CN202336291U - Oxidation injection pipe of desulfurization absorption tower - Google Patents

Oxidation injection pipe of desulfurization absorption tower Download PDF

Info

Publication number
CN202336291U
CN202336291U CN2011205176577U CN201120517657U CN202336291U CN 202336291 U CN202336291 U CN 202336291U CN 2011205176577 U CN2011205176577 U CN 2011205176577U CN 201120517657 U CN201120517657 U CN 201120517657U CN 202336291 U CN202336291 U CN 202336291U
Authority
CN
China
Prior art keywords
accelerating tube
air
hole
tube
absorption tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011205176577U
Other languages
Chinese (zh)
Inventor
王秋平
程爱平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2011205176577U priority Critical patent/CN202336291U/en
Application granted granted Critical
Publication of CN202336291U publication Critical patent/CN202336291U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

The utility model discloses an oxidation injection pipe of a desulfurization absorption tower, and relates to a desulfurization spray type absorption tower fitting, in particular to a tower external oxidation injection pipe, which comprises a drooping accelerating tube (1) and a mixed diffusion tube (2), wherein an air suction accelerating hole (3) is arranged on the pipe wall of the lower end of the drooping accelerating tube (1), a splash-proof pipe segment (4) of the drooping accelerating tube (1) is sleeved on the periphery of the air suction accelerating hole (3) and forms a ring-shaped space with the outer wall of the drooping accelerating tube (1), the upper end of the splash-proof pipe segment (4) is opened, the splash-proof pipe segment (4) is higher than the air suction accelerating hole (3), the lower end of the splash-proof pipe segment (4) is connected with the outer wall of the drooping accelerating tube (1), and a mixed diffusion tube (2) is connected on the lower end of the drooping accelerating tube (1). The oxidation injection pipe of the desulfurization absorption tower has the advantages of simple structure, low construction cost and low maintenance charge.

Description

A kind of desulfuration absorbing tower oxidation playpipe
Technical field
The utility model relates to desulfurization fountain absorption tower accessory, is specifically related to utilize potential energy to promote the tower external oxidation playpipe of slurries oxidizing process.
Background technology
Desulfuration absorbing tower is to use physics and chemical method, removes sulfur dioxide in flue gas (SO 2) device or structures.
In multiple desulfuration absorbing tower; It is the fountain absorption tower that one type of absorption tower is arranged; Its groundwork process is to utilize slurry circulating pump will absorb slurries to be transported to the spraying layer that is made up of a plurality of nozzles; Form intensive atomization slurry spray district after absorbing the atomizer ejection of slurries by spraying layer, slurries contact with flue gas in the atomizing spray district, absorb the SO in the flue gas in contact process 2Deng pernicious gas, accomplish flue gas desulfurization, slurries descend slowly and lightly in the stock tank of bottom, absorption tower along inside, absorption tower.
Desulfurization is also claimed oxidation air with oxidation wind, is the oxidation air that equipment such as oxidation fan provide is transported in the pressure absorption tower slurries, for slurries provide oxygen, with the SO in the slurries 2, H 2SO 3, SO 3 2-Deng being oxidized to SO 4 2-And with slurries in Ca 2+Reaction forms CaSO 42H 2O.
The oxidation air source of the gas has various ways, but mainly is the conveying that relies on external driver device to provide power to carry out oxidation air, has the shortcoming of high, the not enough energy-conserving and environment-protective of complex structure, construction costs and maintenance cost.
Summary of the invention
The utility model technical problem to be solved is: the purpose of the utility model provides a kind of simple in structure, low low a kind of desulfuration absorbing tower oxidation playpipe of maintenance cost that reaches of cost.
The technical solution of the utility model is: it comprises the decline accelerating tube and mixes anemostat; Tube wall is provided with air-breathing acceleration hole to the decline accelerating tube in the lower end; The outer wall that the periphery of decline accelerating tube in place, air-breathing acceleration hole is with splashproof pipeline section and decline accelerating tube forms annular space; The upper end of splashproof pipeline section is uncovered and be higher than air-breathing acceleration hole, and the lower end of splashproof pipeline section is connected with decline accelerating tube outer wall, mixes anemostat and is connected decline accelerating tube lower end.
The technique effect of the utility model is: it has simple in structure, the low low advantage of maintenance cost that reaches of cost, and is specific as follows:
1, can be used to replace oxidation fan and perhaps reduce exerting oneself of oxidation fan, reach energy-conservation effect.
2, air-breathing acceleration hole inhaled air fully mixing in mixing anemostat, mixed slurry reflux is to the bottom, absorption tower, and flow process has increased by one times, has increased the time of contact of oxidation air and slurries, has improved the utilization rate of oxidation air.
3, the slurries pH value that is used to spray is lower, helps the slurries oxidation.
4, mix anemostat and can guarantee that slurry reflux has higher flow velocity when getting into the absorption tower if adopt the caliber identical with air-breathing acceleration hole.Guarantee that slurry stream has higher kinetic energy.
5, the function that there is automatic adjusting inspiratory capacity the air-breathing conciliation of air intake duct chamber is quickened in the decline of desulfuration absorbing tower high potential energy slurries, guarantees that operation is smooth and easy.
6, can adjust the oxidation air amount through the air inflow in the air-breathing acceleration of adjustment absorption tower high potential energy slurries decline accelerating tube hole, it is too high can not cause exporting the oxygen amount.
Description of drawings
Fig. 1 is the sectional structure chart of the utility model;
Fig. 2 is the assembly structure sketch map of the utility model.
The specific embodiment
Among Fig. 1, former smoke inlet 5, clean exhanst gas outlet 6, slurries gathering system 7, spray system 8.
As illustrated in fig. 1 and 2; It comprises decline accelerating tube 1 and mixes anemostat 2; Tube wall is provided with air-breathing acceleration hole 3 to decline accelerating tube 1 in the lower end, and the outer wall that the periphery of decline accelerating tube 1 in 3 places, air-breathing acceleration hole is with splashproof pipeline section 4 and decline accelerating tube 1 forms annular space, and the upper end of splashproof pipeline section 4 is uncovered and be higher than air-breathing acceleration hole 3; The lower end of splashproof pipeline section 4 is connected with decline accelerating tube 1 outer wall, mixes anemostat 2 and is connected decline accelerating tube 1 lower end.The annular space that splashproof pipeline section 4 and decline accelerating tube 1 surround has air-breathing conciliation and prevents the slurries function of splashing.
Said decline accelerating tube 1 lower end outwards is the bell mouth shape expansion.
Said air-breathing acceleration hole 3 is axial long shape hole.。
Said air-breathing acceleration hole 3 is long ellipse hole.Also can adopt the slotted hole of other form
The lower port of decline accelerating tube 1 in 3 places, air-breathing acceleration hole and with mix anemostat 2 connections and all adopt the two-phase alloys steel plate of wear resistant corrosion resistant to process.Mixing anemostat 2 can adopt and the identical pipeline of accelerating tube 1 caliber that descends.
The concise and to the point process of the external oxidation playpipe of desulfuration absorbing tower slurries work during operation:
1,1 reception of decline accelerating tube is from the slurries of slurries gathering system 7 slurries absorption cells; Slurries progressively quicken in the decline process; Through air-breathing acceleration hole 3 time; Suck the part air, slurries quicken (the acceleration here is near acceleration of gravity) rapidly, and slurries and AIR MIXTURES are back to the absorption tower through mix anemostat 2.
2, be back to the inner bigger bubble in absorption tower, under the effect of slurry stream, be sheared and form tiny bubble, tiny bubble is inner the rising on the absorption tower, accomplishes further oxidation.

Claims (4)

1. desulfuration absorbing tower oxidation playpipe; It is characterized in that; It comprises decline accelerating tube (1) and mixes anemostat (2); Tube wall is provided with air-breathing acceleration hole (3) to decline accelerating tube (1) in the lower end, and the outer wall that the periphery that decline accelerating tube (1) is located in air-breathing acceleration hole (3) is with splashproof pipeline section (4) and decline accelerating tube (1) forms annular space, and the upper end of splashproof pipeline section (4) is uncovered and be higher than air-breathing acceleration hole (3); The lower end of splashproof pipeline section (4) is connected with decline accelerating tube (1) outer wall, mixes anemostat (2) and is connected decline accelerating tube (1) lower end.
2. a kind of desulfuration absorbing tower oxidation playpipe as claimed in claim 1 is characterized in that, said decline accelerating tube (1) lower end outwards is the bell mouth shape expansion.
3. a kind of desulfuration absorbing tower oxidation playpipe as claimed in claim 1 is characterized in that said air-breathing acceleration hole (3) is axial long shape hole.
4. a kind of desulfuration absorbing tower oxidation playpipe as claimed in claim 3 is characterized in that said air-breathing acceleration hole (3) is long ellipse hole.
CN2011205176577U 2011-12-10 2011-12-10 Oxidation injection pipe of desulfurization absorption tower Expired - Lifetime CN202336291U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011205176577U CN202336291U (en) 2011-12-10 2011-12-10 Oxidation injection pipe of desulfurization absorption tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011205176577U CN202336291U (en) 2011-12-10 2011-12-10 Oxidation injection pipe of desulfurization absorption tower

Publications (1)

Publication Number Publication Date
CN202336291U true CN202336291U (en) 2012-07-18

Family

ID=46484997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011205176577U Expired - Lifetime CN202336291U (en) 2011-12-10 2011-12-10 Oxidation injection pipe of desulfurization absorption tower

Country Status (1)

Country Link
CN (1) CN202336291U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102397748A (en) * 2011-12-10 2012-04-04 程爱平 Oxidation spray pipe of desulfurization absorption tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102397748A (en) * 2011-12-10 2012-04-04 程爱平 Oxidation spray pipe of desulfurization absorption tower
CN102397748B (en) * 2011-12-10 2014-02-19 程爱平 Oxidation spray pipe of desulfurization absorption tower

Similar Documents

Publication Publication Date Title
CN204417203U (en) A kind of efflux aerator
CN110368787A (en) A kind of ozone denitration injection evenly mixing device
CN201404798Y (en) Uniform airflow distribution device of circulating fluidized bed
CN101537330A (en) Airflow uniform distribution device of circulating fluidized bed
CN202336291U (en) Oxidation injection pipe of desulfurization absorption tower
CN102397748B (en) Oxidation spray pipe of desulfurization absorption tower
CN206276217U (en) A kind of ladder shunting spray column
CN2925589Y (en) Jetting regenerator
CN204147762U (en) A kind of circulating fluid bed flue-gas desulfurizing device adopting special-shaped many venturi
CN207654961U (en) A kind of micro-nano bubble generator
CN206262348U (en) A kind of wet desulphurization tower
CN103908888B (en) Spraying spray desulfurizing tower
CN108671779B (en) A kind of fine gas bubbles generator
CN101993145A (en) Jet flow aerator
CN201896094U (en) Jet aerator
CN202700360U (en) Oxidation air spraying and sucking device used in desulfurizing absorption tower
CN102728211B (en) Device for injecting and inhaling in-tower oxidized air for desulfurizing absorption tower
CN102489135B (en) High potential energy slurry tower exterior oxidation spraying tube for desulfurization absorption tower
CN209576283U (en) Quickly along back reaction desulfurizing tower
CN105298594B (en) Smoke evacuation fluidic device
CN107198953A (en) Desulfurizing tower purifies exhaust system with chimney integrated fume
CN103962022A (en) Fluid mixing device with low pressure loss
CN104096467B (en) A kind of liquid strong oxidizing agent atomization desulphurization system and method
CN102728212B (en) Desulfurizing absorption tower provided with high-potential energy unpowered slurry mixing device
CN202221096U (en) Dynamic superposition spin-flow type desulfurization chimney

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20120718

Effective date of abandoning: 20140219

RGAV Abandon patent right to avoid regrant