CN202147976U - Culvert wall template skidding track - Google Patents

Culvert wall template skidding track Download PDF

Info

Publication number
CN202147976U
CN202147976U CN 201120217692 CN201120217692U CN202147976U CN 202147976 U CN202147976 U CN 202147976U CN 201120217692 CN201120217692 CN 201120217692 CN 201120217692 U CN201120217692 U CN 201120217692U CN 202147976 U CN202147976 U CN 202147976U
Authority
CN
China
Prior art keywords
culvert
support rods
lateral strut
culvert wall
sliding rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201120217692
Other languages
Chinese (zh)
Inventor
刘志辉
刘正渲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSCEC Strait Construction and Development Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical Third Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority to CN 201120217692 priority Critical patent/CN202147976U/en
Application granted granted Critical
Publication of CN202147976U publication Critical patent/CN202147976U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Sewage (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to a culvert wall template skidding track which is characterized by comprising a plurality of cross support rods, rolling pieces and a plurality of vertical support rod, wherein the plurality of cross support rods are fixedly arranged on a wall foundation, the rolling pieces are movably sheathed outside the cross support rods, and the plurality of vertical support rods are fixedly arranged on the ground and fixedly connected with the outer end parts of the cross support rods, and the plurality of cross support rods are all positioned on the same horizontal height. The culvert wall template skidding track not only is convenient in constructing and manufacturing, but also can realize the movement of the template without the engineering machine, and the construction efficiency of the culvert can be improved.

Description

Culvert wall form sliding rail
Technical field
The utility model relates to a kind of culvert wall form sliding rail.
Background technology
Build in the construction at the culvert wall form,, and caused the phenomenon of delaying work, make job schedule receive very big restriction often because factors such as crane deficiency are restricted shifting formwork.
Summary of the invention
The purpose of the utility model is to provide a kind of culvert wall form sliding rail, and it not only constructs easy to make, and can use construction machinery and equipment can realize moving of template, improves the operating efficiency of culvert.
The purpose of the utility model realizes through following technical scheme: a kind of culvert wall form sliding rail is characterized in that: it comprises many lateral strut being fixedly arranged at interval on the body of wall basis, is movably set in outer rolling member of each root lateral strut and many vertical poles that are fixedly arranged on the ground and captive joint with the outer end of each root lateral strut respectively; Each root lateral strut all is positioned on the same level height.
The method of application of the utility model is following: on rolling member, the resistance when utilizing the relative lateral strut of rolling member to rotate to reduce the relative rolling member slippage of template makes template under people's force urges, to move with template erection.
Compared to prior art, the advantage of the utility model is: it not only constructs easy to make, and can use construction machinery and equipment can realize moving of template, avoids incuring loss through delay the duration because of construction machinery and equipment is not enough, improves the operating efficiency of culvert.
Description of drawings
Fig. 1 is the structural representation of a kind of culvert wall form of the utility model sliding rail embodiment.
Fig. 2 is the A-A cutaway view of Fig. 1.
Label declaration: 1, body of wall basis, 2, lateral strut, 3, rolling member, 4, ground, 5, vertical pole, 6, vertical stock, 7, template.
The specific embodiment
Below in conjunction with Figure of description and embodiment the utility model content is elaborated:
The embodiment scheme drawing of a kind of culvert wall form sliding rail that provides for the utility model as depicted in figs. 1 and 2 is characterized in that: it comprises the many lateral strut 2 that are fixedly arranged at interval on the body of wall basis 1, be movably set in outer rolling member 3 of each root lateral strut 2 and many vertical poles 5 that are fixedly arranged on the ground 4 and captive joint with the outer end of each root lateral strut 2 respectively; Each root lateral strut 2 all is positioned on the same level height.
Said rolling member 3 is a steel pipe.
Many vertical poles 5 link together through vertical stock 6.
Said vertical stock 6 is a reinforcing bar.
Said lateral strut 2 and vertical pole 5 are processed by screw-thread steel.

Claims (4)

1. culvert wall form sliding rail is characterized in that: it comprises the many lateral strut (2) that are fixedly arranged at interval on the body of wall basis (1), is movably set in the outer rolling member (3) of each root lateral strut (2) and is fixedly arranged on the many vertical poles (5) that ground (4) is gone up and captiveed joint with the outer end of each root lateral strut (2) respectively; Each root lateral strut (2) all is positioned on the same level height.
2. culvert wall form sliding rail according to claim 1 is characterized in that: said rolling member (3) is a steel pipe.
3. culvert wall form sliding rail according to claim 2 is characterized in that: many vertical poles (5) link together through vertical stock (6).
4. culvert wall form sliding rail according to claim 3 is characterized in that: said vertical stock (6) is a reinforcing bar.
CN 201120217692 2011-06-24 2011-06-24 Culvert wall template skidding track Expired - Lifetime CN202147976U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120217692 CN202147976U (en) 2011-06-24 2011-06-24 Culvert wall template skidding track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120217692 CN202147976U (en) 2011-06-24 2011-06-24 Culvert wall template skidding track

Publications (1)

Publication Number Publication Date
CN202147976U true CN202147976U (en) 2012-02-22

Family

ID=45589044

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120217692 Expired - Lifetime CN202147976U (en) 2011-06-24 2011-06-24 Culvert wall template skidding track

Country Status (1)

Country Link
CN (1) CN202147976U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107254887A (en) * 2017-07-31 2017-10-17 中国十九冶集团有限公司 City integrated piping lane, which is poured, uses outer side mold guider
CN108330852A (en) * 2018-04-16 2018-07-27 长沙理工大学 A kind of device and method suitable for the construction of slab culvert wall body shifting formwork

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107254887A (en) * 2017-07-31 2017-10-17 中国十九冶集团有限公司 City integrated piping lane, which is poured, uses outer side mold guider
CN108330852A (en) * 2018-04-16 2018-07-27 长沙理工大学 A kind of device and method suitable for the construction of slab culvert wall body shifting formwork

Similar Documents

Publication Publication Date Title
CN203213623U (en) Slide guiding and rectifying device
CN204728707U (en) A kind of sliding beam pull bar of length adjustable
CN202147976U (en) Culvert wall template skidding track
CN206034479U (en) Tower crane relay handling supporter device
CN202324567U (en) Moving type large-scale operation platform
CN202467155U (en) Retractable scaffold pedal
CN204022083U (en) A kind of hydraulic pressure wire-unfolding rack
CN202542697U (en) Truss type flexible leg of portal crane
CN206052562U (en) Thin-walled hollow pier capping beam profile steel bracket
CN201873949U (en) Bride prestress stretch-draw trolley
CN205276698U (en) Angle steel in system hole in concrete
CN204139577U (en) Embedment means formula wall-connecting piece after a kind of
CN203022366U (en) Temporary supporting latticed column for grid frame
CN202031380U (en) Fence joint
CN203553621U (en) Power transformation framework lattice beam sliding support
CN201665870U (en) Soil cement multi-way anchor pile of a deep foundation pit support
CN201605864U (en) Narrow base tower for power transmission line
CN206309111U (en) A kind of line bar location and installation component
CN204899034U (en) Prefabricated wall post
CN202575754U (en) Space pipe truss structure secondary truss high altitude lifting moving hanging rack
CN202400545U (en) Quick conveying device for installation of large-scale pipeline on pipe gallery
CN203855330U (en) Combined tower crane wall-attaching device in special-shaped structure
CN202990384U (en) Assembly platform capable being combined freely
CN203271122U (en) Attached template lifting frame
CN206052971U (en) A kind of steel column anchor head

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CSCEC STRAIT CONSTRUCTION AND DEVELOPMENT CO., LTD

Free format text: FORMER NAME: THE THIRD COMPANY OF CHINA SEVENTH ENGINEERING BUREAU CO., LTD.

CP03 Change of name, title or address

Address after: 98-1 No. 350003 Fujian province Fuzhou Mawei District Jiangbin East Avenue

Patentee after: CSCEC Strait Construction and Development Co., Ltd.

Address before: North Road, Gulou District of Fuzhou city of Fujian Province, No. 148 350000

Patentee before: The Third Company of China Seventh Engineering Bureau Co., Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120222