CN202273181U - Continuous beam construction protection hanging basket - Google Patents
Continuous beam construction protection hanging basket Download PDFInfo
- Publication number
- CN202273181U CN202273181U CN2011204063834U CN201120406383U CN202273181U CN 202273181 U CN202273181 U CN 202273181U CN 2011204063834 U CN2011204063834 U CN 2011204063834U CN 201120406383 U CN201120406383 U CN 201120406383U CN 202273181 U CN202273181 U CN 202273181U
- Authority
- CN
- China
- Prior art keywords
- hanging basket
- construction
- continuous beam
- operating platform
- storage tank
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The utility model belongs to the technical field of road and bridge buildings, particularly relates to a continuous beam construction protection hanging basket with the effects of insulating, waterproofing and preventing objects from falling, and aims to provide a continuous beam construction protection hanging basket which has the effects of insulating, waterproofing and preventing objects from falling, can greatly improve the construction efficiency of a construction unit, and guarantees the construction safety. The continuous beam construction protection hanging basket adopts the technical scheme that a steel plate with an insulation layer is arranged on the lower surface of a collet of a construction hanging basket and is grounded, a water storage tank is arranged on the first operation platform of the construction hanging basket, a guardrail is arranged at the periphery of the construction hanging basket; and a second water storage tank is arranged on the second operation platform of the construction hanging basket. The continuous beam construction protection hanging basket is mainly used for continuous construction of the road and bridge buildings.
Description
Technical field
The utility model belongs to the road and bridge technical field of buildings, is specifically related to a kind of Construction of continuous beam protection Hanging Basket that has insulation, waterproof, prevents the object effect of falling.
Background technology
When Construction of continuous beam is crossed over high-voltage line; Construction needs the Hanging Basket of full steel structure to support bed die; The high-voltage power line top trends of the times charged again when Hanging Basket must produce induced voltage on Hanging Basket; When Hanging Basket and power line close together, also may cause the air breakdown between Hanging Basket and the power line, form short circuit, cause power failure.The personnel that require in work progress, can not to cause of the security department line short that gets an electric shock owing to the reason of construction, when construction, do not allow simultaneously from the construction Hanging Basket to power line and railway leak, the existence of potential safety hazard such as junk.
The general mode of building frame and suspension insulating slab that adopts of traditional Construction of continuous beam realizes.
The drawback of building frame suspension insulating slab is: construction receives the field condition restriction bigger, when particularly the two-wire intersecting angle is little or Hanging Basket and high-tension electricity linear distance can't set up near the time and build frame; 2, cost is high, sets up that to build frame most of construction costs that insulate high, particularly when large span, low-angle situation, use a large amount of steel work, and need basis of formation; 3, power failure is many, and the operation that when building and remove frame, all need have a power failure has a strong impact on the normal operation of railway, also the on-the-spot construction speed of influence; 4, difficulty is installed, it is difficult to remove.When installing and remove, want basis of formation, make a large amount of steel work, employ a large amount of heavy lifts; 5, potential safety hazard is many, in building and remove the frame process, employs large lifting equipment and on high-voltage line, constructs, and bumps, pounds circuit and damaged line equipment easily, and is wayward; 6, the duration can not ensure, when using the frame construction on the line, owing to need frequent power failure and the normal operation of railway that conflict is arranged, and can only be in the gap construction that has a power failure, the engineering time limits to big.
On Hanging Basket, directly hang the drawback of insulating slab: 1, insulating slab is difficult for forming integral body, forms many gaps, causes gap discharge easily, does not possess water-proof function; 2, insulating slab is fixing difficult, falls down easily, smashes line facility.
Address these problems, also have a kind of method to be: setting has the steel plate of insulating layer on the collet soffit of Hanging Basket, and with steel plate ground connection, on the preceding operating platform of Hanging Basket, aqua storage tank is set.This method can solve basically avoids the induced voltage problem with vertical junk of getting an electric shock, but also has potential safety hazard, as: the virtual voltage on, can not the detecting operation platform, during accident generation induced voltage, operating personnel still might get an electric shock; Two, preceding operating desk and back operating desk are arranged on the Hanging Basket, the seepy question of operating desk before aqua storage tank can only solve.
Summary of the invention
The utility model overcomes the deficiency of prior art, and technical problem to be solved provides a kind ofly to be had insulation, waterproof, prevent that object from falling, and can greatly improve the efficiency of construction of unit in charge of construction, ensures the Construction of continuous beam protection Hanging Basket of construction safety.
For solving the problems of the technologies described above; The technical scheme that the utility model adopted is: a kind of Construction of continuous beam protection Hanging Basket; Comprise construction Hanging Basket, first operating platform, second operating platform, first aqua storage tank, guardrail and second aqua storage tank; The collet soffit of construction Hanging Basket is provided with the steel plate with insulating layer, steel plate ground connection, and first operating platform of construction Hanging Basket is provided with aqua storage tank; Be provided with guardrail around the described construction Hanging Basket, second operating platform of described construction Hanging Basket is provided with second aqua storage tank.
Said first operating platform is provided with security alerting system, and the described security alerting system and first operating platform and second operating platform are through wiring
.
The utility model compared with prior art has following beneficial effect.
1, the utility model is simple in structure, make easy for installation, safe and reliable, but the reduction of erection time reduce to have a power failure.
2, in the utility model Hanging Basket around be provided with guardrail, form an airtight working platform, and two operating platforms all are provided with aqua storage tank, strengthened water-proof function, guarantee staff's personal safety.
3, the utility model steel plate that will have an insulating layer is located on the collet soffit and ground connection, has strengthened insulation effect, and can be used as the receiver of whereabouts article.
4, two operating platforms in the utility model all are connected with security alerting system, have improved constructor's safety factor, guarantee continuous constructor's safety.
Description of drawings
Below in conjunction with accompanying drawing the utility model is described further.
Fig. 1 is the structural representation of the construction Hanging Basket of the utility model.
Fig. 2 is the right view of Fig. 1.
Among the figure: 1 is the construction Hanging Basket, and 2 is first operating platform, and 3 is second operating platform, and 4 is first aqua storage tank, and 5 is guardrail, and 6 is second aqua storage tank.
The specific embodiment
Like Fig. 1, shown in Figure 2; A kind of Construction of continuous beam protection Hanging Basket; Comprise construction Hanging Basket 1, first operating platform 2, second operating platform 3, first aqua storage tank 4, guardrail 5 and second aqua storage tank 6; The collet soffit of construction Hanging Basket 1 is provided with the steel plate with insulating layer, steel plate ground connection, and first operating platform 2 of construction Hanging Basket 1 is provided with aqua storage tank 4; It is characterized in that: be provided with guardrail 5 around the described construction Hanging Basket 1, second operating platform 3 of described construction Hanging Basket 1 is provided with second aqua storage tank 6.
Said first operating platform 2 is provided with security alerting system, and the described security alerting system and first operating platform 2 and second operating platform 3 are through wiring.
Equal and the security alerting system of two operating platforms in the utility model, when construction period produced 30V voltage as if operating platform, security alerting system was just started working, and has improved constructor's safety factor.
The material that the described protective guard of the utility model adopts is the angle steel of ∠ 50mm * 50mm, and guardrail height is 120cm.
Combine accompanying drawing that the embodiment of the utility model has been done detailed description above; But the utility model is not limited to the foregoing description; In the ken that those of ordinary skills possessed, can also under the prerequisite that does not break away from the utility model aim, make various variations.
Claims (2)
1. a Construction of continuous beam is protected Hanging Basket; Comprise construction Hanging Basket (1), first operating platform (2), second operating platform (3), first aqua storage tank (4), guardrail (5) and second aqua storage tank (6); The collet soffit of construction Hanging Basket (1) is provided with the steel plate with insulating layer; Steel plate ground connection; First operating platform (2) of construction Hanging Basket (1) is provided with aqua storage tank (4), it is characterized in that: be provided with guardrail (5) around the described construction Hanging Basket (1), second operating platform (3) of described construction Hanging Basket (1) is provided with second aqua storage tank (6).
2. a kind of Construction of continuous beam protection Hanging Basket according to claim 1; It is characterized in that: said first operating platform (2) is provided with security alerting system, and described security alerting system is connected through wiring with second operating platform (3) with first operating platform (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011204063834U CN202273181U (en) | 2011-10-24 | 2011-10-24 | Continuous beam construction protection hanging basket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011204063834U CN202273181U (en) | 2011-10-24 | 2011-10-24 | Continuous beam construction protection hanging basket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202273181U true CN202273181U (en) | 2012-06-13 |
Family
ID=46193548
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011204063834U Ceased CN202273181U (en) | 2011-10-24 | 2011-10-24 | Continuous beam construction protection hanging basket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202273181U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103147411A (en) * | 2013-03-30 | 2013-06-12 | 师长宏 | Insulation covering hanging groove |
CN107902583A (en) * | 2017-11-09 | 2018-04-13 | 曾小真 | A kind of road and bridge construction instrument fast lifting equipment |
-
2011
- 2011-10-24 CN CN2011204063834U patent/CN202273181U/en not_active Ceased
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103147411A (en) * | 2013-03-30 | 2013-06-12 | 师长宏 | Insulation covering hanging groove |
CN107902583A (en) * | 2017-11-09 | 2018-04-13 | 曾小真 | A kind of road and bridge construction instrument fast lifting equipment |
CN107902583B (en) * | 2017-11-09 | 2019-10-25 | 倡创(上海)咨询管理事务所 | A kind of road and bridge construction tool fast lifting equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206254818U (en) | A kind of charging pile | |
CN202273181U (en) | Continuous beam construction protection hanging basket | |
CN101958519B (en) | Method for transforming tangent tower of double-circuit double-bundle transmission lines by lifting in electrified mode in another place | |
CN201649612U (en) | Insulating hanging basket for continuous beam construction | |
CN206784971U (en) | A kind of job site periphery high voltage wire protector | |
CN201071487Y (en) | Suspension basket safety protection system device in bridge construction | |
CN204754248U (en) | Super high -rise building construction elevator regularization connects material platform | |
CN211898525U (en) | Reusable distribution box foundation for construction site | |
CN203961373U (en) | Switchbox protection canopy | |
CN204826697U (en) | Railway continuous beam construction safety protective guard strides | |
CN204728225U (en) | A kind of rail rail traffic bridge of embracing evacuates inspection platform | |
CN203902541U (en) | Insulation structure for rail transit platform screen door | |
CN106025975A (en) | Anti-snake climbing device for tower or pillar | |
CN207416825U (en) | There is the raft foundation prevented and reduced natural disasters | |
CN204385620U (en) | For the insulation protecting device of overcrossing railway Construction of continuous beam | |
CN203821619U (en) | Fire-proof blocking structure used in interlayer hole of shaft | |
CN204212068U (en) | Cast-in-situ Beam cradle construction safety cradle | |
CN209227400U (en) | A kind of cast-in-place cradle construction safeguard structure of cantilever across existing electrified railway | |
CN205355764U (en) | Lightning arrestor mounting base | |
CN202323775U (en) | Assembly electricity guard plate for rotating body beam construction protection wall | |
CN202323779U (en) | Overline hanging basket | |
CN104876090B (en) | For the safety guard without scaffold construction, circuit and method | |
CN203666413U (en) | Power supply three rail protecting device | |
CN103879411A (en) | Insulating structure used for rail transit shielding barriers and construction method thereof | |
CN107620259A (en) | Construction protection method for bridge under a kind of high-voltage line |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C35 | Partial or whole invalidation of patent or utility model | ||
IW01 | Full invalidation of patent right |
Decision date of declaring invalidation: 20130314 Decision number of declaring invalidation: 20134 Granted publication date: 20120613 |