Suspending device for heavy steel support of bridge Download PDFInfo
- Publication number
- CN202466422U CN202466422U CN2012200627692U CN201220062769U CN202466422U CN 202466422 U CN202466422 U CN 202466422U CN 2012200627692 U CN2012200627692 U CN 2012200627692U CN 201220062769 U CN201220062769 U CN 201220062769U CN 202466422 U CN202466422 U CN 202466422U
- Authority
- CN
- China
- Prior art keywords
- bridge
- suspending
- construction
- main truss
- suspending device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model relates to the field of the suspension of heavy materials, in particular to a suspending device for a heavy steel support of a bridge, aiming at solving the problem that the existing bridge support has different disadvantages since being suspended by a tower hoist or a large-scale hoist. The suspending device comprises suspending main hook frames, wherein two ends of the two pieces of suspending main hook frames are connected with each other by a front transverse beam and a back transverse beam, and the back ends of the suspending main hook frames are anchored with the top of bridge piers by fining twisted steel bar anchor rods and positioning steel plates; longitudinal slide tracks are welded on the suspending main hook frames, slide I-shaped steels are arranged on the two longitudinal slide tracks, pulley blocks are arranged on the slide I-shaped steels, and hoisting machines and steel wire ropes are arranged behind the top of bridge piers, so that the cost can be saved, the suspending device is safe and controllable, and wide in use range, and the construction cost can be reduced; the suspending device is small in equipment investment, low in construction mechanized requirement, and small in construction safety risk; and the suspending device is not high in the requirement of construction sites, and the difficulties of narrow sites, high piers, the hard hoisting of heavy support can be solved.
Description
Technical field
The utility model relates to weight lifting field, is specially the heavy steel support hanging apparatus of a kind of bridge.
Background technology
Along with greatly developing of bridge construction, the bridge pad construction is more and more, and bearing is increasing, more and more heavier.Weight is restricted to adopt traditional tower crane to lift not only; And pier is high and the construction plant also is restricted, as adopts conventional super-huge crane to lift, and not only lease expenses is higher; And to reinforce sidewalk; The construction plant needs large-area sclerosis concrete, and the input expense is bigger, and construction safety can't guarantee.
Summary of the invention
The utility model adopts tower crane or large-scale crane to lift the existence problem of different shortcomings separately in order to solve existing bridge pad, provides a kind of new bridge heavy steel support hanging apparatus.
The utility model is to adopt following technical scheme to realize: the heavy steel support hanging apparatus of bridge; Comprise the lifting main truss that is positioned at center line both sides, bridge pier top; Two lifting main truss two ends connect through front beam, rear cross beam respectively, two lifting fining twisted steel anchor pole and fixing steel plate and the bridge pier top anchorings of main truss rear end through being embedded in bridge Dun Ding; Two liftings are welded with the straight skidding track respectively on the main trusss, and two straight skidding tracks are provided with the slippage i iron, on the slippage i iron assembly pulley are installed, bridge Dun Ding rear hoist engine is installed and be wound in hoist engine and assembly pulley on wire rope.
Adopt the structure design of the utility model; Two of assembly units lift main truss at the construction field (site); Lift two lifting main trusss respectively to Dun Ding with tower crane, and carry out the anchoring of main truss with fining twisted steel anchor pole and fixing steel plate, forward and backward crossbeam of welding and straight skidding track are linked to be a whole truss with two lifting main trusss on two lifting main trusss; As promoting support body, through hoist engine, wire rope and slippage i iron, assembly pulley heavy steel support is risen to Dun Ding then.
Be fixed with between said straight skidding track and the lifting main truss and strengthen column and diagonal brace, can further strengthen the resistance to overturning between straight skidding track and the lifting main truss.
In order to reduce construction cost, handled easily, said lifting main truss adopts the Hanging Basket main truss, is the Hanging Basket main truss of construction semi girder.
Compared with prior art, the utlity model has following advantage:
1, make full use of turnover material such as member on the Hanging Basket as the truss that promotes bearing, practiced thrift cost, safety has also obtained guarantee, and the scope of application is wide, can reduce construction cost;
2, construction technology is simple, easy operating, and safety is controlled;
3, less equipment investment, mechanization of building operation is less demanding, and construction safety risk is little;
4, the construction plant is less demanding, has solved the difficult problem of narrow and small, the high pier in place, the lifting of heavy bearing.
In a word, adopt the described hanging apparatus of the utility model to construct, significantly reduced construction cost, practiced thrift construction cost, have good economic benefit and social benefit.
Description of drawings
Fig. 1 is the lateral view of the utility model;
Fig. 2 is the vertical view of the utility model;
Among the figure: 1-bridge Dun Ding; 2-lifts main truss; The 3-front beam; The 4-rear cross beam; 5-fining twisted steel anchor pole; The 6-fixing steel plate; 7-straight skidding track; 8-slippage i iron; The 9-assembly pulley; The 10-hoist engine; The 11-wire rope; 12-strengthens column; The 13-diagonal brace.
The specific embodiment
The heavy steel support hanging apparatus of bridge like Fig. 1, shown in 2, comprises being positioned at the lifting main truss 2 that the bridge pier pushes up 1 center line both sides; Adopt the Hanging Basket main truss; Two lifting main truss two ends connect through front beam 3, rear cross beam 4 respectively, play the stabilization of whole truss, and two lifting main truss rear ends are pushed up 1 anchoring through ф 32mm fining twisted steel anchor pole 5 and the fixing steel plate 6 that is embedded in bridge Dun Ding with the bridge pier; The fining twisted steel anchor pole is imbedded concrete 1.3m, is used for the anchoring whole truss; Two liftings are welded with straight skidding track 7, two straight skidding tracks respectively on the main trusss and are provided with slippage i iron 8, and assembly pulley 9 is installed on the slippage i iron, the bridge pier push up 1 rear hoist engine 10 is installed and be wound in hoist engine and assembly pulley on wire rope 11; Be fixed with between straight skidding track 7 and the lifting main truss 2 and strengthen column 12 and diagonal brace 13.
During construction, lifting main truss major part adopts the Hanging Basket main truss, and the lifting main truss can be assembled at the bottom of pier; Re-use tower crane and lift Dun Ding, straight skidding track, slippage i iron and reinforcement column, diagonal brace can lift Dun Ding again after the pier back welding is connected into one; With the welding of Hanging Basket main truss, constitute the primary structure member of lifting, hoist engine adopts JM-5B type building whim; Specified hoisting weight 50KN; Assembly pulley is made up of 1 movable pulley and 2 fixed pulleys, the object of the 6 * 50KN=300KN that can sling, and the assembly pulley wire rope adopts the wire rope of ф 19.5mm.
Case history
Project profile
The middle and south, Shanxi rail channel ZNTJ-1 marks luxuriant Fenhe River grand bridge, and to be positioned at the Cai Jiaya township that makes the county prosperous, Lvliang City, Shanxi Province domestic, total length 1500.45m.This bridge opening is striden and is arranged as: 1-32m freely-supported T beam+1-(70+140+140+140+70) m continuous rigid frame+3-(70+70) m T structure+16-32m freely-supported T beam, totally 28 stride.Maximum is striden 120m, and the highest pier height is 90m; This bridge location is on the small curve radius of sweep R=800m.Whole bridge plane is " S " type.The continuous beam maximum cantilever poured weights of luxuriant Fenhe River grand bridge reaches 236 tons.
Construction effect is estimated
The high pier bearing lifting construction of luxuriant Fenhe River grand bridge adopts the described hanging apparatus of the utility model, has practiced thrift cost, and safety has also obtained guarantee.Do not need the large-scale crane of the outer 500t of rent to lift, saved rental charge 400,000, saved construction simultaneously and widened sidewalk, reinforce 380,000 yuan of expenses such as sidewalk and construction plant sclerosis, add up to and reduce expenses 780,000 yuan.
The bearing of 2# pier was on July 20th, 2011; Only used 56 fens clock time security improvements to put in place; 5# pier bearing was on October 5th, 2011; Used 98 minutes security improvements to put in place, no any security incident in the construction obtains the height favorable comment that Jin Yu Shandong rail channel limited company, middle iron the 3rd designing institute, Sinorael manage how tame units such as Co., Ltd; For similar engineering construction provides utmost point valuable reference and reference, and in the Bridge High-pier bearing lifting completely of Central-South rail channel, apply.
Promotion prospect
Adopt the described hanging apparatus of the utility model, construction safety is reliable, and it is narrow and small to overcome the construction plant, reduces advantages such as construction cost, and is narrow and small especially on construction ground, adopts this lifting heavy objects under the high pier situation, and its advantage is more obvious.
Claims (3)
1. the heavy steel support hanging apparatus of a bridge; It is characterized in that comprising the lifting main truss (2) that is positioned at bridge Dun Ding (1) center line both sides; Two lifting main truss two ends connect through front beam (3), rear cross beam (4) respectively, two fining twisted steel anchor pole (5) and the fixing steel plates (6) and bridge Dun Ding (1) anchoring of lifting main truss rear end through being embedded in bridge Dun Ding; Be welded with straight skidding track (7) respectively on two lifting main trusss; Two straight skidding tracks are provided with slippage i iron (8); Assembly pulley (9) is installed on the slippage i iron, bridge Dun Ding (1) rear hoist engine (10) is installed and be wound in hoist engine and assembly pulley on wire rope (11).
2. the heavy steel support hanging apparatus of bridge according to claim 1 is characterized in that being fixed with between straight skidding track (7) and the lifting main truss (2) and strengthens column (12) and diagonal brace (13).
3. the heavy steel support hanging apparatus of bridge according to claim 1 and 2 is characterized in that lifting main truss (2) and adopts the Hanging Basket main truss.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012200627692U CN202466422U (en) | 2012-02-24 | 2012-02-24 | Suspending device for heavy steel support of bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012200627692U CN202466422U (en) | 2012-02-24 | 2012-02-24 | Suspending device for heavy steel support of bridge |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202466422U true CN202466422U (en) | 2012-10-03 |
Family
ID=46914590
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012200627692U Expired - Fee Related CN202466422U (en) | 2012-02-24 | 2012-02-24 | Suspending device for heavy steel support of bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202466422U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103485539A (en) * | 2013-09-23 | 2014-01-01 | 中国五冶集团有限公司 | Construction control method for large direct-buried steel anchor fluke embedded part |
CN118221014A (en) * | 2024-05-27 | 2024-06-21 | 中铁二局集团有限公司 | Lifting device for cross beam and mounting method thereof |
-
2012
- 2012-02-24 CN CN2012200627692U patent/CN202466422U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103485539A (en) * | 2013-09-23 | 2014-01-01 | 中国五冶集团有限公司 | Construction control method for large direct-buried steel anchor fluke embedded part |
CN103485539B (en) * | 2013-09-23 | 2015-08-19 | 中国五冶集团有限公司 | The construction control method of large-scale direct burial steel anchor fluke built-in fitting |
CN118221014A (en) * | 2024-05-27 | 2024-06-21 | 中铁二局集团有限公司 | Lifting device for cross beam and mounting method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105565176B (en) | A kind of asymmetric cable crane of single column | |
CN204690605U (en) | The self-propelled triangular truss hanging basket of large span beam bridge | |
CN103061264B (en) | Method and device for pre-pressing high-position support single column in water | |
CN203923924U (en) | No. 0 section bracket prepressing device | |
CN105239510A (en) | Dismounting beam support used for high pier small-radius curve cast-in-situ box beam and construction method | |
CN203699694U (en) | Bearing cable or wind-cable pre-stress anchoring device for cable crane | |
CN204080650U (en) | A kind of end bay for road and bridge construction closes up suspension bracket | |
CN103074871B (en) | Arc-shaped slope concrete sliding and lifting template | |
CN205604080U (en) | Building construction platform | |
CN202466422U (en) | Suspending device for heavy steel support of bridge | |
CN103046669A (en) | Prefabricated high strength reinforced concrete shear wall with low strength energy dissipation strip and fabrication method | |
CN107419670A (en) | Hybrid structure of arch and beam formula continuous rigid frame bridge winds up walking cradle construction device and method | |
CN203716044U (en) | Low bearing or middle bearing cable arch combined structural bridge | |
CN204625045U (en) | A kind of steel structure hoisting door shaped stent formula hanging apparatus | |
CN206692230U (en) | A kind of skyscraper row is hung | |
CN204151798U (en) | A kind of steel reinforced concrete anti-slide pile structure | |
CN102926388A (en) | Earth moving device and method for deep foundation pit excavation | |
CN202989781U (en) | Width widened cast-in-place box beam moving support | |
CN105603890A (en) | Extradosed type external cable reinforced girder bridge | |
CN203174882U (en) | Shock resistant composite beam for housing building | |
CN202766985U (en) | Construction device for variable cross-section cantilever box girder | |
CN204530506U (en) | End bay closing device | |
CN206108724U (en) | Simple and easy installing support device of long large -diameter pile base steel reinforcement cage self -control | |
CN211871179U (en) | Arch bridge cable crane pile beam type anchorage structure | |
CN211074121U (en) | Prefabricated prestressed reinforced concrete box girder tensioning platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121003 Termination date: 20200224 |
|
CF01 | Termination of patent right due to non-payment of annual fee |