CN202370090U - Conversion support for large-span space crossed truss - Google Patents

Conversion support for large-span space crossed truss Download PDF

Info

Publication number
CN202370090U
CN202370090U CN2011205466527U CN201120546652U CN202370090U CN 202370090 U CN202370090 U CN 202370090U CN 2011205466527 U CN2011205466527 U CN 2011205466527U CN 201120546652 U CN201120546652 U CN 201120546652U CN 202370090 U CN202370090 U CN 202370090U
Authority
CN
China
Prior art keywords
truss
support
conversion
conversion support
lattice
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011205466527U
Other languages
Chinese (zh)
Inventor
郁政华
贾宝荣
俞媛妍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CN2011205466527U priority Critical patent/CN202370090U/en
Application granted granted Critical
Publication of CN202370090U publication Critical patent/CN202370090U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model relates to a conversion support for a large-span space crossed truss. The conversion support is characterized by consisting of a lattice temporary support and a top pitch point, wherein the lattice temporary support is formed by connecting a horizontal rod and a diagonal web member which respectively consist of a vertical circular pipe and double channel steel; and the top pitch point on the top of the lattice temporary support consists of a cutting plate welded on the top surface of the vertical circular pipe. The conversion support is characterized in that the cutting plate on the top surface of the vertical circular pipe is formed by welding a transverse erect thickened steel plate and four reinforcing steel plates which are perpendicular to the transverse erect thickened steel plate. The conversion support has the advantages that the problem that a main truss is installed after a secondary truss is installed due to the limit of fields and the problem of predeformation in truss span are solved; and the conversion support is safe, reliable and convenient to disassemble.

Description

A kind of conversion that is used for large span space intersection truss is supported
Technical field
The utility model relates to a kind of conversion that is used for large span space intersection truss to be supported.
Background technology
Large span space intersection truss, main couple and jack truss square crossing form the monolithic stability system.When structure was installed, adopt installed main couple earlier more, and the method for jack truss is installed in the back.Because truss span is big, in the main couple installation process, occur easily that the distortion of main couple span centre is excessive, stress surpasses problems such as design load.The engineering that has, because the place restriction can only be installed jack truss earlier, main couple is installed in the back, makes the problem of truss distortion, the ultra design load of stress highlight more.Therefore demand urgently the installation of large span space intersection truss is improved, to solve the truss distortion that in carrying out the installation of large span space intersection truss, is produced at present, the problem of the ultra design load of stress.
Summary of the invention
The purpose of the utility model is to solve in the prior art to intersect at large span space that truss is existing when installing the problem that the distortion of main couple span centre is excessive, stress surpasses design load to occur, provides a kind of large span space that is used for to intersect the conversion of truss and support.A kind of conversion that is used for large span space intersection truss of the utility model design is supported; It is characterized in that: described conversion is supported by interim support of lattice and top node and is formed; Interim horizon bar, the diagonal web member be made up of vertical pipe and Two bors d's oeuveres channel-section steel of supporting of lattice connects to form, and is made up of the knife plate that is welded on the vertical pipe end face in the top node of the interim support, top of lattice.It is characterized in that: the knife plate on vertical pipe end face by one laterally erect add steel plate and four perpendicular reinforcement steel plates welding constitute.The utility model has the advantages that to have solved because of the place restriction that the essential jack truss of installation earlier is the problem of main couple again, solved the problem of truss span centre predeformation, this support pattern is safe and reliable, unloads carried convenient.
Description of drawings
Fig. 1 is the user mode sketch map of the utility model.
Fig. 2 is the top node structural representation of the utility model, and Fig. 3 is the vertical view of Fig. 2.
Below in conjunction with accompanying drawing and construction embodiment the utility model is made detailed operation instruction.
The specific embodiment
Conversion described in the figure is supported by the interim support 1 of lattice and is formed with top node 2; Interim horizon bar, the diagonal web member be made up of vertical pipe 3 and Two bors d's oeuveres channel-section steel 4 of supporting of lattice connects to form, and is made up of the knife plate 5 that is welded on the vertical pipe end face in the top node of the interim support, top of lattice.It is characterized in that: the knife plate on vertical pipe end face is welded with four blocks of perpendicular reinforcement steel plates 7 and is constituted by a steel plate of laterally erectting 6 that adds.
Operating principle is through the span centre at truss 8 at least one interim support to be set, and converts truss into the multispan continuous trusse by the truss of two ends freely-supported.The minimizing truss is installed distortion and is difficult to control, the ultra design load of stress because of span is excessive.In the conversion support top end knife plate of controlling absolute altitude is set, truss is carried out predeformation control.
During practical implementation, when truss is installed, earlier the truss two ends are shelved structurally, span centre is shelved on conversion and supports.After treating the structural system installation, carry out the unloading that the span centre conversion is supported again.During unloading, progressively cut off the top knife plate, make the final free downwarp of truss span centre, structural stress converts.
Through the method for interim support is set at the truss span centre, reduce the span of main couple or jack truss, span centre distortion of control truss and stress.This support pattern is safe and effective to distortion of control truss and stress, has also reduced the segmentation of truss, practices thrift duration and construction cost.

Claims (2)

1. a conversion that is used for large span space intersection truss is supported; It is characterized in that: described conversion is supported by interim support of lattice and top node and is formed; Interim horizon bar, the diagonal web member be made up of vertical pipe and Two bors d's oeuveres channel-section steel of supporting of lattice connects to form, and is made up of the knife plate that is welded on the vertical pipe end face in the top node of the interim support, top of lattice.
2. intersect the conversion of truss and support by the described a kind of large span space that is used for of claim 1, it is characterized in that: the knife plate on vertical pipe end face by one laterally erect add steel plate and four perpendicular reinforcement steel plates welding constitute.
CN2011205466527U 2011-12-23 2011-12-23 Conversion support for large-span space crossed truss Expired - Fee Related CN202370090U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011205466527U CN202370090U (en) 2011-12-23 2011-12-23 Conversion support for large-span space crossed truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011205466527U CN202370090U (en) 2011-12-23 2011-12-23 Conversion support for large-span space crossed truss

Publications (1)

Publication Number Publication Date
CN202370090U true CN202370090U (en) 2012-08-08

Family

ID=46593798

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011205466527U Expired - Fee Related CN202370090U (en) 2011-12-23 2011-12-23 Conversion support for large-span space crossed truss

Country Status (1)

Country Link
CN (1) CN202370090U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107989351A (en) * 2017-11-28 2018-05-04 江苏速捷模架科技有限公司 Disk button quickly assembles truss platform structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107989351A (en) * 2017-11-28 2018-05-04 江苏速捷模架科技有限公司 Disk button quickly assembles truss platform structure

Similar Documents

Publication Publication Date Title
CN201671226U (en) Expanded flanged cross-shaped steel SRC column
CN202559571U (en) Net rack roof with siphon rainwater pipeline
CN104929290A (en) Large-span reinforced concrete orthogonal-diagonal open-web floor and manufacturing method thereof
CN106284838A (en) A kind of lattice Honeycomb Beam sections and large span lattice girder steel and fabrication and installation method thereof
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN204418510U (en) Floor support plate steel bar girder structure
CN202227480U (en) Floor roof connection structure of light-steel house
CN202370090U (en) Conversion support for large-span space crossed truss
CN100422468C (en) Large-span large-column distance quasi-ribbed floor type prestressed steel grid roof structure
CN2923870Y (en) Large-span large-pillar-distance quasi-rib type building-cover type prestress steel-grid roofing
CN103758342A (en) Tool-type top form for buildings
CN201671227U (en) SRC column with diagonally arranged cross steels with flanges
CN203213137U (en) Steel raft foundation for installing steel structure roof
CN202689585U (en) Ground fitting up assembly mould of large steel truss
CN205530324U (en) Miniature stake of thin -walled cold -formed steel
CN103397638A (en) Tie bar for supporting system in high-rigidity integral prestressed fabricated foundation pit support
CN204960324U (en) Suspension type floor formwork support device
CN103276889B (en) Full hall fastener type steel pipe scaffold anti-side shifting method
CN208267379U (en) A kind of trapezoidal steel structure support being used to support 24-32m cast-in-situ box girder and adjustable span
CN203451109U (en) I-shaped steel truss device for tower crane attachment
CN203487794U (en) Main assembling jig frame for large-span steel structure roof primary truss
CN204080617U (en) The bridge tower of many lattice room combining structure or bridge pier
CN205822498U (en) A kind of antidetonation body of wall
CN104674938A (en) Aseismic structure system capable of restoring functions
CN204826194U (en) Higher huge steel construction of security

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

Free format text: FORMER NAME: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 201802 Jiading District Shunda Road, Shanghai, No. 615

Patentee after: Shanghai Mechanized Construction Group Co., Ltd.

Address before: 201802 Jiading District Shunda Road, Shanghai, No. 615

Patentee before: Shanghai Mechanized Construction Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120808

Termination date: 20171223

CF01 Termination of patent right due to non-payment of annual fee