CN202485191U - Methane boiler - Google Patents

Methane boiler Download PDF

Info

Publication number
CN202485191U
CN202485191U CN2012200959113U CN201220095911U CN202485191U CN 202485191 U CN202485191 U CN 202485191U CN 2012200959113 U CN2012200959113 U CN 2012200959113U CN 201220095911 U CN201220095911 U CN 201220095911U CN 202485191 U CN202485191 U CN 202485191U
Authority
CN
China
Prior art keywords
chimney
boiler
combustion chamber
smoke box
smoke
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012200959113U
Other languages
Chinese (zh)
Inventor
史东立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Qunxiang Heating Equipment Co., Ltd.
Original Assignee
HEBEI QUNXIANG HEATING EQUIPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HEBEI QUNXIANG HEATING EQUIPMENT Co Ltd filed Critical HEBEI QUNXIANG HEATING EQUIPMENT Co Ltd
Priority to CN2012200959113U priority Critical patent/CN202485191U/en
Application granted granted Critical
Publication of CN202485191U publication Critical patent/CN202485191U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a methane boiler which comprises a baseboard, a cylindrical water sleeve, a chimney and a firing chamber. The baseboard is provided with a boiler outer cover, the outer wall of the boiler outer cover is provided with a thermometer seat, the cylindrical water sleeve is arranged inside the boiler outer cover, and the chimney penetrates the top end of the boiler outer cover and is connected with a smoke chamber which is in a drum shape. The inner wall of the smoke chamber is provided with a plurality of flat steels which are evenly arranged along the peripheral direction in a welded mode, one end of the chimney is inserted into the smoke chamber and sealed through a blocking plate, and side walls of the smoke chamber is provided with a plurality of holes which are evenly arranged. The firing chamber is connected with the smoke chamber through a plurality of smoke tubes, and the bottom of the firing chamber is connected with the baseboard through a plurality of support pillars. The methane boiler has the advantages that heating surfaces of the smoke chamber are enlarged, and thus more heat is converted out, thermal efficiency of the boiler is improved, energy is saved and service life of the boiler is prolonged. Due to the fact that the sides of the chimney are provided with the holes in design, thus residence time of flue and gas in the smoke chamber is prolonged so that the heat is better absorbed by water.

Description

A kind of methane boiler
Technical field
The utility model relates to a kind of methane boiler.
Background technology
Along with national energy-saving and emission-reduction task situation is more and more severeer, the energy-conserving and environment-protective product will become the market mainstream.Traditional boiler adopts is the threaded flue technology or in smoke pipe, increases flame-resistant sheet, makes flue gas rest on the time lengthening in the stove, thereby reaches the effect that improves heat exchange.
The utility model content
The purpose of the utility model provides a kind of methane boiler, has increased the smoke box heating surface, has improved boiler thermal output, and energy savings has prolonged service life of boiler.
The purpose of the utility model is to realize through following technical scheme:
A kind of methane boiler comprises: base plate, outer casing is set on the base plate, and the outer casing outer wall is provided with the temperature gauge stand; Be located at the cylindrical water jacket in the outer casing; Chimney, chimney pass the outer casing top and connect smoke box; And pass through the combustion chamber that some smoke pipes connect smoke boxes, the bottom, combustion chamber connects base plates through some support columns; Said smoke box in the form of a roll, its inwall along the circumferential direction is welded with some evenly distributed band steels; One end of said chimney inserts smoke box and through the closure plate sealing, its sidewall has some evenly distributed holes; Said smoke box and combustion chamber all are located in the water jacket, and bottom, said combustion chamber is coated with refractory cement.
Said outer wall of combustion chamber connects sees fiery passage and burner interface, and the other end of seeing fiery passage and burner interface all passes water jacket and outer casing and stretches out.
Said burner connects the combustion chamber through burner interface and the flange of being located at said burner one end, and the burner other end is provided with air inlet and air inlet, and a side and the air inlet corresponding position of flange are equipped with supercharging device.
The beneficial effect of the utility model is: increased the smoke box heating surface, thereby heat is more changed away, improved boiler thermal output, energy savings has prolonged service life of boiler; The perforate design of chimney side has prolonged flue gas in the smoke box time of staying, and heat is absorbed by water better.
Description of drawings
According to accompanying drawing the utility model is done further explain below.
Fig. 1 is the cutaway view of the described a kind of methane boiler of the utility model embodiment;
Fig. 2 is the vertical view of the described a kind of methane boiler of the utility model embodiment.
Among the figure:
1, base plate; 2, outer casing; 3, temperature gauge stand; 4, water jacket; 5, chimney; 6, smoke box; 7, smoke pipe; 8, combustion chamber; 9, support column; 10, supercharging device; 11, band steel; 12, hole; 13, refractory cement; 14, see fiery passage; 15, burner interface; 16, burner; 17, flange; 18, air inlet; 19, air inlet.
The specific embodiment
Shown in Fig. 1-2, the described a kind of methane boiler of the utility model embodiment comprises: base plate 1, outer casing 2 is set on the base plate 1, and outer casing 2 outer walls are provided with temperature gauge stand 3; Be located at the cylindrical water jacket 4 in the outer casing 2; Chimney 5, chimney 5 pass outer casing 2 tops and connect smoke box 6; And pass through the combustion chamber 8 that some smoke pipes 7 connect smoke boxes 6,8 bottoms, combustion chamber connect base plates 1 through some support columns 9; Said smoke box 6 in the form of a roll, its inwall along the circumferential direction is welded with 24 evenly distributed band steels 11; One end of said chimney 5 inserts smoke box 6 and through closure plate 20 sealings, its sidewall has 4 evenly distributed holes 12.Said smoke box 6 all is located in the water jacket 4 with combustion chamber 8, between water jacket 4 and smoke box and the combustion chamber 8 certain interval is arranged, and forms a water layer, to improve heat exchange efficiency.8 bottoms, said combustion chamber are coated with refractory cement 13.Said combustion chamber 8 outer walls connect sees fiery passage 14 and burner interface 15, and the other end of seeing fiery passage 14 and burner interface 15 all passes water jacket 4 with outer casing 2 and stretch out.Burner 16 is through burner interface 15 and the flange 17 connection combustion chambers 8 of being located at said burner 16 1 ends, and burner 16 other ends are provided with air inlet 18 and air inlet 19, and a side of flange 17 and air inlet 18 corresponding positions are equipped with supercharging device 10.
During concrete the use; Because chimney 5 sidewalls have 4 holes 12, and are provided with closure plate 20 between chimney 5 and the smoke box 6, flue gas can directly directly not be discharged to atmosphere from chimney 5 bottoms during boiler combustion; But run into the bottom press to rapidly during closure plate 20 around with 24 Welding flat steels 11 and whole smoke box 6 inwalls at smoke box position; 4 holes 12 of being opened by the next door again after the contact fully are discharged in the atmosphere, and flue gas prolonged in 6 time of staying of smoke box, contact-making surface strengthens, thereby improved heat exchange efficiency thereby make.In addition, 8 bottoms have increased the 100mm water layer in the combustion chamber, improve heat exchange area on the one hand, have reduced the bottom steel plate deformed on the other hand, improve the service life that the thermal efficiency has prolonged boiler simultaneously again.The utility model adopts the supercharging of whirlwind eddy current, and pressurized effect is obvious, has reduced the model and the power of motor of apolegamy blower fan simultaneously, has reduced the use cost in user's later stage.And adopt the high-tension electricity sparking, and ignition success rate is high, and safety coefficient is high.
The utility model is not limited to above-mentioned preferred forms; Anyone can draw other various forms of products under the enlightenment of the utility model; No matter but on its shape or structure, do any variation; Every have identical with a application or akin technical scheme, all drops within the protection domain of the utility model.

Claims (5)

1. methane boiler; Comprise: base plate (1), chimney (5) and combustion chamber (8), outer casing (2) is set on the base plate (1), outer casing (2) outer wall is provided with temperature gauge stand (3); Be provided with cylindrical water jacket (4) in the outer casing (2); Chimney (5) passes outer casing (2) top and connects smoke box (6), and combustion chamber (8) connect smoke box (6) through some smoke pipes (7), and combustion chamber (8) bottom connects base plate (1) through some support columns (9); It is characterized in that: smoke box (6) in the form of a roll, smoke box (6) inwall along the circumferential direction is welded with some evenly distributed band steels (11); One end of chimney (5) inserts in the smoke box (6) and through closure plate (20) sealing, chimney (5) sidewall has some evenly distributed holes (12).
2. a kind of methane boiler according to claim 1 is characterized in that: said smoke box (6) and combustion chamber (8) all are located in the water jacket (4).
3. a kind of methane boiler according to claim 2 is characterized in that: said combustion chamber (8) bottom is coated with refractory cement (13).
4. a kind of methane boiler according to claim 3; It is characterized in that: said combustion chamber (8) outer wall connect to be seen fiery passage (14) and burner interface (15), and the other end of seeing fiery passage (14) and burner interface (15) all passes water jacket (4) and outer casing (2) and stretches out.
5. a kind of methane boiler according to claim 4; It is characterized in that: burner (16) connects combustion chamber (8) through burner interface (15) and the flange (17) of being located at said burner (16) one ends; Burner (16) other end is provided with air inlet (18) and air inlet (19), and a side of flange (17) and air inlet (18) corresponding position are equipped with supercharging device (10).
CN2012200959113U 2012-03-14 2012-03-14 Methane boiler Expired - Fee Related CN202485191U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012200959113U CN202485191U (en) 2012-03-14 2012-03-14 Methane boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012200959113U CN202485191U (en) 2012-03-14 2012-03-14 Methane boiler

Publications (1)

Publication Number Publication Date
CN202485191U true CN202485191U (en) 2012-10-10

Family

ID=46959609

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012200959113U Expired - Fee Related CN202485191U (en) 2012-03-14 2012-03-14 Methane boiler

Country Status (1)

Country Link
CN (1) CN202485191U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104374091A (en) * 2014-11-06 2015-02-25 无锡鸿声铝业有限公司 Intelligent heating furnace
CN104390343A (en) * 2014-11-06 2015-03-04 无锡鸿声铝业有限公司 Intelligent water heater
CN104456505A (en) * 2014-12-02 2015-03-25 中国矿业大学 Low-concentration coal-bed methane or methane gas steam boiler
CN104456925A (en) * 2014-11-06 2015-03-25 无锡鸿声铝业有限公司 Heating furnace
CN108361974A (en) * 2018-02-09 2018-08-03 山东科技大学 A kind of energy-saving natural gas stove

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104374091A (en) * 2014-11-06 2015-02-25 无锡鸿声铝业有限公司 Intelligent heating furnace
CN104390343A (en) * 2014-11-06 2015-03-04 无锡鸿声铝业有限公司 Intelligent water heater
CN104456925A (en) * 2014-11-06 2015-03-25 无锡鸿声铝业有限公司 Heating furnace
CN104456505A (en) * 2014-12-02 2015-03-25 中国矿业大学 Low-concentration coal-bed methane or methane gas steam boiler
CN108361974A (en) * 2018-02-09 2018-08-03 山东科技大学 A kind of energy-saving natural gas stove

Similar Documents

Publication Publication Date Title
CN202485191U (en) Methane boiler
CA2573333A1 (en) High efficiency, wet-base, downfired multi-pass water heater
CA2783277A1 (en) High efficiency gas-fired water heater
CN204477999U (en) Vertical environment protection boiler
CN201203257Y (en) Energy-saving environment protection type ambient pressure boiler
CN210569203U (en) Steam hot air double-coil hot air furnace
CN113375141A (en) Energy-efficient steam boiler
CN203595271U (en) Vertical non-pressurized water-tube chamber combustion water boiler with high heat exchange performance
CN202485209U (en) Environmental-friendly and energy-saving multi-purpose furnace
CN202719636U (en) Efficient energy-saving stove
CN201615597U (en) Hot blast furnace
CN202361622U (en) Energy-saving air heater
CN202835317U (en) Vertical type boiler with towering pipe
CN202543266U (en) Energy-saving overall thermal processor for ball pot
CN203595111U (en) Normal pressure vertical type water pipe chamber burning hot water boiler
CN203036695U (en) Small stove producing hot water and steam
CN210373376U (en) Steam generator
CN202066194U (en) Radiating pan type hot air boiler
CN201138059Y (en) Hot-pipe explosion-preventing gas fuel heating stove
CN201748480U (en) Energy-saving warming stove
CN202024467U (en) Thermal superconductive pipe boiler
CN202613419U (en) Novel energy saver for boilers
CN101706153A (en) Efficient oil-burning boiler
CN201166455Y (en) Atmosphere pressure hot water heating stove
CN206094535U (en) Energy -saving boiler furnace body

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHI DONGLI

Free format text: FORMER OWNER: HEBEI QUNXIANG HEATING EQUIPMENT CO., LTD.

Effective date: 20131018

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 074000 BAODING, HEBEI PROVINCE TO: 072750 BAODING, HEBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20131018

Address after: 072750 Zhuozhou city in Hebei province Twin Towers District No. 312 Wenchang Temple Street Minghui

Patentee after: Shi Dongli

Address before: 074000, 216 North Main Street, Baoding, Hebei, Gaobeidian

Patentee before: Hebei Qunxiang Heating Equipment Co., Ltd.

ASS Succession or assignment of patent right

Owner name: DU YUGE

Free format text: FORMER OWNER: SHI DONGLI

Effective date: 20131118

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 072750 BAODING, HEBEI PROVINCE TO: 074000 BAODING, HEBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20131118

Address after: 401, room 3, unit 2, Yue Yue District, 30 Jie Jie Hutong, union West Road, Hebei, Gaobeidian, 074000

Patentee after: Du Yuge

Address before: 072750 Zhuozhou city in Hebei province Twin Towers District No. 312 Wenchang Temple Street Minghui

Patentee before: Shi Dongli

ASS Succession or assignment of patent right

Owner name: HEBEI QUNXIANG HEATING EQUIPMENT CO., LTD.

Free format text: FORMER OWNER: DU YUGE

Effective date: 20131209

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 074000 BAODING, HEBEI PROVINCE TO: 071000 BAODING, HEBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20131209

Address after: 071000, 216 North Main Street, Baoding, Hebei, Gaobeidian

Patentee after: Hebei Qunxiang Heating Equipment Co., Ltd.

Address before: 401, room 3, unit 2, Yue Yue District, 30 Jie Jie Hutong, union West Road, Hebei, Gaobeidian, 074000

Patentee before: Du Yuge

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121010

Termination date: 20180314