- CN202329130U CN202329130U CN2011204688756U CN201120468875U CN202329130U CN 202329130 U CN202329130 U CN 202329130U CN 2011204688756 U CN2011204688756 U CN 2011204688756U CN 201120468875 U CN201120468875 U CN 201120468875U CN 202329130 U CN202329130 U CN 202329130U
- Authority
- CN
- China
- Prior art keywords
- melting
- refractory cement
- heating
- heating rods
- sample
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model relates to a novel molten sample furnace which is simple in structure and used for observing the inside situation. The novel molten sample furnace consists of a steel furnace frame (1), four heating rods (2), metal rings (3), a refractory cement board (4), six melting tanks (5) and a power supply (6) and is characterized in that the four longitudinally-arranged heating rods (2) are embedded into the steel furnace frame (1) and are fixedly arranged on the lower surface of the upper part of the steel furnace frame (1) by the metal rings (3); the rectangular refractory cement board (4) is embedded in the upper part of the steel furnace frame (1); and the six melting tanks (5) are arranged on the refractory cement board (4). The novel molten sample furnace has the beneficial effects that each heating rod (2) adopts a silicon carbide rod with high heat conductivity; as the distances between each melting tank (5) and the adjacent two heating rods (2) are equal, the heated situations of each melting tank (5) are identical; and as no shelter is arranged on each melting tank (5), an operator is convenient for observing the change situation of a sample in the melting tank (5), so that the super-fusion phenomenon caused by no visibility is avoided, and the time required by observation is simultaneously reduced.
Description
Technical field
The utility model relates to a kind of sample-melting stove, relates in particular to a kind of novel sample-melting stove.
Background technology
When a kind of unknown solid matter is detected, often to detect its fusing point.Sample-melting stove is a kind of device that is used for specially to solid matter heating, can solid-state material be fused into liquid state through it, thereby reach the mensuration to melting point substance.Sample-melting stove in the market can not directly be observed its molten state when unknown sample being carried out the fusing point detection, occur melting phenomenon sometimes, and the result is measured in influence.
Summary of the invention
In order to solve the problems of the technologies described above; The utility model provides a kind of simple in structure, the novel sample-melting stove that can observe inner case, is made up of steel grate (1), heating rod (2), becket (3), refractory cement plate (4), melting channel (5), power supply (6), it is characterized in that the heating rod two ends are provided with becket; Four heating rods of vertically arranging embed the steel grate; And be fixed on the lower surface on steel grate top through becket, and four heating rods are in same horizontal plane and are parallel to each other, and the distance between adjacent heating rod is identical; The top of steel grate is embedded with rectangular refractory cement plate; The refractory cement plate is provided with six melting channels, and columniform melting channel is by two row, three row proper alignment, and every row are provided with two melting channels and are positioned between two adjacent heating rods.
The beneficial effect of the utility model is: heating rod adopts the silicon carbide rod with high-termal conductivity; Melting channel is identical with the distance of adjacent two heating rods; Therefore the situation of being heated of each melting channel is identical, does not have shelter on the melting channel, is convenient to the situation of change that the operator observes sample in the melting channel; Avoided phenomenon not occurring melting, reduced the time that observation station needs simultaneously owing to visual.
Description of drawings
Fig. 1 is the structural representation of the utility model;
Fig. 2 is the device sketch map of the utility model.
The specific embodiment
According to Fig. 1, shown in Figure 2; Heating rod (2) two ends are provided with becket (3), and becket (3) plating nickel on surface, four heating rods parallel to each other (2) are fixed on the lower surface on steel grate (1) top through becket (3); The two ends of heating rod (2) link to each other with power supply (6); Heating rod (2) adopts the carborundum with high-termal conductivity, and after the energized (6), heating rod (2) can redden in heating; The top of steel grate (1) is embedded with rectangular refractory cement plate (4); Refractory cement plate (4) is provided with six columniform melting channels (5); Melting channel (5) is whenever shown two melting channels (5) by two row, three row proper alignment, is positioned between adjacent two heating rods (2); The sample that will measure fusing point is placed in the melting channel (5); After the energized (6); Heating rod (2) the heating generation heat that reddens heats for the sample in the melting channel (5), and sample is slowly melted; The fusion process operator of sample can very clearly observe, and the temperature of sample can detect through the Non-contact Infrared Temperature Measurement appearance.
Claims (1)
1. novel sample-melting stove; Constitute by steel grate (1), heating rod (2), becket (3), refractory cement plate (4), melting channel (5), power supply (6); It is characterized in that heating rod (2) two ends are provided with becket (3), four heating rods of vertically arranging (2) embed steel grate (1), and are fixed on the lower surface on steel grate (1) top through becket (3); Four heating rods (2) are in same horizontal plane and are parallel to each other; Distance between adjacent heating rod (2) is identical, and the top of steel grate (1) is embedded with rectangular refractory cement plate (4), and refractory cement plate (4) is provided with six melting channels (5); Columniform melting channel (5) is by two row, three row proper alignment, and every row are provided with two melting channels (5) and are positioned between adjacent two heating rods (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011204688756U CN202329130U (en) | 2011-11-23 | 2011-11-23 | Novel molten sample furnace |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011204688756U CN202329130U (en) | 2011-11-23 | 2011-11-23 | Novel molten sample furnace |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202329130U true CN202329130U (en) | 2012-07-11 |
Family
ID=46441111
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011204688756U Expired - Fee Related CN202329130U (en) | 2011-11-23 | 2011-11-23 | Novel molten sample furnace |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202329130U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102914155A (en) * | 2012-11-15 | 2013-02-06 | 天津口岸检测分析开发服务有限公司 | Sample melting furnace |
CN105136530A (en) * | 2015-06-25 | 2015-12-09 | 国家电网公司 | On-site detection method for cable shielding layer material |
-
2011
- 2011-11-23 CN CN2011204688756U patent/CN202329130U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102914155A (en) * | 2012-11-15 | 2013-02-06 | 天津口岸检测分析开发服务有限公司 | Sample melting furnace |
CN105136530A (en) * | 2015-06-25 | 2015-12-09 | 国家电网公司 | On-site detection method for cable shielding layer material |
CN105136530B (en) * | 2015-06-25 | 2017-10-17 | 国家电网公司 | A kind of in-situ check and test method of cable shield material |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103713007B (en) | The softening drippage point of sintering deposit experimental apparatus for testing | |
CN202442935U (en) | Integrated measuring device for physical property of high temperature melting body | |
CN101153837A (en) | Dynamic testing method and system for wetting property | |
CN202329130U (en) | Novel molten sample furnace | |
CN105057857A (en) | Process method for assembling and welding pile leg of ocean platform | |
CN103399031A (en) | Novel sintering pot test research apparatus | |
CN104155339A (en) | Experimental platform for melt dripping and ignition of vertically-fixed thermoplastic material | |
CN202382874U (en) | Platinum channel thermocouple temperature measuring device | |
CN205786056U (en) | A kind of test material preparation device measuring asphalt surface free energy | |
CN203422331U (en) | Novel sintering pot experimental research device | |
CN204330151U (en) | A kind of pipeline thermometric and stationary installation | |
CN201184829Y (en) | Detection heater for crystallizer electric thermo-couple | |
CN104154750B (en) | A kind of system measuring metallurgical insulation material heat insulation effect | |
CN203816648U (en) | Heatable temperature control bitumen holding basin | |
CN203518589U (en) | High-temperature test furnace | |
CN204903434U (en) | A contrast device that is used for detecting adj. tabular building materials heat -proof quality | |
CN107860228A (en) | A kind of refractory material heat conduction detection trial furnace and its detection method | |
CN204203137U (en) | Ash melting testing tool and pallet thereof | |
CN204924998U (en) | Softening point detection device | |
CN207456174U (en) | A kind of refractory material heat conduction detects trial furnace | |
CN106248456A (en) | A kind of ash prod cast tool | |
CN202598625U (en) | Electromagnetic oven | |
CN220136378U (en) | Crucible supporting system | |
CN102706766A (en) | Molybdenum laser thermal fatigue test device | |
CN204214665U (en) | Material access device is used in a kind of high temperature furnace test |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120711 Termination date: 20121123 |