CN202447582U - Conveyer device for six-ton die forging production line of flange - Google Patents

Conveyer device for six-ton die forging production line of flange Download PDF

Info

Publication number
CN202447582U
CN202447582U CN2011205795219U CN201120579521U CN202447582U CN 202447582 U CN202447582 U CN 202447582U CN 2011205795219 U CN2011205795219 U CN 2011205795219U CN 201120579521 U CN201120579521 U CN 201120579521U CN 202447582 U CN202447582 U CN 202447582U
Authority
CN
China
Prior art keywords
flange
production line
die forging
tons
forging production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011205795219U
Other languages
Chinese (zh)
Inventor
周英志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO HANA HEAVY INDUSTRY CO LTD
Original Assignee
QINGDAO HANA HEAVY INDUSTRY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO HANA HEAVY INDUSTRY CO LTD filed Critical QINGDAO HANA HEAVY INDUSTRY CO LTD
Priority to CN2011205795219U priority Critical patent/CN202447582U/en
Application granted granted Critical
Publication of CN202447582U publication Critical patent/CN202447582U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a conveyer device for a six-ton die forging production line of a flange. The device comprises a frame, and a conveying chain and a driving device are arranged on the frame, and are connected with each other. The device is simple in structure, convenient to operate, time-saving, labor-saving, energy-saving and high in working efficiency, and the whole forging steps are connected through the conveying chain.

Description

Six tons of die forging production line conveying apparatus of flange
Technical field
The utility model relates to the transport in the flange forging process, specifically, relates to the flange transport in six tons of die forging production lines of a kind of flange.
Background technology
Forge in the process at flange; Especially in the whole operation that die forging is forged; Normally tick the flange blank, be carried to 2 tons of pneumatic hammer places by machinery operator by manual work, carry out base through 2 tons of pneumatic hammers after; Be carried to six tons of die forgings by forging type hammer out by machinery operator, be carried to 1000 tons of pressure bead cutter punchings through machinery operator again and cut edge.At last, be carried to tank and carry out solution treatment.The whole machining process process wastes time and energy and inefficiency owing to all operate with the operator of operating machine through manual pick.
The utility model content
The utility model forges the problems referred to above that exist in the process to existing flange, has proposed six tons of die forging production line conveying apparatus of flange of a kind of simple in structure, easy to operate, high efficiency.
The technical scheme of the utility model is: six tons of die forging production line conveying apparatus of a kind of flange, and this device comprises framework, and carrier chain and drive unit are installed on the framework, carrier chain is connected with drive unit.
Preferably, drive unit comprises motor and speed reducer, and motor is connected with reductor through belt, and reductor is connected with carrier chain.
Preferably, described base of frame is provided with the support of support frame.
The beneficial effect of the utility model is: the utility model is simple in structure, and is easy to operate, through carrier chain whole forging process coupled together, time saving and energy saving, energy savings, high efficiency.
Description of drawings
Accompanying drawing 1 is the structural representation of the utility model specific embodiment;
Accompanying drawing 2 is the face of the bowing structural representation of the utility model specific embodiment.
The specific embodiment
For structure, characteristic and other purpose that can further understand the utility model, combine accompanying drawing and appended embodiment to specify as follows at present, illustrated embodiment only is used to explain the technical scheme of the utility model, and non-limiting the utility model.
Six tons of die forging production line conveying apparatus of a kind of flange, this device comprises framework 1, framework 1 bottom is provided with the support 5 of support frame 1.Carrier chain 2 and drive unit are installed on the framework 1, and carrier chain 2 is connected with drive unit.Drive unit comprises motor 3 and reductor 4, and motor 3 is connected with reductor 4 through belt, and reductor 4 is connected with carrier chain 2.
During work, motor 2 drives reductor 4 work through belt, and reductor 4 drives carrier chain 2 and rotates; Power is provided for carrier chain 2, and after reductor 4 slowed down, the moment of torsion that offers carrier chain 2 was bigger; The flange forging is ticked the blank in the heating furnace in process, is placed on the carrier chain 2; Be delivered to 2 tons of pneumatic hammer bases, six tons of die hammer moulding and 1000 tons of pressure bead cutter punchings successively by carrier chain 2 and cut edge, be delivered to tank at last and carry out solution treatment, accomplish each forging process.

Claims (3)

1. six tons of die forging production line conveying apparatus of a flange, it is characterized in that: this device comprises framework (1), and carrier chain (2) and drive unit are installed on the framework (1), carrier chain (2) is connected with drive unit.
2. six tons of die forging production line conveying apparatus of flange as claimed in claim 1 is characterized in that: drive unit comprises motor (3) and reductor (4), and motor (3) is connected with reductor (4) through belt, and reductor (4) is connected with carrier chain (2).
3. like claim 1 or six tons of die forging production line conveying apparatus of 2 any described flanges, it is characterized in that: described framework (1) bottom is provided with the support (5) of support frame (1).
CN2011205795219U 2011-12-31 2011-12-31 Conveyer device for six-ton die forging production line of flange Expired - Fee Related CN202447582U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011205795219U CN202447582U (en) 2011-12-31 2011-12-31 Conveyer device for six-ton die forging production line of flange

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011205795219U CN202447582U (en) 2011-12-31 2011-12-31 Conveyer device for six-ton die forging production line of flange

Publications (1)

Publication Number Publication Date
CN202447582U true CN202447582U (en) 2012-09-26

Family

ID=46863476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011205795219U Expired - Fee Related CN202447582U (en) 2011-12-31 2011-12-31 Conveyer device for six-ton die forging production line of flange

Country Status (1)

Country Link
CN (1) CN202447582U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103909197A (en) * 2013-01-07 2014-07-09 苏州昆仑重型装备制造有限公司 Blank conveying device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103909197A (en) * 2013-01-07 2014-07-09 苏州昆仑重型装备制造有限公司 Blank conveying device
CN103909197B (en) * 2013-01-07 2016-12-28 苏州昆仑重型装备制造有限公司 Stock conveyer device

Similar Documents

Publication Publication Date Title
CN102861855B (en) Automatic riveting device
CN203875888U (en) Workpiece turn-over and transfer mechanism on stamping production line
CN202639243U (en) Automatic box turnover machine
CN202219284U (en) Multi-station continuous punching machine
CN202387911U (en) Heavy-duty vehicle brake block riveting machine
CN203304436U (en) Automatic feeding device of punching machine tool
CN202447582U (en) Conveyer device for six-ton die forging production line of flange
CN202863790U (en) Full-automatic metal strip welding packaging machine
CN202333038U (en) Improved storage battery pole piece brushing machine
CN203574512U (en) Efficient multi-station rotor sheet sorting machine
CN202943314U (en) Cross hole machining device in steering gear valve body
CN202387793U (en) Crimping machine for solar water heater tank
CN202824501U (en) Automatic riveting equipment
CN201324990Y (en) Elevator
CN103848192A (en) Rotary lifting conveyor
CN103658288B (en) Hardware & tools blanking device
CN203574510U (en) Efficient multi-station stator sheet sorting machine
CN102699161B (en) Workpiece rotating stamping die
CN202387918U (en) Oil pressure riveting machine
CN204727157U (en) A kind of C-type steel overturn conveying apparatus
CN102101150A (en) Knife-net riveting rotary mechanism
CN203649096U (en) Hardware tool discharge device and feed equipment special for hardware tool discharge device
CN202450120U (en) Integrated solution treatment device of flange six-ton die forging production line
CN203156057U (en) Material loading, feeding and discharging device in turning of oil pipe and oil sucker rod
CN103723493A (en) Reversing feeding device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
DD01 Delivery of document by public notice

Addressee: Qingdao Hana Heavy Industry Co.,Ltd.

Document name: Notification to Pay the Fees

DD01 Delivery of document by public notice

Addressee: Qingdao Hana Heavy Industry Co.,Ltd.

Document name: Notification of Termination of Patent Right

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120926

Termination date: 20141231

EXPY Termination of patent right or utility model