CN202298579U - Gate slot of workshop of hydropower station - Google Patents

Gate slot of workshop of hydropower station Download PDF

Info

Publication number
CN202298579U
CN202298579U CN2011204148809U CN201120414880U CN202298579U CN 202298579 U CN202298579 U CN 202298579U CN 2011204148809 U CN2011204148809 U CN 2011204148809U CN 201120414880 U CN201120414880 U CN 201120414880U CN 202298579 U CN202298579 U CN 202298579U
Authority
CN
China
Prior art keywords
gate slot
gate
telescopic mast
hydropower station
slot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011204148809U
Other languages
Chinese (zh)
Inventor
王凤安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NORTHWEST HYDRO CONSULTING ENGINEERS CHECC
PowerChina Northwest Engineering Corp Ltd
Original Assignee
NORTHWEST HYDRO CONSULTING ENGINEERS CHECC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NORTHWEST HYDRO CONSULTING ENGINEERS CHECC filed Critical NORTHWEST HYDRO CONSULTING ENGINEERS CHECC
Priority to CN2011204148809U priority Critical patent/CN202298579U/en
Application granted granted Critical
Publication of CN202298579U publication Critical patent/CN202298579U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Power-Operated Mechanisms For Wings (AREA)

Abstract

The utility model belongs to the field of designing workshops of hydropower stations, and in particular relates to a gate slot of a workshop of a hydropower station. A gate is arranged on the gate slot. The gate slot is characterized in that telescopic columns are arranged in the gate slot and are arranged at the bottom of the gate slot, the tops of the telescopic columns are fixed at the bottom of the gate; a column library is arranged at the bottom of the gate slot and is used for storing the telescopic columns; the telescopic columns are compressible plastic telescopic columns or rigid structure telescopic columns; and the column library is a concrete pothole or a concrete pothole lined with steel plates. The utility model provides the gate slot of the workshop of the hydropower station, solving a problem that the gate slot can be automatically temporarily blocked when the gate is started (lifted up) in a background technology.

Description

A kind of powerhouse of hydropower station gate slot
Technical field
The utility model belongs to the powerhouse of hydropower station design field, is specifically related to a kind of powerhouse of hydropower station gate slot.
Background technology
China's waterpower resourses (water ability) are very abundant; The first according to the world; Single economic developable total installation of generating capacity (power) just reaches about 4.5 hundred million kilowatts; Exactly because but the abundant reason of waterpower resourses (water can) perhaps, everybody does not note how improving the problem of generating efficiency, especially how improves the problem of generating efficiency through the design of optimizing the power generation construction thing.
Generated output (installed capacity) depends on the product of the discharge of river and effective head, and effective head is the productive head after the head loss of gross head deduction, and head loss mainly is the head loss that occurs in gate slot.Therefore, how can interim automatically shutoff gate slot when (mentioning) at gate opening, be problem just to be solved.
The utility model content
The purpose of the utility model is to provide a kind of powerhouse of hydropower station gate slot, with solve the gate opening described in the background technology can be automatically when (mentioning) problem of shutoff gate slot temporarily.
For reaching above-mentioned purpose, the utility model provides a kind of powerhouse of hydropower station gate slot, and it is provided with gate, it is characterized in that: be provided with telescopic mast in this gate slot, this telescopic mast is positioned at the bottom of this gate slot, and its top is fixed on the bottom of said gate; The bottom of this gate slot is provided with the post storehouse that is used to store this telescopic mast.
Said telescopic mast is compressible plastics telescopic mast or rigidity framework telescopic mast.
Said post storehouse is the coagulation heatable adobe sleeping platform groove after coagulation heatable adobe sleeping platform groove or the steel plate liner.
The utility model has the advantages that: utilize the concrete in mass completion coagulation heatable adobe sleeping platform groove of gate slot bottom or the coagulation heatable adobe sleeping platform groove conduct after the steel plate liner to deposit telescopic mast post storehouse, can save the concrete work amount; Telescopic mast is compressible plastics, rubber telescopic mast or rigidity framework telescopic mast, and manufacture craft is simple, cheap, be easy to apply; The compression of telescopic mast or promote and not need special equipment, power or technology, that leans on gate fully heavyly puts and promotes the purpose that reaches interim shutoff gate slot, simple to operate.The more important thing is the gate slot that provides through the utility model, improved the effective head amount in power station, practiced thrift the energy and cost.
Description of drawings
Below in conjunction with embodiment the utility model is further specified:
Fig. 1 is a Hydroelectric Plant gate slot elevational schematic view;
Fig. 2 is the powerhouse of hydropower station gate slot elevational schematic view that the utility model provides;
Fig. 3 is gate slot that the bottom the is provided with telescopic mast sketch map when closing;
Fig. 4 is gate slot that the bottom the is provided with telescopic mast sketch map when opening;
Fig. 5 is that gate slot that the bottom the is provided with telescopic mast A when closing is to sketch map;
Fig. 6 is that gate slot that the bottom the is provided with telescopic mast A when opening is to sketch map.
Description of reference numerals: 1, trashrack; 2, access door; 3, service gate; 4, the tail water overhauling door; 5,6,7, telescopic mast; 8, gate; 9, the post storehouse.
The specific embodiment
Structure of hydropower station is in order to control flow and head, is provided with the gate of control flow and head, title service gate in the import of generating set; Import at generating set is provided with the gate that overhauls generating set respectively with outlet, claims access door; The head loss that three fan brake gate slotes produce is about 0.4m, accounts for 5/1000 of effective head usually, just reaches about 4.5 hundred million kilowatts of estimations by total installation of generating capacity (power), and about 10,000,000,000 kilowatt hours of electric weight (degree) are sent in then annual loss.
For fear of this loss; Like Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, shown in Figure 6, the utility model provides a kind of powerhouse of hydropower station gate slot, and it is provided with gate 8; Be provided with telescopic mast 5,6,7 in this gate slot; As shown in Figure 2, access door 2, service gate 3 and tail water overhauling door (gate slot) bottom telescopic mast 5,6,7, its top is fixed on the bottom (see figure 3) of gate 8; The bottom of this gate slot is provided with post storehouse 9 (see figure 5)s that are used to store this telescopic mast 5,6,7.
Telescopic mast 5,6,7 is compressible plastics, rubber telescopic mast or rigidity framework telescopic mast, and manufacture craft is simple, cheap, be easy to apply.Said post storehouse 9 is the coagulation heatable adobe sleeping platform grooves after coagulation heatable adobe sleeping platform groove or the steel plate liner.
Utilize the concrete in mass completion coagulation heatable adobe sleeping platform groove of gate slot bottom or the coagulation heatable adobe sleeping platform groove conduct after the steel plate liner to deposit telescopic mast post storehouse, can save the concrete work amount; The compression of telescopic mast 5,6,7 or promote and not need special equipment, power or technology, that leans on gate 8 fully heavyly puts and promotes the purpose that reaches interim shutoff gate slot, simple to operate.
Above gate slot will be reduced the about 0.13m of head loss by the interim shutoff of telescopic mast.Improve the effective head amount in power station, practiced thrift the energy and cost.

Claims (3)

1. powerhouse of hydropower station gate slot, it is provided with gate, it is characterized in that: be provided with telescopic mast in this gate slot, this telescopic mast is positioned at the bottom of this gate slot, and its top is fixed on the bottom of said gate; The bottom of this gate slot is provided with the post storehouse that is used to store this telescopic mast.
2. a kind of powerhouse of hydropower station gate slot as claimed in claim 1 is characterized in that: said telescopic mast is compressible plastics telescopic mast or rigidity framework telescopic mast.
3. a kind of powerhouse of hydropower station gate slot as claimed in claim 1 is characterized in that: said post storehouse is the coagulation heatable adobe sleeping platform groove after coagulation heatable adobe sleeping platform groove or the steel plate liner.
CN2011204148809U 2011-10-27 2011-10-27 Gate slot of workshop of hydropower station Expired - Lifetime CN202298579U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204148809U CN202298579U (en) 2011-10-27 2011-10-27 Gate slot of workshop of hydropower station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204148809U CN202298579U (en) 2011-10-27 2011-10-27 Gate slot of workshop of hydropower station

Publications (1)

Publication Number Publication Date
CN202298579U true CN202298579U (en) 2012-07-04

Family

ID=46367508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204148809U Expired - Lifetime CN202298579U (en) 2011-10-27 2011-10-27 Gate slot of workshop of hydropower station

Country Status (1)

Country Link
CN (1) CN202298579U (en)

Similar Documents

Publication Publication Date Title
CN103034961A (en) Judgment method of power grid power-saving level
CN203939621U (en) The solar energy energy accumulation electricity generator that draws water
CN203603851U (en) Wind-solar hybrid automatic foam discharge device
CN202298579U (en) Gate slot of workshop of hydropower station
CN202194797U (en) Solar photovoltaic water pump
CN204258406U (en) The electric automobile charge-discharge machine of the wide output area of a kind of low-voltage
CN205842824U (en) Coke-oven plant's primary cooler heating water waste heat recovery device
CN202659406U (en) Reflux water pumping hydroelectric generation device
CN202354565U (en) Leisure sunshade
CN201827010U (en) Hydroelectric generation device with cooling tower
CN202973576U (en) Simple solar heat collection device
CN202423514U (en) New energy automobile power battery pack
CN202142552U (en) Solar ground grid counterweight pressing block
CN202361347U (en) Optimized structure of solar photo-thermal power generation energy storage tank and steam generator
CN203553269U (en) Operation gas plug for storage batteries
CN108374745A (en) A kind of supercharging air formula high pressure water energy storing device and method
CN203364505U (en) Precision-casting light-weight solar energy engineering machine
CN202758489U (en) Solar traffic post
CN202401526U (en) Intelligent relay variable frequency water supply device
CN202662618U (en) Novel solar cell
CN203813736U (en) Intelligent switching station with solar energy power supplying
CN203364643U (en) Heat accumulation case with waste heat
CN203066036U (en) Small type reinforced concrete movable dam
CN202333558U (en) Box-type transformer substation with access ladder
CN202579357U (en) Novel staggered water suction device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA ELECTRIC POWER CONSTRUCTION GROUP NORTHWEST

Free format text: FORMER NAME: HYDROCHINA XIBEI ENGINEERING CORPORATION

Owner name: HYDROCHINA XIBEI ENGINEERING CORPORATION

Free format text: FORMER NAME: NORTHWEST HYDROELECTRIC INVESTIGATION + DESIGN INSTITUTE OF CHINA HYDROPOWER ENGINEERING CONSULTING

CP01 Change in the name or title of a patent holder

Address after: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Patentee after: POWERCHINA NORTHWEST ENGINEERING Co.,Ltd.

Address before: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Patentee before: NORTHWEST HYDRO CONSULTING ENGINEERS, CHECC

Address after: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Patentee after: NORTHWEST HYDRO CONSULTING ENGINEERS, CHECC

Address before: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Patentee before: Northwest Hydro Consulting Engineers, CHECC

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120704