CN202245377U - Wellhead ore drawing shuttle groove - Google Patents

Wellhead ore drawing shuttle groove Download PDF

Info

Publication number
CN202245377U
CN202245377U CN2011203581287U CN201120358128U CN202245377U CN 202245377 U CN202245377 U CN 202245377U CN 2011203581287 U CN2011203581287 U CN 2011203581287U CN 201120358128 U CN201120358128 U CN 201120358128U CN 202245377 U CN202245377 U CN 202245377U
Authority
CN
China
Prior art keywords
shuttle groove
groove
ore drawing
shuttle
ore
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011203581287U
Other languages
Chinese (zh)
Inventor
苏顺前
兰文耀
张文明
罗洪春
杨兴跃
冯在华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WENSHAN DOUNAN MANGANESE INDUSTRY Co Ltd YUNNAN
Original Assignee
WENSHAN DOUNAN MANGANESE INDUSTRY Co Ltd YUNNAN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WENSHAN DOUNAN MANGANESE INDUSTRY Co Ltd YUNNAN filed Critical WENSHAN DOUNAN MANGANESE INDUSTRY Co Ltd YUNNAN
Priority to CN2011203581287U priority Critical patent/CN202245377U/en
Application granted granted Critical
Publication of CN202245377U publication Critical patent/CN202245377U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model provides a wellhead ore drawing shuttle groove, which comprises a hopper, a shuttle groove opening formed on the lateral wall of the hopper, the ore drawing shuttle groove connected with the shuttle groove opening, a diverting shuttle groove and a diverting device. The ore drawing shuttle groove comprises a shuttle groove bottom plate and two shuttle groove lateral plates, the diverting shuttle groove is communicated with one lateral side of the ore drawing shuttle groove and comprises a diverting shuttle groove bottom plate and a diverting shuttle groove lateral plate, and the diverting device enables the ore drawing shuttle groove to be connected with the shuttle groove opening during ore drawing and leads the diverting shuttle groove to be connected with the shuttle groove opening during slagging. The wellhead ore drawing shuttle groove can meet the requirements for no influence on the slagging during ore loading of a loader and no influence on the ore drawing during slag loading, can effectively separate ore from slag, increases working time of a winch, and improves ore extraction rate.

Description

Well head ore drawing shuttle groove
Technical field
The utility model relates to machinery manufacturing technology field, particularly a kind of well head ore drawing shuttle groove.
Background technology
Well head ore drawing shuttle groove is a kind of device that is used for ore being carried and introducing in skip bucket or mine car when falling the ore deposit mining site.As shown in Figure 1, be the constructional drawing of well head ore drawing shuttle groove in the prior art.This well head ore drawing shuttle groove comprises compositions such as funnel 1 ', shuttle notch 2 ', shuttle groove side plate 3 ', shuttle trough floor 4 ' and shuttle groove bracing frame.Be the slag field outside the barricade 5, can bits be discharged in the slag field outside the barricade 5 ' during slagging.
There is following technological deficiency in existing well head ore drawing shuttle groove:
1, after ore drawing finishes, if change slagging, then need earlier that the shovel of the ore in the mining site is totally, slagging again need with the shovel of the slag stone in the mining site totally can continue ore drawing again after having put slag.The structure of this well head ore drawing shuttle groove had both consumed the time when carrying out above work, can not effectively separate slag again.
2, the shovel ore deposit before the slagging is that shovel is sordid only according to machinery, therefore also needs manpower that remaining lump ore is carried out mining site.Tiny in addition ore also is difficult to clean out, and so just makes ore sneak in the slag stone.Equally, the shovel slag before the ore drawing will clear mining site with slag stone with the ore of sneaking in the slag stone, simultaneously, also can holiday slag stone in mining site.
The utility model content
The utility model is intended to solve the technical matters that exists in the prior art at least, has proposed a kind of well head ore drawing shuttle groove.
The utility model provides a kind of well head ore drawing shuttle groove, comprising: funnel; Be formed on the shuttle notch on the said hopper side walls; The ore drawing shuttle groove that links to each other with said shuttle notch, wherein, said ore drawing shuttle groove comprises shuttle trough floor and two shuttle groove side plates; With the spreader groove that a side of said ore drawing shuttle groove is connected, said spreader groove comprises spreader trough floor and two spreader groove side plates; And part flow arrangement, said part flow arrangement links to each other said ore drawing shuttle groove when ore drawing with said shuttle notch, and when deslagging, said spreader groove is linked to each other with said shuttle notch.
In an embodiment of the utility model, said part flow arrangement further comprises: the shunting door, and said shunting door is arranged on a side of said ore drawing shuttle groove; Shunting door pivot, said shunting door pivot are arranged on an end of said shunting door, and said shunting door can rotate around said shunting door pivot.
In an embodiment of the utility model, said ore drawing shuttle groove is identical with the width of said spreader groove.
In an embodiment of the utility model, the width of said shunting door equals the width of said ore drawing shuttle groove and said spreader groove.
The well head ore drawing shuttle groove of the utility model does not influence slagging when can satisfy loader dress ore deposit, does not influence ore drawing in the time of the dress slag, and ore deposit, slag can effectively be separated, and increases the winch work-hours, improves the ore removal rate.
Additional aspect of the utility model and advantage part in the following description provide, and part will become obviously from the following description, or recognize through the practice of the utility model.
Description of drawings
Above-mentioned and/or additional aspect of the utility model and advantage obviously with are easily understood becoming the description of embodiment from combining figs, wherein:
Fig. 1 is the constructional drawing of well head ore drawing shuttle groove in the prior art;
Fig. 2 is the constructional drawing of the well head ore drawing shuttle groove of the utility model embodiment.
The specific embodiment
Describe the embodiment of the utility model below in detail, the example of said embodiment is shown in the drawings, and wherein identical from start to finish or similar label is represented identical or similar elements or the element with identical or similar functions.Be exemplary through the embodiment that is described with reference to the drawings below, only be used to explain the utility model, and can not be interpreted as restriction the utility model.
In the description of the utility model; Term " vertically ", " laterally ", " on ", the orientation of indications such as D score, " preceding ", " back ", " left side ", " right side ", " vertically ", " level ", " top ", " end " or position relation be for based on orientation shown in the drawings or position relation; Only be for the ease of describing the utility model rather than requiring the utility model therefore can not be interpreted as restriction with specific azimuth configuration and operation to the utility model.
As shown in Figure 2, be the constructional drawing of the well head ore drawing shuttle groove of the utility model embodiment.This well head ore drawing shuttle groove comprises funnel 1, be formed on the shuttle notch 2 on the sidewall of funnel 1, the ore drawing shuttle groove that links to each other with shuttle notch 2, and the spreader groove that is connected with a side of ore drawing shuttle groove.Wherein, ore drawing shuttle groove comprises shuttle trough floor 4 and two shuttle groove side plates 3, and the spreader groove comprises spreader trough floor 8 and two spreader groove side plates 7.In the embodiment of the utility model, this well head ore drawing shuttle groove also comprises part flow arrangement, and this part flow arrangement links to each other ore drawing shuttle groove when ore drawing with shuttle notch 1, and when deslagging, the spreader groove is linked to each other with shuttle notch 1.
Refer again to Fig. 2, part flow arrangement further comprises shunting door 6 and shunting door pivot 9.Wherein, shunting door 6 is arranged on a side of ore drawing shuttle groove, and shunting door pivot 9 is arranged on an end of shunting door 6, and shunting door 6 can rotate around shunting door pivot 9.In an embodiment of the utility model, shunting door 6 can be steel plate and processes.In an embodiment of the utility model, ore drawing shuttle groove is identical with the width of spreader groove, and the width of shunting door 6 equals the width of ore drawing shuttle groove and spreader groove.Particularly, when the needs slagging, can make shunting door 6 block ore drawing shuttle groove, like this when funnel is poured bits into, bits promptly, can carry out and shovel the ore deposit the 5 outer slag fields from the spreader concentrated flow to barricade simultaneously; When the needs ore drawing, can make shunting door 6 block the spreader groove, ore is promptly gone into mining site from ore drawing shuttle concentrated flow, and the shovel slag can carry out simultaneously.Thereby both are not disturbed mutually, thereby race against time, improve the work efficiency of winch.
The remarkable advantage that improves the new shuttle groove in back is: since the shuttle groove was transformed, every month per day all more than 126 cars, calculates by 7 minutes 1 cars, can transport 8 cars in 1 hour, and promptly winch is average daily after transformation moves more than 1 hour than before transforming more.Work area mine-haul truck per car ore is 5.5 tons, per day many transportation 10 cars, 55 tons of ores of promptly per day many transportations.In sum, the well head ore drawing shuttle groove of the utility model does not influence slagging when can satisfy loader dress ore deposit, does not influence ore drawing in the time of the dress slag, and ore deposit, slag can effectively be separated, and increases the winch work-hours, improves the ore removal rate.
In the description of this specification sheets, the description of reference term " embodiment ", " some embodiment ", " example ", " concrete example " or " some examples " etc. means the concrete characteristic, structure, material or the characteristics that combine this embodiment or example to describe and is contained among at least one embodiment or example of the utility model.In this manual, the schematic statement to above-mentioned term not necessarily refers to identical embodiment or example.And concrete characteristic, structure, material or the characteristics of description can combine with suitable manner in any one or more embodiment or example.
Although illustrated and described the embodiment of the utility model; Those having ordinary skill in the art will appreciate that: under the situation of principle that does not break away from the utility model and aim, can carry out multiple variation, modification, replacement and modification to these embodiment, the scope of the utility model is limited claim and equivalent thereof.

Claims (4)

1. a well head ore drawing shuttle groove is characterized in that, comprising:
Funnel;
Be formed on the shuttle notch on the said hopper side walls;
The ore drawing shuttle groove that links to each other with said shuttle notch, wherein, said ore drawing shuttle groove comprises shuttle trough floor and two shuttle groove side plates;
With the spreader groove that a side of said ore drawing shuttle groove is connected, said spreader groove comprises spreader trough floor and two spreader groove side plates; With
Part flow arrangement, said part flow arrangement link to each other said ore drawing shuttle groove when ore drawing with said shuttle notch, and when deslagging, said spreader groove are linked to each other with said shuttle notch.
2. well head ore drawing shuttle groove as claimed in claim 1 is characterized in that said part flow arrangement further comprises:
The shunting door, said shunting door is arranged on a side of said ore drawing shuttle groove;
Shunting door pivot, said shunting door pivot are arranged on an end of said shunting door, and said shunting door can rotate around said shunting door pivot.
3. well head ore drawing shuttle groove as claimed in claim 2 is characterized in that said ore drawing shuttle groove is identical with the width of said spreader groove.
4. well head ore drawing shuttle groove as claimed in claim 3 is characterized in that, the width of said shunting door equals the width of said ore drawing shuttle groove and said spreader groove.
CN2011203581287U 2011-09-22 2011-09-22 Wellhead ore drawing shuttle groove Expired - Fee Related CN202245377U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011203581287U CN202245377U (en) 2011-09-22 2011-09-22 Wellhead ore drawing shuttle groove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011203581287U CN202245377U (en) 2011-09-22 2011-09-22 Wellhead ore drawing shuttle groove

Publications (1)

Publication Number Publication Date
CN202245377U true CN202245377U (en) 2012-05-30

Family

ID=46106654

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011203581287U Expired - Fee Related CN202245377U (en) 2011-09-22 2011-09-22 Wellhead ore drawing shuttle groove

Country Status (1)

Country Link
CN (1) CN202245377U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104843413A (en) * 2015-03-24 2015-08-19 昆山德友机械设备有限公司 Distributing mechanism for electronic tube sockets

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104843413A (en) * 2015-03-24 2015-08-19 昆山德友机械设备有限公司 Distributing mechanism for electronic tube sockets

Similar Documents

Publication Publication Date Title
CN202156782U (en) Conveying device with combined functions of automatic digging and lifting
CN107520953A (en) A kind of building block brick automatic production line
CN103334755A (en) Slope hoisting and crushing system for deep open-pit mine
CN202245377U (en) Wellhead ore drawing shuttle groove
CN201482547U (en) Movable crushing station
CN104828468B (en) The breakage-proof machine of lump coal height drop
CN209145603U (en) Mining system
CN202765879U (en) Unloading system for dump truck with indicating device
CN201932163U (en) Mining car for preventing materials from being deposited and adhered at bottom
CN206796209U (en) A kind of environment-friendly type concrete mixing plant
CN202001820U (en) Wear-resisting lining plate
CN207290465U (en) A kind of building block brick automatic production line
CN206765094U (en) A kind of heavy duty detergent concrete mixing plant
CN206156114U (en) A novel discharge hopper for car is unloaded
CN201506602U (en) Wear-resistant device of blocky ore transportation process hopper
CN206126036U (en) Prevent blocking up, stand wear and tear feeder hopper
CN201077633Y (en) Suspended type receiving hopper backing block
CN202642738U (en) Reclaimer with self-releasing buffer bed
CN204110674U (en) A kind of lower ore deposit funnel
CN203383821U (en) Slope lifting and crushing system for deep open pit
CN211366114U (en) Ore blocking device for ore pass vibration ore drawing machine of mine stope
CN206767168U (en) Coal automotive unloading system
CN207973247U (en) A kind of buildup buffering, the conveying device of skip bucket ore storage bin feed inlet
CN201763387U (en) Electric finger gate
CN103241481A (en) Arch-breaking and blockage-cleaning ore bin

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120530

Termination date: 20160922

CF01 Termination of patent right due to non-payment of annual fee