CN202257232U - Circulating water system for thermal power plant - Google Patents

Circulating water system for thermal power plant Download PDF

Info

Publication number
CN202257232U
CN202257232U CN2011203528459U CN201120352845U CN202257232U CN 202257232 U CN202257232 U CN 202257232U CN 2011203528459 U CN2011203528459 U CN 2011203528459U CN 201120352845 U CN201120352845 U CN 201120352845U CN 202257232 U CN202257232 U CN 202257232U
Authority
CN
China
Prior art keywords
circulating water
water
circulating
controller
power plant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011203528459U
Other languages
Chinese (zh)
Inventor
彭德刚
谭建华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Hot New Energy Technology Co., Ltd.
Original Assignee
CHENGDU STONE NEW ENERGY TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU STONE NEW ENERGY TECHNOLOGY Co Ltd filed Critical CHENGDU STONE NEW ENERGY TECHNOLOGY Co Ltd
Priority to CN2011203528459U priority Critical patent/CN202257232U/en
Application granted granted Critical
Publication of CN202257232U publication Critical patent/CN202257232U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Water Treatment By Electricity Or Magnetism (AREA)

Abstract

The utility model relates to a circulating water system for a thermal power plant, and discloses the circulating water system which aims at avoiding the disadvantages that the circulating water system in the prior art is easy to cause system scaling and water resource waste. The circulating water system for the thermal power plant comprises a circulating water pond, a circulating water pump, a condenser, a cooling tower, a control device, a blowdown valve and a charging pump, wherein the circulating water pond, the circulating water pump, the condenser and the cooling tower are sequentially connected through a pipeline; the control device is connected with the blowdown valve and the charging pump; the control device comprises a DCS (Distributed Control System), a circulating water detecting system, a blowdown valve controller and a charging pump controller; the DCS is connected with the blowdown valve controller and the charging pump controller; and the circulating water detection system comprises a temperature detection device, a total hardness detection device, a total alkalinity detection device, a pH value detection device and an electric conductivity detection device. The circulating water system is mainly used in a circulating water cooling system in the thermal power plant.

Description

The circulating-water in thermal power plant system
Technical field
The utility model relates to the circulating-water in thermal power plant system, and particularly circulating water quality detects control system.
Background technology
Recirculated water is long-term used in generating plant, chemical plant and a lot of heat transmission equipment, and the water yield is huge, and financial cost is high.Recirculated cooling water is because heat radiation evaporation, makes that various mineral matters are constantly concentrated increase with ion concentration in the water, and separates out and be deposited on the heating surface; Make heat interchanger heat conductivility variation; Heat exchange efficiency reduces, and energy consumption increases, and can cause line clogging, discharge to diminish when serious and produces underdeposit corrosion.In the circulating cooling system, heat interchanger and pipeline be mostly by made, and salinity, dissolved oxygen DO etc. contact and can make metal produce galvanic corrosion in metal material and the water.Water saving has become a lot of enterprises of a kind of puzzlement serious problems with the contradiction of fouling of heat exchanger corrosion.
Comprise with recirculated water corrosive attack and the closely-related parameter of fouled condition: saturation index (Is), index of stability (S) and scaling index (PSI).
1, saturation index (Is)
When dissolves carbonate reaches capacity state in water, there is following transient equilibrium relation:
Ca(HCO 3) 2=Ca 2++2HCO 3- (1-1)
HCO 3-=H ++CO 3- (1-2)
CaCO 3=Ca 2++CO 3 2- (1-3)
Bright lattice rel in 1936 has proposed the notion of saturation pH value and saturation index according to above-mentioned equilibrium relation, in water, whether can separate out incrustation scale to judge lime carbonate, and proposes to control separating out of incrustation scale to add the pre-service that acid adds alkali.
Can find out from reaction equation (1-2) with (1-3), add alkali like Xiang Shuizhong, then H +Be neutralized, the pH value of water raises, and reaction equation (1-2) carries out to right-hand, and reaction equation (1-3) carries out to left, and lime carbonate is prone to separate out.If lime carbonate is state of saturation in the water, then reaction equation (1-1), (1-2), (1-3) are in equilibrium state, and calcium bicarbonate does not resolve into lime carbonate, and lime carbonate can not continue dissolving yet.This moment, the pH value of water was called this water saturation pH value, represented with PHs.Bright lattice rel has been derived the formula that calculates PHs, and judges separating out of incrustation scale with the difference of actual pH value and PHs value.This difference is called saturation index (also claiming bright lattice rel index), representes with Is.
When Is>0, calcium carbonate scale can be separated out, and this water belongs to fouling type water;
When Is<0, the calcium carbonate scale layer that then was attached to originally on the heat-transfer area can be dissolved, carbon steel exposed in water corroded, and this water belongs to corrosion type water;
When Is=0, lime carbonate is not promptly separated out, and original calcium carbonate scale layer can be not dissolved yet, and this water belongs to stable type water.
2 index of stability (S)
Nineteen forty-six thunder now Nasdaq index go out, false judgment often appears in saturation index when prediction water quality character.At some in particular cases, though its saturation value be on the occasion of, aqueous corrosion property is very strong.
Thunder is contained on the basis of a large amount of experiments now, has proposed to replace saturation index prediction water quality performance with 2PHs-PH.And be called index of stability to the difference of 2PHS-PH.
3 scaling indexs (PSI)
Pa Kelazi in 1979 thinks corrosion and the fouling tendency that basicity more can reaction cycle water than the practical measurement pH value of water.After a hundreds of circulation had been done to study, he thought that the practical measurement pH value with water in the index of stability changes more practical in production of equilibrated ph value (PHeq) into, and equilibrated ph value and basicity can be calculated by following formula:
PHeq=1.465lg (M basicity)+4.54
The total alkalinity of recirculated water in M basicity-system (in lime carbonate, unit is mg/L)
And propose:
PSI=2PHs-PHeq>6 corrosion
PSI=2PHs-PHeq=6 is stable
PSI=2PHs-PHeq<6 foulings
Above-mentioned three kinds of judge index to fouling corrosion; Though all be the theory that grows up on bright lattice rel basis; They are main with bright lattice rel index, and index of stability and scaling index are auxilliary, but they have a very big weakness; That calculates very numerous and diverse exactly, is unfavorable for the instantaneous control that exercises supervision.
Conventional circulation generally includes water charging system, circulating water pool, water circulating pump, condenser, cooling tower, control device, blowoff valve and charge pump etc.Circulating water pool, water circulating pump, condenser, cooling tower link to each other through pipeline successively, constitute cooling system.Water charging system mainly is the quantity of circulating water according to default, timely replenishment cycles water, the capacity of maintenance circulating water pool.Control device is connected with charge pump with blowoff valve, controls its opening and closing, adds corrosion inhibiting and descaling agent, sewage effluent to circulating water pool.
The prior art circulation is that the determination data with supplementing water carries out approximate treatment; Control with 70%~80% of corrosion inhibiting and descaling agent scale inhibition ability; Most of at home industries in the general tradition comparatively all of circulating water treatment, all adopt blowdown manually or timer blowdown according to each analytical test result at present, daily in service owing to produce to load and change; Same cooling water quality also can change thereupon; The variation of monitoring water quality promptly and accurately will bring fouling or etching problem to system, thereby influence ordinary production if fail in the case.In other words, if discovery variation water quality early, that petty increase analysis frequency that just needs; Adopt the timer blowdown to set according to initial calculated value often; Blowdown is put once setting, generally can not change, and when water quality changes, can not monitor equally.In sum, the low level management of blowdown can cause that circulation blowdown flow rate deficiency causes system's fouling, and the excessive meeting of blowdown causes the increase of waste, manual work and the operating cost of water resource.
The utility model content
The utility model technical matters to be solved is directed against the shortcoming that the prior art circulation causes system's fouling and water resource waste easily exactly, and a kind of circulating-water in thermal power plant system based on computer distributed control system (DCS) is provided.
The utility model solve the technical problem; The technical scheme that adopts is; The circulating-water in thermal power plant system; Comprise circulating water pool, water circulating pump, condenser, cooling tower, control device, blowoff valve and charge pump, said circulating water pool, water circulating pump, condenser, cooling tower link to each other through pipeline successively, and said control device is connected with charge pump with blowoff valve; It is characterized in that; Said control device comprises DCS system, recirculated water detection system, blowoff valve controller and charge pump controller, and said DCS system is connected with the charge pump controller with the blowoff valve controller, and said blowoff valve controller is connected with charge pump with blowoff valve respectively with the charge pump controller; Said recirculated water detection system is made up of temperature-detecting device, total hardness pick-up unit, total alkalinity pick-up unit, pH value pick-up unit and conductivity pick-up unit, and said conductivity pick-up unit is arranged in the circulating water line.
Concrete, said DCS system is made up of computer system.
Concrete, said medicine comprises corrosion inhibiting and descaling agent and/or saline and alkaline spreading agent.
The beneficial effect of the utility model is; Only need to gather less data (being generally 5 groups of data); Just can find the optimization control parameter and the blowdown set point of water quality easily, online conductivity pick-up unit can monitor the variation of water quality automatically, just can change the blowdown set point in time through the DCS system; Change the size (, need not make any setting and change usually) of blowdown flow rate giving under the situation of water quality stabilizing.The utility model can be accomplished the accurate control of recirculated water blowdown, can avoid the fouling corrosion of circulation, can reasonably carry out blowdown control again, practices thrift great amount of water resources.Do several simple conventional analysis chemical examinations (doing 1~2 time in per 12 hours) in service daily needs and follow the tracks of judgement, thereby reduce manually-operated, reduce operating cost, bring distinct economic, really reach the effect of energy-saving and emission-reduction to enterprise as water quality.
Description of drawings
Fig. 1 is the structural representation of the utility model;
Fig. 2 is the control device structural representation.
Embodiment
Below in conjunction with accompanying drawing and embodiment, describe the technical scheme of the utility model in detail.
The circulation of the utility model is through gathering the recirculated water analysis data, and some data need be through manually input, and some data can detect (like TDS) automatically.Control device carries out corresponding calculated according to these data, obtains the recirculated water index of discrimination, comprises saturation index Is, index of stability S, scaling index PSI.And correspondence goes out the best blowdown point (reference electrode conductance parameter is set) of system.The DCS system is sent to charge pump controller and blowoff valve controller with steering order; And the online conductivity of foundation contrasts the determination data of recirculated water and the setting range of blowdown optimum set point; Automatically the start and stop of being controlled the blowdown solenoid valve by controller reach best reasonable blowdown, thereby reach the purpose of water-saving and emission-reducing.
Embodiment
This routine circulating-water in thermal power plant system, as shown in Figure 1, comprise circulating water pool, water circulating pump, condenser, cooling tower, control device, blowoff valve and charge pump.Circulating water pool, water circulating pump, condenser, cooling tower link to each other through pipeline successively, constitute circulating cooling system, and the water charging system among the figure is used for when the water level of circulating water pool is lower than setting value owing to blowdown and evaporation, replenishing.This routine control device is as shown in Figure 2, comprises DCS system, recirculated water detection system, blowoff valve controller and charge pump controller.The recirculated water detection system is made up of temperature-detecting device, total hardness pick-up unit, total alkalinity pick-up unit, pH value pick-up unit and conductivity pick-up unit among the figure, and these pick-up units detect circulating water temperature, total hardness, total alkalinity and pH value parameter in real time.The means of passing through that these supplemental characteristics have input to the DCS system, and what have then can gather automatically, is monitored in real time by the DCS system.Particularly the conductivity pick-up unit is arranged in the circulating water line, gathers the recirculated water conductivity data in real time, and the DCS system sets the blowdown point according to the recirculated water conductivity data, and through blowoff valve controller control sewage discharge.The DCS system is also according to circulating water temperature, total hardness, total alkalinity, conductivity and pH value; Computation cycles water index of discrimination; Comprise saturation index, index of stability, scaling index, and the recirculated water controlled variable of calculated value and setting is compared, in time add corrosion inhibiting and descaling agent and/or saline and alkaline spreading agent through the charge pump controller; Recirculated water saturation index, index of stability, scaling index are controlled at setting range; Can not produce fouling and corrosion, adding medicine and sewage effluent that again can not be too much, thus reach the purpose of water-saving consumption-reduction.This routine DCS system adopts computer system to constitute, and has operation interface intuitively, is convenient to carry out man-machine interaction.
Comparison with the regular circulation water system
Because the change that analysis data of itself and blowdown are provided with a little is untimely, just set the blowdown point at last, owing to carrying out accurately or in time controlling and cause following harm:
Being set to 10 with the blowdown point is example, and blowdown point fluctuates up and down acutely, has been up to 24, and at this moment rate of water make-up has reduced, but the ion in the water increases substantially, and equipment scaling trend increases, and the safe operation of equipment is caused very big harm.During the fluctuation downwards of blowdown point, minimumly reached 3.5, the water ions content is low, and scaling tendency reduces, but blowdown flow rate can significantly increase, and rate of water make-up also can significantly increase, and adds the production cost of large enterprises, causes economic loss.
The circulation of the utility model adopts the DCS system to control in real time, and water quality is fluctuation in a narrow margin around blowdown point 10; Upwards fluctuation is no more than 12; Downward fluctuation can not be lower than 8, in fouling and economical operation, has found optimum, and blowdown is provided with a little and effective control device owing to and analyzing, calculate, changing; Avoided the above-mentioned two kinds of harm in the conventional control better, safety and production and economical operation have had better guarantee.

Claims (2)

1. circulating-water in thermal power plant system; Comprise circulating water pool, water circulating pump, condenser, cooling tower, control device, blowoff valve and charge pump; Said circulating water pool, water circulating pump, condenser, cooling tower link to each other through pipeline successively; Said control device is connected with charge pump with blowoff valve, it is characterized in that, said control device comprises DCS system, recirculated water detection system, blowoff valve controller and charge pump controller; Said DCS system is connected with the charge pump controller with the blowoff valve controller; Said blowoff valve controller is connected with charge pump with blowoff valve respectively with the charge pump controller, and said recirculated water detection system is made up of temperature-detecting device, total hardness pick-up unit, total alkalinity pick-up unit, pH value pick-up unit and conductivity pick-up unit, and said conductivity pick-up unit is arranged in the circulating water line.
2. circulating-water in thermal power plant according to claim 1 system is characterized in that, said DCS system is made up of computer system.
CN2011203528459U 2011-09-20 2011-09-20 Circulating water system for thermal power plant Expired - Fee Related CN202257232U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011203528459U CN202257232U (en) 2011-09-20 2011-09-20 Circulating water system for thermal power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011203528459U CN202257232U (en) 2011-09-20 2011-09-20 Circulating water system for thermal power plant

Publications (1)

Publication Number Publication Date
CN202257232U true CN202257232U (en) 2012-05-30

Family

ID=46118446

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011203528459U Expired - Fee Related CN202257232U (en) 2011-09-20 2011-09-20 Circulating water system for thermal power plant

Country Status (1)

Country Link
CN (1) CN202257232U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103529801A (en) * 2013-10-22 2014-01-22 国家电网公司 Circulating control system recycling urban reclaimed water in circulating cooling water of power plant
CN105954482A (en) * 2016-04-26 2016-09-21 国家电网公司 Method for detecting water quality of external cooling water system of converter station

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103529801A (en) * 2013-10-22 2014-01-22 国家电网公司 Circulating control system recycling urban reclaimed water in circulating cooling water of power plant
CN103529801B (en) * 2013-10-22 2016-02-24 国家电网公司 Municipal middle water is back to the cyclic control system of circulating cooling water of power plant
CN105954482A (en) * 2016-04-26 2016-09-21 国家电网公司 Method for detecting water quality of external cooling water system of converter station

Similar Documents

Publication Publication Date Title
CN102445929B (en) Circulated water system of thermal power plant
CN103058336B (en) Direct-current electrolytic treatment process and equipment for circulating cooling water
CN207473382U (en) A kind of industrial circulating cooling water intelligent operation manages system
CN203159359U (en) An operation device for a circulating cooling water system with a high concentration ratio
CN204298090U (en) Industrial exhaust heat type low temperature multi-effect seawater desalting system
CN104787877B (en) One way of life sewage recycling treatment method and device
CN101943919B (en) Method for controlling concentration multiplying power of circulating cooling water and concentration multiplier
CN202257232U (en) Circulating water system for thermal power plant
CN203768039U (en) Intercooled closed type recirculating cooling water system for calcium carbide furnace
CN106830372A (en) Automatic cleaning-type device for electrochemical water preparation and its operation method
CN201812213U (en) Concentration ratio instrument for circulating cooling water system
CN204440183U (en) A kind of decarburization hard-off water is the recirculated water concentration rate control system of moisturizing
CN112214044B (en) Circulating water automatic control system and method based on total amount control
CN112391654B (en) Electrolytic system capable of stably controlling temperature of conventional electrolyte
CN211393895U (en) Water saving system is controlled to recirculated cooling water intelligence
CN210620240U (en) Improve analytic system of hydrochloric acid of thermal efficiency
CN203656899U (en) Waste heat boiler blowdown heat exchange device
CN209460224U (en) A kind of antisludging agent hardness tolerant fastness to alkali performance measuring and evaluating device
CN206901885U (en) A kind of cooling water circulation utilization apparatus
CN105886679A (en) System and method for producing water vapor by blast furnace slag
TWM603950U (en) Cooling circulating water management equipment based on cooling tower
CN201245452Y (en) Circulation water treatment monitoring apparatus
CN206570102U (en) Automatic cleaning-type device for electrochemical water preparation
CN101973605B (en) Cooling circulating water electrochemistry water quality stabilization treatment system
CN205730842U (en) Waste water sub-prime collection and treatment device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHENGDU HOT NEW ENERGY TECHNOLOGY CO., LTD.

Free format text: FORMER NAME: CHENGDU STONE NEW ENERGY TECHNOLOGY CO., LTD.

CP03 Change of name, title or address

Address after: The people of Wuhou District road Chengdu city Sichuan province 610041 four Branch Road No. 3 National 863 software incubator base in Sichuan on the third floor

Patentee after: Chengdu Hot New Energy Technology Co., Ltd.

Address before: Wuhou District chinatek road Chengdu 610041 Sichuan province No. 3 National 863 software incubator base in Sichuan 3 floor

Patentee before: Chengdu Stone New Energy Technology Co., Ltd.

C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: The people of Wuhou District road Chengdu city Sichuan province 610041 four Branch Road No. 3

Patentee after: Chengdu Hot New Energy Technology Co., Ltd.

Address before: The people of Wuhou District road Chengdu city Sichuan province 610041 four Branch Road No. 3 National 863 software incubator base in Sichuan on the third floor

Patentee before: Chengdu Hot New Energy Technology Co., Ltd.

PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Thermal power plant circulating water system

Effective date of registration: 20140208

Granted publication date: 20120530

Pledgee: The Agricultural Bank of Chengdu branch of Limited by Share Ltd Chinese Sichuan

Pledgor: Chengdu Hot New Energy Technology Co., Ltd.

Registration number: 2014510000003

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120530

Termination date: 20170920

CF01 Termination of patent right due to non-payment of annual fee