CN202380642U CN 201120562575 CN201120562575U CN202380642U CN 202380642 U CN202380642 U CN 202380642U CN 201120562575 CN201120562575 CN 201120562575 CN 201120562575 U CN201120562575 U CN 201120562575U CN 202380642 U CN202380642 U CN 202380642U
Authority
CN
China
Prior art keywords
muscle
wall
main
ribs
distance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201120562575
Other languages
Chinese (zh)
Inventor
陈霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSCEC Strait Construction and Development Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority to CN 201120562575 priority Critical patent/CN202380642U/en
Application granted granted Critical
Publication of CN202380642U publication Critical patent/CN202380642U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model relates to a ladder rib, which is characterized by comprising a pair of main ribs which are respectively disposed on the left side and the right side and parallel to each other and a plurality of stepping ribs which are perpendicularly and fixedly connected between the two main ribs and sequentially distributed at intervals along the extending direction of the main ribs. The stepping ribs located at the two ends and the middle of the main ribs are top mold ribs, and the stepping ribs located at other parts of the main ribs are framework ribs. The distance between end portions of the top mold ribs and the main ribs close to corresponding end portions is equal and larger than the distance between corresponding end portions of the framework ribs and the main ribs close to the corresponding end portions. The length of each top mold rib is = wall thickness - reserved wall expansion value. The ladder rib is capable of effectively avoiding deviation caused by the fact that shear wall reinforcement is affected by subsequent handling, ensures construction quality of shear walls, and also is fast and convenient in construction and strong in operability.

Description

The ladder muscle
Technical field
The utility model relates to a kind of ladder muscle.
Background technology
Shear wall structure is a kind of structure commonly used in the modern architecture; At present owing to shear wall body of wall reinforcing bar is just simply formed by the colligation of transverse reinforcement and vertical reinforcement; Therefore influenced by subsequent handling such as template installation, concreting etc., cause mass defects such as body of wall reinforcing bar off normal and protective layer thickness deficiency.Traditional job practices can only be through the operation of joining a regular shift or class of mounting reinforcing steel bars worker when the concreting; Come the reinforcing bar of off normal is corrected; Consumption worker not only consuming time; And since construction quality depend on reinforcing bar footman operating personnel sense of responsibility and with the cooperating of concreting operation, so construction quality is unstable.
Summary of the invention
In order to solve existing in prior technology the problems referred to above; The utility model provides a kind of ladder muscle, and it not only can effectively avoid shear wall body of wall reinforcing bar influenced by subsequent handling and the off normal phenomenon that produces, guarantees the construction quality of shear wall; And it is convenient to construct, workable.
The utility model technical scheme is to constitute like this; A kind of ladder muscle is characterized in that: it comprises that a pair of left and right sides and parallel each other main muscle and Duo Gen vertical fixing of being divided into is connected between two main muscle and along the main muscle bearing of trend muscle of marking time spaced apart successively; The muscle of marking time that is positioned at main muscle two ends and middle part is the backform muscle, and the muscle of marking time that is positioned at other position of main muscle is the skeleton muscle; Each end of each root backform muscle is with identical near the distance between the main muscle of respective end and greater than the respective end of each root skeleton muscle and near the distance between the main muscle of this respective end, the length=thickness of wall body of each root backform muscle-reservation body of wall swell value.
Said reservation body of wall swell value is preferably 2mm.
Colligation between ladder muscle and the shear wall body of wall reinforcing bar is for ease fixed; When the length bearing of trend level of waiting to build cavity along body of wall when the main muscle of said ladder muscle was set up, adjacent two distances between the muscle of marking time=perpendicular placed body of wall to wait to build in the cavity and wait to build the distance between the length bearing of trend of cavity two vertical reinforcements adjacent one another are along body of wall; When the height bearing of trend of waiting to build cavity along body of wall when the main muscle of said ladder muscle vertically set up, adjacent two distance=horizontal cross of marking time between the muscle were arranged at that body of wall is waited to build in the cavity and wait to build the distance between the height bearing of trend of cavity two horizontal reinforcements adjacent one another are along body of wall.
For effective control body of wall protective layer thickness, the diameter x2 of the distance=thickness of wall body-body of wall protective layer thickness-main muscle between two main muscle.
The operating principle of the utility model technique scheme is explained as follows: during construction; Can the length bearing of trend level frame that the ladder muscle waits to build cavity along body of wall be established or waits that along body of wall the height bearing of trend of building cavity vertically sets up; Making being cross-linked of the main muscle of ladder muscle and the muscle of marking time carry out colligation between position and vertical reinforcement or the horizontal reinforcement fixes; Form stable reinforced bar support structure; Prevent to build the skew that process produces, the end through the backform rod leans the location and can guarantee the thickness of wall body of building template.
Compared to prior art; The utlity model has following advantage: the utility model is simple in structure, and is easy to use, and fastness is strong; The off normal phenomenon that not only can effectively avoid shear wall body of wall reinforcing bar influenced by subsequent handling and produce; Guarantee the construction quality of shear wall, and it is convenient to construct, workable.
Description of drawings
Fig. 1 is the example structure sketch map of a kind of ladder muscle of providing of the utility model.
Fig. 2 is the user mode sketch map of Fig. 1, and the main muscle of ladder muscle waits that along body of wall the length bearing of trend level of building cavity sets up among the figure, one or two colligation place of only having drawn among the figure, and all the other are corresponding to be cross-linked the place and also will to carry out corresponding colligation and fix.
Label declaration among the figure: 1, main muscle, 2, the backform muscle, 3, the skeleton muscle, 4, vertical reinforcement, 5, colligation place.
The specific embodiment
Below in conjunction with the Figure of description and the specific embodiment the utility model content is elaborated:
Be illustrated in figure 1 as the example structure sketch map of a kind of ladder muscle that the utility model provides, it is characterized in that: it comprises and a pair ofly is divided into the left and right sides and parallel each other main muscle 1 and the Duo Gen vertical fixing is connected between two main muscle 1 and along the main muscle 1 bearing of trend muscle of marking time spaced apart successively; The muscle of marking time that is positioned at main muscle 1 two ends and middle part is a backform muscle 2, and the muscle of marking time that is positioned at main muscle 1 other position is a skeleton muscle 3; Each end of each root backform muscle 2 is with identical near the distance between the main muscle 1 of respective end and greater than the respective end of each root skeleton muscle 3 and near the distance between the main muscle 1 of this respective end, the length=thickness of wall body of each root backform muscle 2-reservation body of wall swell value.
Said reservation body of wall swell value is 2mm.
When the length bearing of trend level of waiting to build cavity along body of wall when the main muscle 1 of said ladder muscle was set up, adjacent two distances between the muscle of marking time=perpendicular placed body of wall to wait to build in the cavity and wait to build the distance between the length bearing of trend of cavity two vertical reinforcements 4 adjacent one another are along body of wall; When the height bearing of trend of waiting to build cavity along body of wall when the main muscle 1 of said ladder muscle vertically set up, adjacent two distance=horizontal cross of marking time between the muscle were arranged at that body of wall is waited to build in the cavity and wait to build the distance between the height bearing of trend of cavity two horizontal reinforcements adjacent one another are along body of wall.
The diameter x2 of the distance=thickness of wall body-body of wall protective layer thickness-main muscle 1 between two main muscle 1.
The length of the backform muscle 2 at edge is exposed in two main muscle 1 ends can be identical or different, and when ladder muscle horizontal positioned, the length that two main muscle 1 expose can be identical; When the ladder muscle was vertically placed, the alternative shear wall vertical reinforcement of ladder muscle at this moment, according to job specfication, staggered in order to make butt joint, and the length that two main muscle 1 expose can be different.

Claims (5)

1. ladder muscle is characterized in that: it comprises and a pair ofly is divided into the left and right sides and parallel each other main muscle (1) and many vertical fixing are connected between two main muscle (1) and along main muscle (1) the bearing of trend muscle of marking time spaced apart successively; The muscle of marking time that is positioned at main muscle (1) two ends and middle part is backform muscle (2), and the muscle of marking time that is positioned at other position of main muscle (1) is skeleton muscle (3); Each end of each root backform muscle (2) is with identical near the distance between the main muscle (1) of respective end and greater than the respective end of each root skeleton muscle (3) and near the distance between the main muscle (1) of this respective end, the length=thickness of wall body of each root backform muscle (2)-reservation body of wall swell value.
2. ladder muscle according to claim 1 is characterized in that: said reservation body of wall swell value is 2mm.
3. ladder muscle according to claim 1 and 2 is characterized in that: a certain at least end end of two main muscle (1) is with the most different near the distance between the backform muscle (2) of this end.
4. ladder muscle according to claim 1 and 2; It is characterized in that: when the length bearing of trend level of waiting to build cavity along body of wall when the main muscle (1) of said ladder muscle was set up, adjacent two distances between the muscle of marking time=perpendicular placed body of wall to wait to build in the cavity and wait to build the distance between the length bearing of trend of cavity two vertical reinforcements (4) adjacent one another are along body of wall; When the height bearing of trend of waiting to build cavity along body of wall when the main muscle (1) of said ladder muscle vertically set up, adjacent two distance=horizontal cross of marking time between the muscle were arranged at that body of wall is waited to build in the cavity and wait to build the distance between the height bearing of trend of cavity two horizontal reinforcements adjacent one another are along body of wall.
5. ladder muscle according to claim 1 and 2 is characterized in that: the diameter x2 of the distance=thickness of wall body between two main muscle (1)-body of wall protective layer thickness-main muscle (1).
CN 201120562575 2011-12-29 2011-12-29 Ladder rib Expired - Lifetime CN202380642U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120562575 CN202380642U (en) 2011-12-29 2011-12-29 Ladder rib

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120562575 CN202380642U (en) 2011-12-29 2011-12-29 Ladder rib

Publications (1)

Publication Number Publication Date
CN202380642U true CN202380642U (en) 2012-08-15

Family

ID=46629154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120562575 Expired - Lifetime CN202380642U (en) 2011-12-29 2011-12-29 Ladder rib

Country Status (1)

Country Link
CN (1) CN202380642U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590039A (en) * 2018-05-07 2018-09-28 五冶集团上海有限公司 A kind of the ladder muscle and its application method of control shear wall vertical reinforcement spacing
CN109537813A (en) * 2018-11-14 2019-03-29 五冶集团上海有限公司 Application of the ladder muscle in shear force wall reinforcing steel bar spacing and protective layer thickness control

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590039A (en) * 2018-05-07 2018-09-28 五冶集团上海有限公司 A kind of the ladder muscle and its application method of control shear wall vertical reinforcement spacing
CN109537813A (en) * 2018-11-14 2019-03-29 五冶集团上海有限公司 Application of the ladder muscle in shear force wall reinforcing steel bar spacing and protective layer thickness control

Similar Documents

Publication Publication Date Title
CN106884541B (en) Positioning assembly, positioning device and positioning method for reserved dowel bars in shear wall
KR101462202B1 (en) Form traveller for through bridge
CN103774749A (en) Large-span prestressed concrete F plate frame structure system
US10400450B2 (en) Deck panel for construction
CN202380642U (en) Ladder rib
CN206216902U (en) Prefabricated bar body reinforcing bar binding tire film
CN204370803U (en) A kind of adjustable column template reinforces mould
CN203640278U (en) Stair construction die shelf
CN102071801A (en) Positioning method and structure for hollow pipes in concrete hollow slab
CN208396106U (en) Detachable bed die steel bar truss floor support plate
CN203200982U (en) Steel bar truss buckling hanging type floor support plate
CN217175688U (en) Assembled formwork connecting structure
CN205296583U (en) Novel box post
CN208266661U (en) Cable-stayed bridge wide cut beam lattice main beam structure and combinations thereof template system
CN205976216U (en) A steel structrual concrete supporting beam
CN103334582A (en) Method for installing and constructing short-leg shear wall formwork supporting system
CN209163439U (en) Tool-typed formwork installs structure at a kind of structure drop plate
CN208441463U (en) A kind of superelevation square column formwork reinforcement system
CN202227275U (en) Pier template for constructing faced concrete pier
CN203420470U (en) Installation construction structure of short-limb shear-wall formwork supporting system
CN202969887U (en) Bidirectional-stress full-house scaffold for structure construction of subway stations
CN208473283U (en) A kind of convenient production of construction materials formwork for placing of splicing
CN207392559U (en) A kind of Punching Shear peg in flat slab structure freezer
CN206220355U (en) A kind of long-span beams structure of use UHPC materials
CN207193775U (en) A kind of reinforcing shaping equipment of Cast-in-situ Beam exterior sheathing

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 350015 Block A, Zhongjian Strait Business Plaza, 60 Rujiangxi Road, Mawei District, Fuzhou City, Fujian Province (Free Trade Test Zone)

Patentee after: CSCEC Strait Construction and Development Co., Ltd.

Address before: 350000 No. 3 Construction Company of No. 148 Beihuan Middle Road, Fuzhou City, Fujian Province

Patentee before: The Third Company of China Seventh Engineering Bureau Co., Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120815