CN202188941U - Pressure automatic alarm system in vacuum combined pre-loading seal membrane - Google Patents

Pressure automatic alarm system in vacuum combined pre-loading seal membrane Download PDF

Info

Publication number
CN202188941U
CN202188941U CN2011202935138U CN201120293513U CN202188941U CN 202188941 U CN202188941 U CN 202188941U CN 2011202935138 U CN2011202935138 U CN 2011202935138U CN 201120293513 U CN201120293513 U CN 201120293513U CN 202188941 U CN202188941 U CN 202188941U
Authority
CN
China
Prior art keywords
vacuum
alarm system
pressure
automatic alarm
seal membrane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011202935138U
Other languages
Chinese (zh)
Inventor
肖策
宋增力
褚丝绪
张永杰
纪建成
高有为
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin MCC20 Construction Co Ltd
Original Assignee
Tianjin MCC20 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin MCC20 Construction Co Ltd filed Critical Tianjin MCC20 Construction Co Ltd
Priority to CN2011202935138U priority Critical patent/CN202188941U/en
Application granted granted Critical
Publication of CN202188941U publication Critical patent/CN202188941U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Measuring Fluid Pressure (AREA)

Abstract

The utility model discloses a pressure automatic alarm system in a vacuum combined pre-loading seal membrane, characterized in that a pressure gage in a vacuum preloading device is an electric contact pressure gage, a normally open contact of the electric contact pressure gage is in parallel connection with an auxiliary normally open contact of an intermediate relay and then is in series connection together with a normally closed contact of a reset button in a coil power supply loop of the intermediate relay, and another one auxiliary normally open contact of the intermediate relay is in series connection in a power supply loop of a combined aural and visual alarm.. The pressure automatic alarm system in the vacuum combined pre-loading seal membrane of the utility model employs the cooperation work structure of the electric contact pressure gage and the combined aural and visual alarm, when a vacuum pressure reduces to a set value, the combined aural and visual alarm is started, and operators on duty start investigating the leakage point at the first time, thereby being beneficial to the engineering quality, at the same time, reducing the needed time, mechanical cost and electricity cost of reaching a design pressure again, and reducing the construction cost. The pressure automatic alarm system in the vacuum combined pre-loading seal membrane is simple in structure, convenient in installation, low in labor cost and cost, and by using the pressure automatic alarm system in the vacuum combined pre-loading seal membrane, the labor intensity is reduced to a great degree, the working efficiency is improved, and the manpower, material resources and financial resources are saved.

Description

Combined vacuum and surcharge preloading diaphragm seal internal pressure automatic alarm system
Technical field
The utility model relates to a kind of automatic alarm system, particularly relates to a kind of combined vacuum and surcharge preloading diaphragm seal internal pressure automatic alarm system.
Background technology
South China coastland major part is a silt coast, and mostly soil layer is mud, silt clay, mud matter mild clay and mud mulling layer, belongs to saturated normal consolidation soft clay.This type soil has that water cut height, compressibility are big, poor permeability, highly sensitive, intensity is low and characteristics such as uneven thickness.Vacuum preloading joint preloading method is the development in recent years reinforced soft soil ground new technology of getting up just, and combined vacuum and surcharge preloading is safe and reliable, and treatment effect is good, and at present, this method is widely used in fields such as traffic, harbour, water conservancies.
The vacuum tightness that can reach in the effect of vacuum preloading and the diaphragm seal has great relation, and the difference of air pressure and external atmosphere pressure remains under the condition of 80~90KPa under film, and vacuum preloading can reach effect preferably.Vacuumize under the normal situation at vacuum pump, the CCP during construction is guaranteed to seal intact exactly.Though geotextile and medium coarse sand are all arranged as protection up and down at diaphragm seal; But in the process of preloading medium coarse sand and soil; Because starting material and construction machinery still the phenomenon that diaphragm seal is staved can take place, often be just to be found after several hours by the patrolman; At this moment the scope of seeking leak source has increased, and difficulty has strengthened.If the very first time at rupture of membranes found by the operator on duty, to searching leak source, and repair at once, reduce the decline that vacuumizes regional film downforce, it is fixed to accelerate soft soil foundation, highly beneficial to construction quality.
At present; Conventional way is to watch tensimeter numerical value to judge whether diaphragm seal problem takes place, and it is long that pressure reduces the time by the patrolman, and the reason of producing for the analysis and judgement problem is brought bigger difficulty; Need to increase labour's cooperation and search the gas leakage point; Labour intensity is big, and the labour cost expenditure is many, and construction quality is difficult to guarantee.
The utility model content
The utility model provides a kind of combined vacuum and surcharge preloading diaphragm seal internal pressure automatic alarm system for solving the technical matters that exists in the known technology.
The technical scheme that the utility model is taked for the technical matters that exists in the solution known technology is: a kind of combined vacuum and surcharge preloading diaphragm seal internal pressure automatic alarm system; The tensimeter of vacuum prepressing device is an electro connecting pressure gauge, and the normal opened contact of said electro connecting pressure gauge is serially connected with in the coil power supply loop of auxiliary reclay with the normally closed contact of SR after an auxiliary normal opened contact parallel connection of auxiliary reclay; The auxiliary normal opened contact of another of auxiliary reclay is serially connected with in the current supply circuit of audible-visual annunciator.
Advantage and the good effect that the utlity model has are: the structure that adopts electro connecting pressure gauge and audible-visual annunciator collaborative work; When vacuum pressure power was reduced to setting value, audible-visual annunciator started at once, and the operator on duty begins investigation gas leakage point in the very first time; Favourable to construction quality; Simultaneously, reduce the needed time of design pressure that reaches again, machinery expense and the electricity charge, reduced construction cost.And the utility model is simple in structure, and is easy for installation, reduced labour intensity to a great extent, improved work efficiency, artificial less investment, and cost is low, has saved human and material resources and financial resources.
Description of drawings
Fig. 1 is the structural representation of the utility model.
Embodiment
For further understanding summary of the invention, characteristics and the effect of the utility model, the following examples of giving an example now, and conjunction with figs. specifies as follows:
See also Fig. 1; A kind of combined vacuum and surcharge preloading diaphragm seal internal pressure automatic alarm system; The tensimeter SP of vacuum prepressing device is an electro connecting pressure gauge, and the normal opened contact of electro connecting pressure gauge SP is serially connected with in the coil power supply loop of auxiliary reclay KA with the normally closed contact of SR SB after the auxiliary normal opened contact parallel connection of auxiliary reclay KA; The auxiliary normal opened contact of another of auxiliary reclay KA is serially connected with in the current supply circuit of audible-visual annunciator BL.
In the present embodiment, the model of electro connecting pressure gauge SP is HQ-Y-100; The model of auxiliary reclay KA is JZJ-14; The model of audible-visual annunciator is SG-103, and the shared 24V power module of the current supply circuit of the coil of auxiliary reclay KA and audible-visual annunciator BL is supplied power, and the model of above-mentioned 24V power module is YKC-J111.
The principle of work of the utility model:
Carry out in the whole process of aqueous vapor separation in vacuum prepressing device, the variation through electro connecting pressure gauge monitoring diaphragm seal internal pressure utilizes it to open and close, and reaches the purpose of timely warning.The concrete course of work is:
1) when the difference of air pressure under the film and external atmosphere pressure is higher than 80KPa, the normal opened contact of electro connecting pressure gauge stays open state, and auxiliary reclay does not receive; Auxiliary contact is not closed, and to making alarm circuit not closed, audible-visual annunciator does not receive; Do not send chimes of doom, pilot lamp dodges and does not work simultaneously.Vacuum preloading is in normal operating conditions.
2) when the difference of air pressure under the film and external atmosphere pressure is lower than 80KPa, the normal opened contact of electro connecting pressure gauge is closed, and auxiliary reclay receives electricity, and auxiliary contact is closed, and to making alarm circuit closed, audible-visual annunciator gets electric, sends chimes of doom, and pilot lamp is glittering simultaneously.After the staff sees warning, make audible-visual annunciator stop to report to the police, and check the not enough reason of on-the-spot vacuum pressure through SR.
Although combine accompanying drawing that the preferred embodiment of the utility model is described above; But the utility model is not limited to above-mentioned embodiment, and above-mentioned embodiment only is schematically, is not restrictive; Those of ordinary skill in the art is under the enlightenment of the utility model; Not breaking away under the scope situation that the utility model aim and claim protect, can also make a lot of forms, these all belong within the protection domain of the utility model.

Claims (1)

1. combined vacuum and surcharge preloading diaphragm seal internal pressure automatic alarm system; It is characterized in that; The tensimeter of vacuum prepressing device is an electro connecting pressure gauge, and the normal opened contact of said electro connecting pressure gauge is serially connected with in the coil power supply loop of auxiliary reclay with the normally closed contact of SR after an auxiliary normal opened contact parallel connection of auxiliary reclay; The auxiliary normal opened contact of another of auxiliary reclay is serially connected with in the current supply circuit of audible-visual annunciator.
CN2011202935138U 2011-08-12 2011-08-12 Pressure automatic alarm system in vacuum combined pre-loading seal membrane Expired - Fee Related CN202188941U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202935138U CN202188941U (en) 2011-08-12 2011-08-12 Pressure automatic alarm system in vacuum combined pre-loading seal membrane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202935138U CN202188941U (en) 2011-08-12 2011-08-12 Pressure automatic alarm system in vacuum combined pre-loading seal membrane

Publications (1)

Publication Number Publication Date
CN202188941U true CN202188941U (en) 2012-04-11

Family

ID=45920383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202935138U Expired - Fee Related CN202188941U (en) 2011-08-12 2011-08-12 Pressure automatic alarm system in vacuum combined pre-loading seal membrane

Country Status (1)

Country Link
CN (1) CN202188941U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102323002A (en) * 2011-08-12 2012-01-18 天津二十冶建设有限公司 Combined vacuum and surcharge preloading diaphragm seal internal pressure automatic alarm system
CN117387870A (en) * 2023-12-12 2024-01-12 华土木(厦门)科技有限公司 Vacuum preloading underwater sealing film damage visualization accurate positioning method and system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102323002A (en) * 2011-08-12 2012-01-18 天津二十冶建设有限公司 Combined vacuum and surcharge preloading diaphragm seal internal pressure automatic alarm system
CN117387870A (en) * 2023-12-12 2024-01-12 华土木(厦门)科技有限公司 Vacuum preloading underwater sealing film damage visualization accurate positioning method and system
CN117387870B (en) * 2023-12-12 2024-03-26 华土木(厦门)科技有限公司 Vacuum preloading underwater sealing film damage visualization accurate positioning method and system

Similar Documents

Publication Publication Date Title
CN102323002A (en) Combined vacuum and surcharge preloading diaphragm seal internal pressure automatic alarm system
CN106128035A (en) The geological disaster forecasting method merged based on neutral net and multi-parameter information
CN103335876A (en) Remoulding soft clay sample preparation device and method based on vacuum combined electron-osmosis effect
CN202188941U (en) Pressure automatic alarm system in vacuum combined pre-loading seal membrane
CN213363961U (en) Deep basal pit precipitation inspection well alarm device
CN205785327U (en) Urban Underground pipe gallery dynamic monitoring based on Internet of Things and early warning system
CN103185201B (en) Oil and gas pipes manual valve chamber integration leakage monitoring terminal
CN103835360B (en) Automatic drainage system of box culvert road
CN103866756B (en) Oversized-area efficient energy-saving vacuumizing soft foundation treatment system and construction method
CN113882322B (en) Intelligent water stopping method for repairing underwater concrete damaged dry chamber
CN207934010U (en) Anti-erosion water and soil separator
Liu et al. Design and implementation of monitoring and early warning system for urban roads waterlogging
CN215977119U (en) Damaged dry chamber cabin of concrete under water restores intelligent stagnant water and equips
CN201176596Y (en) Pipe well simultaneous for draining and pressure-reduction dewatering
CN202830960U (en) Intelligent intermittent bailing type pumping unit steel structure foundations
CN202532191U (en) Oil-gas pipeline and manual valve chamber integrated leakage monitoring terminal
CN105178284B (en) A kind of pulse vacuum prepressing water discharge device and method of the soft base of muck soil
CN111096181B (en) Monitoring feedback type greening method and system for ecological restoration
CN109115972A (en) A kind of one-dimensional rock pillar simulated water pressure of acquisition groundwater parameter is from numeration factually experiment device
CN205857255U (en) A kind of automatic vacuum prepressing water discharge consolidation model pilot system
CN209620222U (en) Cut-off equipment and shunting well with outer expansion sleeve
CN211200411U (en) Side slope protection pile and side slope monitoring and protection system thereof
CN202930909U (en) Waterlogging supervising device in enclosed bus
CN214277562U (en) Buried undisturbed underground water monitoring device
CN201574781U (en) Water level alarm apparatus of water sump of deep well of underground mine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120411