CN202487453U - Monitoring device for opening and closing of high-voltage isolating switch - Google Patents

Monitoring device for opening and closing of high-voltage isolating switch Download PDF

Info

Publication number
CN202487453U
CN202487453U CN2012200579985U CN201220057998U CN202487453U CN 202487453 U CN202487453 U CN 202487453U CN 2012200579985 U CN2012200579985 U CN 2012200579985U CN 201220057998 U CN201220057998 U CN 201220057998U CN 202487453 U CN202487453 U CN 202487453U
Authority
CN
China
Prior art keywords
circuit
closing
opening
monitoring device
isolating switch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012200579985U
Other languages
Chinese (zh)
Inventor
张国灿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Quanzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2012200579985U priority Critical patent/CN202487453U/en
Application granted granted Critical
Publication of CN202487453U publication Critical patent/CN202487453U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model relates to the field of electrical devices, in particular to a monitoring device for opening and closing of a high-voltage isolating switch. The monitoring device for the opening and the closing of the high-voltage isolating switch are formed by a control circuit, and the control circuit is composed of a radiating circuit and a receiving circuit. The radiating circuit is formed by a start button, an intermediate relay KM, a stop button and an infrared sensing reflector in sequence. The receiving circuit is formed by an opening signal circuit and a closing signal circuit. A direct-current power supply provides electricity for the circuit. The monitoring device for the opening and the closing of the high-voltage isolating switch can effectively monitor the opening and the closing of the high-voltage isolating switch, achieves state visualization the high-voltage isolating switch, provides reliable and effective opening and closing signals, and enables accuracy to reach 99% and failure rate to almost reach zero, and as laser light is used for an emission source, the monitoring device for the opening and the closing of the high-voltage isolating switch has the advantages of being powerful in anti-interference, good in stability, strong in penetrability, and suitable for external environment, thereby meeting requirements for the state visualization of equipment in a smart substation.

Description

High voltage isolator divide-shut brake monitoring device
Technical field
The utility model relates to the electric device field, is specifically related to high voltage isolator divide-shut brake monitoring device.
Background technology
Intelligent transformer station is the demand of combined with intelligent electrical network; Automation of transformation substations technology is enriched to realize the intelligent substation function; Intelligent transformer station is intelligent grid operation and the key of controlling; As the key that is connected intelligent grid generating, transmission of electricity, power transformation, distribution, electricity consumption and scheduling six big links, intelligent transformer station be voltage of transformation in the intelligent grid, acceptance and distribution electric energy, control flow of power to the important electric power facility of adjustment voltage, be that intelligent grid " flow of power, information flow, Business Stream " three flows the focus of compiling; Has very important effect to building strong intelligent grid; Whether a present main equipment isolating switch reaches state can't be realized function visual and supervision, situation that can not comprehensive observation isolating switch location status, and therefore must set up the video camera of different azimuth more; Owing to receive the interference of magnetic field and environment, do not reach the requirement of intelligent power transformation simultaneously.
Summary of the invention
The purpose of the utility model provides high voltage isolator divide-shut brake monitoring device, keeps watch on high voltage isolator divide-shut brake position, for realizing that the high voltage isolator status visualization provides reliably, effective divide-shut brake position signalling.
High voltage isolator divide-shut brake monitoring device is made up of control circuit; Said this control circuit is made up of radiating circuit and receiving circuit; Said radiating circuit is made up of start button, auxiliary relay KM, stop button, infrared induction reflector successively; Said receiving circuit is made up of separating brake position signal circuit and the parallel connection of closing position signal circuit, and said circuit is by DC power supply.
The contact KM-1 of said auxiliary relay, KM-3 are normal opened contact; The contact KM-2 of said auxiliary relay KM, KM-4 are normal opened contact; After start button starts; The contact KM-1 of auxiliary relay KM, KM-3 closed communicating, the contact KM-2 of auxiliary relay KM, KM-4 closed communicating, the infrared induction reflector transmits.
Said separating brake position signal circuit is made up of intermediate relay ZJ, green light successively; Said closing position signal circuit is in series by intermediate relay ZJ, stop button, red light, infrared reception inducing receiver successively, and the normally closed contact ZJ-2 of said green light, intermediate relay ZJ, ZJ-4 are communicated to zero line.
Said infrared induction reflector and infrared reception inducing receiver are installed on the rotation position of end link under the isolating switch porcelain vase respectively; When combined floodgate puts in place; Reflector and receiver are located along the same line, and the infrared ray that receiver is received reflector promptly sends switching signal, during separating brake; Infrared induction reflector and infrared reception inducing receiver stagger, and receiver does not receive infrared ray and promptly sends sub-gate signal.
Owing to be provided with said structure; This monitoring device can keep watch on effectively that high voltage isolator divide-shut brake position realizes the high voltage isolator state visually provides reliable, effective divide-shut brake position signalling; Accuracy up to 99%, failure rate is almost nil, adopt laser as emission source; Strong interference immunity, good stability, penetrability are strong, are applicable to external environment, to realize the visual requirement of intelligent substation equipment state.
Description of drawings
Fig. 1 is the circuit theory diagrams of the utility model high voltage isolator divide-shut brake monitoring device.
Fig. 2 is the user mode reference diagram of the utility model high voltage isolator divide-shut brake monitoring device.
Embodiment
Like Fig. 1, shown in Figure 2; High voltage isolator divide-shut brake monitoring device is made up of control circuit; Said this control circuit is made up of radiating circuit and receiving circuit; Said radiating circuit is made up of start button SB1, auxiliary relay KM, stop button SB2, infrared induction reflector successively, and said receiving circuit is made up of separating brake position signal circuit and the parallel connection of closing position signal circuit, and said circuit is by DC power supply.
The contact KM-1 of said auxiliary relay, KM-3 are normal opened contact; The contact KM-2 of said auxiliary relay KM, KM-4 are normal opened contact; After start button SB1 starts; The contact KM-1 of auxiliary relay KM, KM-3 closed communicating, the contact KM-2 of auxiliary relay KM, KM-4 closed communicating, the infrared induction reflector transmits.
Said separating brake position signal circuit is made up of intermediate relay ZJ, green light successively; Said closing position signal circuit is in series by intermediate relay ZJ, stop button SB2, red light, infrared reception inducing receiver successively, and the normally closed contact ZJ-2 of said green light, intermediate relay ZJ, ZJ-4 are communicated to zero line.
Said infrared induction reflector 2 and infrared reception inducing receiver 3 are installed on the rotation position of 1 time end link 21 of isolating switch porcelain vase respectively; When combined floodgate puts in place; Reflector 2 is located along the same line with receiver 3, and the infrared ray that receiver 3 is received reflector 2 promptly sends switching signal, during separating brake; Infrared induction reflector 2 staggers with infrared reception inducing receiver 3, and receiver 3 does not receive infrared ray and promptly sends sub-gate signal
During use, the following end link 21 rotation positions installation of porcelain vase is considered in the concrete installation site of intelligent supervisory device, and the position that had so both guaranteed to follow the tracks of disconnecting link 4 guarantees to keep enough safe distances with live part simultaneously.After 21 rotations of isolating switch mechanical linkage put in place, when receiver 3 received laser signal, the resistance at its two ends of diode in the device was very little, i.e. conducting, and inner sensitive switch S is closed, the ZJ actuating of relay, normal opened contact is uploaded the closing position of isolating switch.During mechanical linkage 21 change positions, when receiver did not receive infrared signal, the resistance at its two ends was very big, promptly opens circuit when the isolating switch separating brake, and inner sensitive switch S breaks off, and the ZJ relay normally closed contact is uploaded the position of isolating switch separating brake.Device inspection loop: intelligent supervisory device design review (check) (DR) loop, for guaranteeing the normal operation of device, relay control is adopted in site inspection; But the situation of operations staff's regular check device; Method is pressed start button SB1, voltage relay KM action, and its contact is connected reflector; After inspection finishes, press stop button SB2 device and recover normal.This monitoring device adopts the 6V DC power supply, therefore, and must be from 220V AC power rectification step-down.The contact that utilizes intermediate relay ZJ is as the on-the-spot divide-shut brake position signalling of disconnecting link.And be connected to intelligent control box with cable through the contact of auxiliary relay, and utilize optical fiber to be sent to station level after the switching signal through Ethernet interface, reach the purpose of record, analysis and judgement.

Claims (3)

1. high voltage isolator divide-shut brake monitoring device; It is characterized in that: constitute by control circuit; Said this control circuit is made up of radiating circuit and receiving circuit; Said radiating circuit is made up of start button, auxiliary relay KM, stop button, infrared induction reflector successively, and said receiving circuit is made up of separating brake position signal circuit and the parallel connection of closing position signal circuit, and said circuit is by DC power supply.
2. high voltage isolator divide-shut brake monitoring device according to claim 1 is characterized in that: the contact KM-1 of said auxiliary relay, KM-3 are normal opened contact, and the contact KM-2 of said auxiliary relay KM, KM-4 are normal opened contact.
3. high voltage isolator divide-shut brake monitoring device according to claim 1; It is characterized in that: said separating brake position signal circuit is made up of intermediate relay ZJ, green light successively; Said closing position signal circuit is in series by intermediate relay ZJ, stop button, red light, infrared reception inducing receiver successively, and the normally closed contact ZJ-2 of said green light, intermediate relay ZJ, ZJ-4 are communicated to zero line.
CN2012200579985U 2012-02-22 2012-02-22 Monitoring device for opening and closing of high-voltage isolating switch Expired - Fee Related CN202487453U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012200579985U CN202487453U (en) 2012-02-22 2012-02-22 Monitoring device for opening and closing of high-voltage isolating switch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012200579985U CN202487453U (en) 2012-02-22 2012-02-22 Monitoring device for opening and closing of high-voltage isolating switch

Publications (1)

Publication Number Publication Date
CN202487453U true CN202487453U (en) 2012-10-10

Family

ID=46961857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012200579985U Expired - Fee Related CN202487453U (en) 2012-02-22 2012-02-22 Monitoring device for opening and closing of high-voltage isolating switch

Country Status (1)

Country Link
CN (1) CN202487453U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103489675A (en) * 2013-09-24 2014-01-01 国家电网公司 Disconnecting link operation position photoelectric dialyser
CN104198929A (en) * 2014-07-14 2014-12-10 国网上海市电力公司 Detection device and detection method for outdoor high voltage isolator
CN106019137A (en) * 2016-07-19 2016-10-12 南宏电力科技有限公司 Switch state detecting circuit of protective relaying device
CN106252119A (en) * 2016-08-31 2016-12-21 国网山东省电力公司淄博供电公司 Disconnecting switch monitoring arrangement
CN109192566A (en) * 2018-08-02 2019-01-11 广东电网有限责任公司 The judgment means and method of a kind of substation's disconnecting link opening and closing position
CN109406991A (en) * 2018-09-18 2019-03-01 四川大学 A kind of horizontal rotation type high-voltage isolation switch in-place closing confirmation method based on laser optical path
CN113096985A (en) * 2021-04-08 2021-07-09 广东电网有限责任公司 Isolating switch on-off monitoring device
WO2024041676A1 (en) * 2023-02-28 2024-02-29 湖北清江水电开发有限责任公司 Monitoring method for switching-off/switching-on state of isolating switch

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103489675A (en) * 2013-09-24 2014-01-01 国家电网公司 Disconnecting link operation position photoelectric dialyser
CN104198929A (en) * 2014-07-14 2014-12-10 国网上海市电力公司 Detection device and detection method for outdoor high voltage isolator
CN106019137A (en) * 2016-07-19 2016-10-12 南宏电力科技有限公司 Switch state detecting circuit of protective relaying device
CN106019137B (en) * 2016-07-19 2018-07-27 南宏电力科技有限公司 A kind of switch condition detection circuit of protective relaying device
CN106252119A (en) * 2016-08-31 2016-12-21 国网山东省电力公司淄博供电公司 Disconnecting switch monitoring arrangement
CN109192566A (en) * 2018-08-02 2019-01-11 广东电网有限责任公司 The judgment means and method of a kind of substation's disconnecting link opening and closing position
CN109192566B (en) * 2018-08-02 2023-12-29 广东电网有限责任公司 Device and method for judging disconnecting link opening and closing positions of transformer substation
CN109406991A (en) * 2018-09-18 2019-03-01 四川大学 A kind of horizontal rotation type high-voltage isolation switch in-place closing confirmation method based on laser optical path
CN109406991B (en) * 2018-09-18 2021-05-04 四川大学 In-place closing confirmation method based on horizontal rotation type high-voltage isolating switch
CN113096985A (en) * 2021-04-08 2021-07-09 广东电网有限责任公司 Isolating switch on-off monitoring device
CN113096985B (en) * 2021-04-08 2023-03-28 广东电网有限责任公司 Isolating switch on-off monitoring device
WO2024041676A1 (en) * 2023-02-28 2024-02-29 湖北清江水电开发有限责任公司 Monitoring method for switching-off/switching-on state of isolating switch

Similar Documents

Publication Publication Date Title
CN202487453U (en) Monitoring device for opening and closing of high-voltage isolating switch
CN106093674B (en) Using the self-powered electric network fault detection device of short circuit current and method
CN104460614A (en) Hotel energy-consumption intelligent remote monitoring and managing system
CN110205972B (en) Rail transit deicing snow melt system
CN104192026B (en) Based on electrification railway contact net electric isolating switch and the method for supervising of power supply switching type
CN104330607B (en) Alternating current scurries into the detection of straight-flow system and compels to jump device
CN203481922U (en) Distribution automation remote measuring and control device for distribution monitoring
CN204136803U (en) Based on the electrification railway contact net electric isolating switch of power supply switching type
CN204376211U (en) A kind of high-tension switch cabinet smart grounding disconnecting link
CN201789342U (en) Transformer substation direct-current device monitoring system adopting GPRS communication mode
CN104253480A (en) 10-KV box-type transformer station with intelligent monitoring function
CN102694417A (en) Intelligent distribution system
CN203027026U (en) Remote operation and video monitoring system for integrated intelligent isolating switch
CN107437848B (en) System and method for non-signal access of stand-by power supply in monitoring background
CN202076844U (en) Integrated monitoring protector with operation safety protection
CN201514454U (en) Intelligent long-range cable short circuit earth fault alarm device
CN204304416U (en) Be used in the microcomputer protective relay device on the switch cubicle of installing on-load switch
CN203799488U (en) Household digital intelligent distribution box
CN203760863U (en) Automatic pole-mounted switch cabinet of distribution network
CN208226677U (en) A kind of line feed terminals based on zigbee wireless transmission
CN207968078U (en) A kind of control device of four-wire system electric isolating switch
CN207053251U (en) A kind of grid entry point supervising device of family expenses photovoltaic generating system
CN204259220U (en) Electric substation's digital supervision night illumination tele-control system
CN104319889B (en) A kind of with neutral point isolation switch operation realization protection automatic switching method
CN204391897U (en) A kind of integrated monitoring system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20131202

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Patentee after: State Grid Corporation of China

Patentee after: State Grid Fujian Electric Power Co., Ltd.

Patentee after: Quanzhou Power Supply Company, State Grid Fujian Electric Power Co., Ltd.

Address before: 362000 Fujian city of Quanzhou province Erythrina Road on electric power building A building room 713 Quanzhou Electric Power Bureau substation maintenance department

Patentee before: Zhang Guocan

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121010

Termination date: 20180222

CF01 Termination of patent right due to non-payment of annual fee