of fiber-optic grating sensor closed loop
CN102183322A (en) A method for detecting coal mine roof stress in real time and predetermining roof caving
CN102721406B (en) Construction beam gesture monitoring system
CN207060073U (en) A kind of railroad train is close to prior-warning device
CN202296926U (en) Intelligent inclination-preventing monitoring system for tower crane
CN205977278U (en) Judge device of tunnel stability
CN201989811U (en) Construction safety protection alarm device
CN203065039U (en) Metal structure health monitoring system of crane
CN201503423U (en) Device for performing real-time monitoring on dynamic stability of concrete structure
CN204346572U (en) Subgrade Subsidence fiber-optic vibration Real-Time Monitoring and warning system
CN204694666U (en) The step test instrument of reinforcing bar coaxial cable structure one dimension concrete health monitoring
CN204988570U (en) Building stress monitoring device
CN204368188U (en) Infrared detector railway crossing warning device
CN211651761U (en) Mud liquid level measuring and alarming device during geological core drilling

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20121107