CN202467810U - Touchdown detection device for drill rods of rotary drilling rigs - Google Patents

Touchdown detection device for drill rods of rotary drilling rigs Download PDF

Info

Publication number
CN202467810U
CN202467810U CN2012200256033U CN201220025603U CN202467810U CN 202467810 U CN202467810 U CN 202467810U CN 2012200256033 U CN2012200256033 U CN 2012200256033U CN 201220025603 U CN201220025603 U CN 201220025603U CN 202467810 U CN202467810 U CN 202467810U
Authority
CN
China
Prior art keywords
rotary drilling
wireless signal
detection device
drilling rig
information processing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012200256033U
Other languages
Chinese (zh)
Inventor
刘劲
李晟
谢德兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING KELEI MACHINERY Co Ltd
Original Assignee
CHONGQING KELEI MACHINERY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING KELEI MACHINERY Co Ltd filed Critical CHONGQING KELEI MACHINERY Co Ltd
Priority to CN2012200256033U priority Critical patent/CN202467810U/en
Application granted granted Critical
Publication of CN202467810U publication Critical patent/CN202467810U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model aims to provide a touchdown detection device for drill rods of rotary drilling rigs, which is designed for solving the problem that in the prior art, operators can not accurately monitor the state of the head part of a drill rod in real time, thereby often causing a phenomenon that a steel wire rope of a main hoist is unordered. According to the scheme, the touchdown detection device for drill rods of rotary drilling rigs is characterized by comprising a hoisting pulley arranged on a hoisting mechanism of a rotary drilling rig; the hoisting pulley is provided with a pin shaft sensor, a data acquisition unit and a wireless signal transmitting device which are sequentially connected; and the touchdown detection device also comprises an information processing device arranged in an operation chamber of the rotary drilling rig, a wireless signal receiving device matched with the wireless signal transmitting device is arranged in the information processing device, a computer which is connected with the wireless signal receiving device and is used for processing signal data is also arranged in the information processing device, and the information processing device is also provided with an information output terminal connected with the computer.. By using the touchdown detection device provided by the utility model, operators can accurately monitor the state of the head part of the drill rod in real time, thereby avoiding a phenomenon that a steel wire rope of a main hoist is unordered.

Description

The rotary drilling rig drilling rod checkout gear that contacts to earth
Technical field
The utility model relates to a kind of rig that is used for the land transport device that has.
Background technology
Rotary drilling rig is a kind of multi-functional, high efficiency pouring pile hole equipment.Noise was little when it had construction, friction, no soil deformation, displacement; Little to surrounding constructure influence, the stake footpath is big, and length can freely be selected; And can enlarge the bottom, pile body stiffness is big, and bearing capacity of single pile is big; Efficient is high, and system stake low cost and other advantages, is approved by domestic basic engineering institute and unit in charge of construction at present.Along with the increase of rotary drilling rig recoverable amount on market, the user also proposes higher requirement to the functional performance of rotary drilling rig.As: rotary drilling rig often occurs because of operator's error causes the phenomenon of master winch wire rope disorder cable, thereby causes wire rope low application life in work progress, and sounding error is big.
The utility model content
The utility model is intended to provide a kind of rotary drilling rig drilling rod checkout gear that contacts to earth, and to solve the monitoring drilling rod head state that operator of the prior art can't be accurately real-time, causes the problem of master winch wire rope disorder cable often.
The purpose of the utility model can reach through following measure: the checkout gear that contacts to earth of the rotary drilling rig drilling rod in this programme; It is characterized in that: comprise the elevator pulley that is installed on the rotary drilling rig hoisting mechanism; The elevator pulley is provided with bearing pin sensor, data acquisition unit and the wireless signal transmitting device that connects successively; Also comprise and be used to be located at the information processor in the rotary drilling rig operating room; Be provided with wireless signal receiving system in the information processor with said wireless signal transmitting device coupling; Also be provided with in the information processor be connected with the wireless signal receiving system be used for processing signals data computing machine, also be provided with the information outlet terminal that is connected with said computer on the information processor.
Said elevator pulley is installed on the hoisting mechanism of rotary drilling rig, and drilling rod is fixed with the wire rope that is wrapped on the elevator pulley.In the course of work; The bearing pin sensor is monitored the stress of elevator pulley at any time; And signal sent to the computer in the information processor through data acquisition unit and wireless signal transmission/receiving system, after drilling rod contacted to earth, drilling rod acted on pull of steel wire and is certain to tangible minimizing; Computer then can detect described variation; Contact to earth to judge that drilling rod is actual, remind the operator through the information outlet terminal then, said information outlet terminal can be the various devices that can send alerting signal such as loudspeaker, display, alarm lamp.
Data acquisition unit carries out operations such as AD conversion and the coding of signal, and the also available wireless signal transmitting device of transferring to of encoding operation is accomplished, and computer then can be to the information of receiving processing such as decode.
Computer carries out initialization in the back that powers on to the drilling rod automatic stop control functional module of contacting to earth; Then the bearing pin sensor signal that collects is put, analyzes in order the back and obtain reference data; Reference data steel wire rope tension data real-time and initial setting compare; If reference data is less than the data of setting then send control signal; Simultaneously current depth measurement data are also caught up with the depth measurement data of preserving when once holing and are compared, if data of preserving when hole less than the last time then report to the police to the information outlet terminal are in position at the bottom of the hole, hole otherwise give tacit consent to drilling rod; If reference data is greater than the data of setting then Vehicle Controller is not sent out control signal, the operator normally transfers drilling rod.
Further: said information outlet terminal is a LED display.
Description of drawings
Below in conjunction with the accompanying drawing and the specific embodiment the utility model is done further detailed explanation:
Fig. 1 is the sketch map of rotary drilling rig top hoisting mechanism among the utility model embodiment.
The specific embodiment
Known concrete structure and characteristic are no longer set forth at this in the following proposal.As shown in Figure 1: the rotary drilling rig hoisting mechanism includes elevator pulley 1; The bearing pin of installing in the elevator pulley 2 is provided with the bearing pin sensor; Signal treatment box 3 also is installed in elevator pulley 1; The data acquisition unit and the wireless signal transmitter that are connected are installed in it, information processor is installed in driver's cabin, also be provided with the wireless signal receiver, computer and the LED display that are connected on the information processor.
Above-described only is the preferred implementation of the utility model; Should be understood that; For a person skilled in the art, under the prerequisite that does not break away from the utility model structure, can also make some distortion and improvement; These also should be regarded as the protection domain of the utility model, and these can not influence effect and practical applicability that the utility model is implemented.

Claims (2)

1. the rotary drilling rig drilling rod checkout gear that contacts to earth; It is characterized in that: comprise the elevator pulley that is installed on the rotary drilling rig hoisting mechanism; The elevator pulley is provided with bearing pin sensor, data acquisition unit and the wireless signal transmitting device that connects successively; Also comprise and be used to be located at the information processor in the rotary drilling rig operating room; Be provided with the wireless signal receiving system with said wireless signal transmitting device coupling in the information processor, also be provided with in the information processor be connected with the wireless signal receiving system be used for processing signals data computing machine, also be provided with the information outlet terminal that is connected with said computer on the information processor.
2. the rotary drilling rig drilling rod according to claim 1 checkout gear that contacts to earth, it is characterized in that: said information outlet terminal is a LED display.
CN2012200256033U 2012-01-19 2012-01-19 Touchdown detection device for drill rods of rotary drilling rigs Expired - Fee Related CN202467810U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012200256033U CN202467810U (en) 2012-01-19 2012-01-19 Touchdown detection device for drill rods of rotary drilling rigs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012200256033U CN202467810U (en) 2012-01-19 2012-01-19 Touchdown detection device for drill rods of rotary drilling rigs

Publications (1)

Publication Number Publication Date
CN202467810U true CN202467810U (en) 2012-10-03

Family

ID=46915975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012200256033U Expired - Fee Related CN202467810U (en) 2012-01-19 2012-01-19 Touchdown detection device for drill rods of rotary drilling rigs

Country Status (1)

Country Link
CN (1) CN202467810U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104048635A (en) * 2014-06-16 2014-09-17 上海中联重科桩工机械有限公司 Accumulated hole depth measuring system, measuring method and engineering machinery with accumulated hole depth measuring system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104048635A (en) * 2014-06-16 2014-09-17 上海中联重科桩工机械有限公司 Accumulated hole depth measuring system, measuring method and engineering machinery with accumulated hole depth measuring system

Similar Documents

Publication Publication Date Title
CN201628537U (en) Top plate displacement monitoring instrument
WO2007109555A3 (en) Underground monitoring system and method
EP3020914A3 (en) Well monitoring
CN204827532U (en) Monitored control system in pit reports to police in colliery based on thing networking
CN104326360B (en) High pedestal jib crane holographic measuring method
CN202467810U (en) Touchdown detection device for drill rods of rotary drilling rigs
CN202609745U (en) Monitoring device of brake control system of mine hoist
CN203177842U (en) A well wall deformation parameter detecting system based on the control of an ATMEGA128
CN205177142U (en) Data wireless transmission system in hydrometric cableway pressure depth measurement device
CN203224223U (en) Device for detecting layer separation of surrounding rock based on displacement sensors and wireless transmission
CN206787527U (en) A kind of simple landslide monitoring device
CN202523195U (en) Motor type wireless monitor for air-defense alarm
CN101985834B (en) Automatic control system for plastic dewatering plate process quality
CN107676078A (en) Coal mine underground water pulse wireless measurement while drilling system and measurement method
CN204386569U (en) A kind of oil well perforation low limit detector
CN202970702U (en) Rotary drilling rig with depth measurement function
CN203569598U (en) Precast pile capable of being monitored in real time
CN201802382U (en) Crown block anticollision device
CN204495310U (en) A kind of brake glide quantity detector of crane
CN105066948B (en) Distress in concrete remote real time monitoring system
CN205297549U (en) Detecting device of water level in pit
CN204728328U (en) Oil field anchoring pile warning device
CN204102294U (en) No killing well ram block position monitoring device
CN103822657B (en) Underground coal mine fully-mechanized mining working advancing distance dynamic monitor
CN204691760U (en) A kind of coal bed gas open hole well sand face sniffer based on using screw pump mining

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121003

Termination date: 20150119

EXPY Termination of patent right or utility model