CN202302576U - Adjustable foundation bolt for mounting equipment with larger vibration - Google Patents

Adjustable foundation bolt for mounting equipment with larger vibration Download PDF

Info

Publication number
CN202302576U
CN202302576U CN 201120426194 CN201120426194U CN202302576U CN 202302576 U CN202302576 U CN 202302576U CN 201120426194 CN201120426194 CN 201120426194 CN 201120426194 U CN201120426194 U CN 201120426194U CN 202302576 U CN202302576 U CN 202302576U
Authority
CN
China
Prior art keywords
equipment
screw rod
center hole
anchor slab
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120426194
Other languages
Chinese (zh)
Inventor
姜青国
李海明
王伟
董玉启
熊浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin MCC20 Construction Co Ltd
Original Assignee
Tianjin MCC20 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin MCC20 Construction Co Ltd filed Critical Tianjin MCC20 Construction Co Ltd
Priority to CN 201120426194 priority Critical patent/CN202302576U/en
Application granted granted Critical
Publication of CN202302576U publication Critical patent/CN202302576U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses an adjustable foundation bolt for mounting equipment with larger vibration. The adjustable foundation bolt constitutively comprises a screw rod and a sleeve arranged outside the screw rod; the upper end of the sleeve is provided with an upper anchor plate provided with a center hole; the lower end of the sleeve is provided with a lower anchor plate provided with a center hole; the upper end of the screw rod, which stretches out of the center hole of the upper anchor plate, is provided with a retaining nut; a shear block is welded on the upper anchor plate; the lower end of the screw rod, which stretches out of the center hole of the lower anchor plate, is in threaded connection with a positioning nut; and the positioning nut is welded at the bottom of the lower anchor plate. The adjustable foundation bolt has the advantages that the process is simple; the manufacturing is convenient; the labor power, material resources and time are saved; the adjustable foundation bolt has a certain adjustment amount; not only is the mounting precision of the equipment guaranteed, but also a bolt hole of a bottom board of the equipment is not necessary to be enlarged; and the integrality of the mounted equipment and a foundation is enhanced, so as to guarantee the normal running of the equipment with the larger vibration.

Description

Be used to install the adjustable ground foot bolt of vibrations than large equipment
Technical field
The utility model relates to a kind of fastening or engineering element that fixed equipment is used, and in particular, the utility model relates to a kind of stone bolt of vibrations than large equipment that be used to install.
Background technique
General stone bolt is in order to fixed equipment among the concreting basis time is embedded in the basis.Equipment is installed and is mainly contained two types with stone bolt traditionally:
One of which is the placement of concrete basis at equipment to be installed place, and on the basis, reserves anchor (bolt) hole, treats to install when equipment is installed stone bolt again, after the equipment adjustment is qualified, expects second pouring with pea gravel concreten or from levelling grouting again.Such bolt is not high to the required precision in pre-embedded anchoring bolts hole, but can only be used for stressed less position or less important position.
They are two years old; Be the direct-burried stone bolt, require stone bolt to be fixed on the bolt frame inspection bolt center line and the qualified after-pouring concrete of absolute altitude at equipment to be installed place; And in the concreting process, note the variation of inspection bolt center line and absolute altitude; In time proofread and correct simultaneously, the equipment of treating carries out the handing-over of bolt when installing checks and accepts, and secondary is built the grouting material after equipment is installed adjustment.Such bolt usually is used for stressed bigger position, is that the center permissible error of requirement pre-embedded anchoring bolts is ± 2 millimeters to the installation precision of bolt among the GB50204-2002 " concrete structure engineering construction quality acceptance specification ".
So high required precision has increased the difficulty of civil engineering, and especially in concreting process, the shaking force of concrete impact force and vibrating spear is all installed bolt and produced considerable influence.Some engineering is to find just that when civil engineering specialty and equipment are installed specialty handing-over examination bolt position and absolute altitude deviation are excessive; The correction and stone bolt does not allow to get angry; So; Can only the bolt hole of equipment be enlarged, with the installation precision of assurance equipment, and this correction mode often has a negative impact to equipment operation.
For guaranteeing that the equipment smooth installation carries out and guarantee the installation precision of equipment, can finely tune stone bolt when being preferably in erection unit, therefore, adopted the tup bolt in some engineering.Described tup bolt belongs to a kind of special shape of direct-burried bolt; Mounting type as the one of which is: when concrete foundation is built, special moulding box (anchor plate) is embedded in the basis; Like this, can when erection unit, dismantle or a certain amount of adjustment stone bolt.But the processing of tup bolt is difficulty relatively, complex process, and most owners are reluctant to adopt.
The model utility content
The utility model technical problem to be solved remedies the defective of above-mentioned existing technology exactly, and a kind of adjustable ground foot bolt of vibrations than large equipment that be used to install is provided for this reason.
The technique effect of the utility model is achieved through following technological scheme:
A kind ofly be used to install the adjustable ground foot bolt of vibrations, comprise screw rod and be arranged on the outside sleeve pipe of said screw rod than large equipment; The upper end of said sleeve pipe is provided with the last anchor slab that has center hole, and the lower end of said sleeve pipe is provided with the following anchor slab that has center hole; Said screw rod stretches out said upper end of going up the anchor slab center hole and is provided with tightening nut, welding shearing piece on the described upward anchor slab; Said screw rod stretches out the said lower end of anchor slab center hole down and is threaded with setscrew nut, and described setscrew nut is welded on the said bottom of anchor slab down.
The said diameter of going up center hole on the anchor slab equals the diameter of said sleeve pipe.
The diameter of center hole is greater than the diameter 1~3mm of said screw rod on the said anchor slab down.
The beneficial effect of the utility model is:
(1) only need common engineering elements such as steel pipe, steel plate, nut just can accomplish processing, technology is simple, saves human and material resources, time.
(2) can reliably be connected with fixing frame, have certain adjustment amount, thereby guarantee precision of equipment installation.
(3) can be after detecting himself installation precision equipment in place, and after the detection facility installation precision pouring grouting material, both guaranteed precision of equipment installation, need not to enlarge the bolt hole of equipment bay again.
(4) setting of said shearing-resistance blocks has strengthened the equipment that is mounted and basic integrity, can guarantee to shake the normal operation than large equipment.
Description of drawings
Fig. 1 is the structural representation of the utility model;
Fig. 2 is the installation situation schematic representation after the utility model is accomplished grouting.
Among the figure: 1--screw rod 2--tightening nut 3--shearing-resistance blocks 4--goes up anchor slab 8-setscrew nut 9--equipment bay 10--base concrete under the anchor slab 5--sleeve pipe 6-grouting material 7--
Embodiment
For the utility model is understood more easily, the technological scheme of the utility model is done to specify below in conjunction with accompanying drawing and embodiment.
Fig. 1 shows the structure of the utility model, and Fig. 2 shows the installation situation after the utility model is accomplished grouting.Visible with reference to Fig. 1, Fig. 2:
The utility model is used to install the adjustable ground foot bolt of vibrations than large equipment, and its formation comprises screw rod 1, and the outer installment of said screw rod 1 has the sleeve pipe 5 with its concentric;
The upper end of said sleeve pipe 5 is provided with anchor slab 4, and described going up on the anchor slab 4 has center hole, and the diameter of this center hole equals the diameter of said sleeve pipe 5, welding shearing piece 3 on the anchor slab 4 on described;
The lower end of said sleeve pipe 5 is provided with down anchor slab 7, also has center hole on the described following anchor slab 7, and the diameter of this center hole is greater than the diameter 1~3mm of said screw rod 1, and the setscrew nut 8 with described screw rod 1 concentric is welded in the bottom of said anchor slab 7 down;
Described screw rod 1 stretches out said upper end of going up anchor slab 4 center holes and is provided with the tightening nut 2 that is used for fixing equipment bay 9, and described screw rod 1 stretches out the said lower end of anchor slab 7 center holes down and is threaded with described setscrew nut 8.
With described setscrew nut 8 and the purpose that described anchor slab 7 down is welded as a whole, prevent exactly that described screw rod 1 is in course of adjustment to rotate.
The installation method of the utility model is following:
(1) when installation, such assembled earlier that the utility model is as shown in Figure 1, the part that then wherein said screw rod 1 top is exposed (comprising the described anchor slab 4 of going up) is sealed protection with adhesive tape;
(2) the utility model that assembles is placed the anchor bolt fixing frame, adjust the position of said screw rod 1 and check said screw rod 1 center line and absolute altitude qualified after, build Equipment Foundations concrete 10;
(3) treat that the Equipment Foundations health reaches strength grade of concrete after, protection things such as adhesive tape are removed, check once more whether the position of said screw rod 1 correct; If deviation is arranged; Instruments such as jack capable of using are rectified a deviation (but the correction of forbidding to get angry), rectify a deviation qualified after, the equipment installation in position;
(4) equipment in place is adjusted; To be tested fold lattice after; In the cavity of said sleeve pipe 5, build grouting material 6, treat that the grouting material reaches after the strength grade, in the screw rod that passes equipment bay 91 upper end; Fastening through said tightening nut 2 links together described anchor slab 7, Equipment Foundations 10, equipment bay 9 down with described screw rod 1 securely;
(5) last, will be welded as a whole with described equipment bay 9 again with the said shearing-resistance blocks 3 that described upward anchor slab 4 welds together, strengthen the whole soundness of equipment in place and Equipment Foundations with this.
Abovely with reference to accompanying drawing and embodiment the utility model is schematically described, this description does not have restricted.Those of ordinary skill in the art will be understood that in practical application the set-up mode of each parts all some change possibly take place in the utility model, and other staff also possibly make similar Design under its enlightenment.Only it is pointed out that otherwise break away from the design aim of the utility model that all conspicuous change and similar Design thereof all are included within the protection domain of the utility model.

Claims (3)

1. one kind is used to install the adjustable ground foot bolt of vibrations than large equipment, comprises screw rod, it is characterized in that the outer installment of said screw rod has sleeve pipe; The upper end of said sleeve pipe is provided with the last anchor slab that has center hole, and the lower end of said sleeve pipe is provided with the following anchor slab that has center hole; Said screw rod stretches out said upper end of going up the anchor slab center hole and is provided with tightening nut, welding shearing piece on the described upward anchor slab; Said screw rod stretches out the said lower end of anchor slab center hole down and is threaded with setscrew nut, and described setscrew nut is welded on the said bottom of anchor slab down.
2. according to claim 1ly be used to install the adjustable ground foot bolt of vibrations, it is characterized in that the said diameter of going up center hole on the anchor slab equals the diameter of said sleeve pipe than large equipment.
3. according to claim 1ly be used to install the adjustable ground foot bolt of vibrations, it is characterized in that the diameter of center hole is greater than the diameter 1~3mm of said screw rod on the said anchor slab down than large equipment.
CN 201120426194 2011-11-01 2011-11-01 Adjustable foundation bolt for mounting equipment with larger vibration Expired - Fee Related CN202302576U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120426194 CN202302576U (en) 2011-11-01 2011-11-01 Adjustable foundation bolt for mounting equipment with larger vibration

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120426194 CN202302576U (en) 2011-11-01 2011-11-01 Adjustable foundation bolt for mounting equipment with larger vibration

Publications (1)

Publication Number Publication Date
CN202302576U true CN202302576U (en) 2012-07-04

Family

ID=46371470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120426194 Expired - Fee Related CN202302576U (en) 2011-11-01 2011-11-01 Adjustable foundation bolt for mounting equipment with larger vibration

Country Status (1)

Country Link
CN (1) CN202302576U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102778249A (en) * 2012-08-14 2012-11-14 中国水电顾问集团中南勘测设计研究院 Piston type lifting general base
CN103953065A (en) * 2014-05-22 2014-07-30 赵东京 Power equipment base fastening device and fixing method
CN108677997A (en) * 2018-05-28 2018-10-19 中石化石油工程技术服务有限公司 The lower margin pre-embedded device of large scale equipment and the lower margin installation method of large scale equipment

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102778249A (en) * 2012-08-14 2012-11-14 中国水电顾问集团中南勘测设计研究院 Piston type lifting general base
CN103953065A (en) * 2014-05-22 2014-07-30 赵东京 Power equipment base fastening device and fixing method
CN103953065B (en) * 2014-05-22 2015-11-18 赵东京 A kind of power-equipment pedestal fastener and fixing means
CN108677997A (en) * 2018-05-28 2018-10-19 中石化石油工程技术服务有限公司 The lower margin pre-embedded device of large scale equipment and the lower margin installation method of large scale equipment

Similar Documents

Publication Publication Date Title
AU2012334092B2 (en) Foundation for a wind turbine
CN105484157B (en) Positioning device and construction method of capping beam of prefabricated bridge
CN203684398U (en) Device for positioning embedded parts in reinforced concrete structure
US20070065234A1 (en) Method for the earthwork of a foundation sunk for a wind energy facility
CN201896365U (en) Installing and fixing device for flat plate pre-embedded piece on surface of concrete
CN105421666B (en) Pre-stressed carbon fiber plate anchor and its construction method
CN202302576U (en) Adjustable foundation bolt for mounting equipment with larger vibration
CN206971769U (en) A kind of rubber support installation positioning special purpose device
CN203270599U (en) Foundation bolt pre-buried die
CN110468727B (en) Temporary prestress tensioning pedestal and lifting point integrated structure of segmental beam and construction method
CN105256894A (en) Construction method for precisely mounting embedded bolt sleeves of seismic isolation and reduction support
CN110656657A (en) Compressor foundation bolt installation method
JP2009121143A (en) Platform forming body and platform setting method
CN106906996A (en) Reusable pre-buried ring
CN204343319U (en) Cableway pipe patten pre-embedded anchoring bolts jig
CN205171381U (en) Prefabricated assembly bridge bent cap positioner
JP5907447B1 (en) Steel column base
CN115807508A (en) Construction method and node for building steel structure column base installation foundation
CN107740497B (en) Construction method for embedding foundation bolts on overflow surface of hydraulic building
CN207092104U (en) A kind of steel-pipe pile attachment structure
CN103132462B (en) Combination tool for controlling down-warping of components and installation and usage method of combination tool
CN202381269U (en) Adjusting device of mounting levelness of basic ring of wind driven generator
CN105155485A (en) Gate pier pre-stressed anchor cable sleeve installation device and construction method thereof
CN211772773U (en) Bridge built-in fitting structure
CN201803057U (en) Foundation bolt for installation of metallurgical equipment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120704