CN202137169U - High-efficiency dust collection device for crushing as-fired coal of coking plant - Google Patents

High-efficiency dust collection device for crushing as-fired coal of coking plant Download PDF

Info

Publication number
CN202137169U
CN202137169U CN201120098014U CN201120098014U CN202137169U CN 202137169 U CN202137169 U CN 202137169U CN 201120098014 U CN201120098014 U CN 201120098014U CN 201120098014 U CN201120098014 U CN 201120098014U CN 202137169 U CN202137169 U CN 202137169U
Authority
CN
China
Prior art keywords
dust
belt conveying
pipe
conveying room
dust shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201120098014U
Other languages
Chinese (zh)
Inventor
王玖文
任加新
潘清霞
焦玉雪
毕经生
刘剑
耿俊峰
杨逢庭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LAIWU TAISHAN COKING CO Ltd
Original Assignee
LAIWU TAISHAN COKING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LAIWU TAISHAN COKING CO Ltd filed Critical LAIWU TAISHAN COKING CO Ltd
Priority to CN201120098014U priority Critical patent/CN202137169U/en
Application granted granted Critical
Publication of CN202137169U publication Critical patent/CN202137169U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Coke Industry (AREA)

Abstract

The utility model discloses a high-efficiency dust collection device for crushing as-fired coal of a coking plant, which comprises two crushers (1), two feeding pipes (2), a main dust sucking pipe (3), a belt conveying chamber (4) and a suction hood (5). The high-efficiency dust collection device is characterized in that two ends of a circulating air channel (8) are respectively connected with the two feeding pipes (2), a dust sucking branch pipe (6) is arranged on the main dust sucking pipe (3) and connected with an auxiliary suction hood (7), and the auxiliary suction hood (7) is disposed on the belt conveying chamber (4). By the aid of the high-efficiency dust collection device, the pressure of an integral system is reduced, dust blockage in the dust sucking pipe is greatly reduced, dust escape is also remarkably decreased, accordingly, an operating environment of a belt corridor is purified, and pollution to surrounding environments is reduced.

Description

Go into the fragmentation of stove coal and use the high-effective dust-removing device coke-oven plant
Technical field
The utility model relates to the improvement of a kind of coke-oven plant with dust arrester, and specifically go into the fragmentation of stove coal and uses the high-effective dust-removing device a kind of coke-oven plant.
Background technology
The coke-oven plant is a coal chemical industry enterprises, carries out in the broken transportation using dust arrester to carry out dedusting, the prior dedusting device going into the stove coal; As shown in Figure 1, comprise that two disintegrating machines 1, feed pipe 2, main sweep-up pipe 3, belt conveying room 4 and 5, two disintegrating machines 1 of dust shield are connected with corresponding feed pipe 2 respectively; Its discharge nozzle is connected with belt conveying room 4 respectively, and belt conveying room 4 is provided with belt housing, leaks to prevent dust; End at belt conveying room 4 is provided with dust shield 5, and dust shield 5 is connected with main sweep-up pipe 3, goes into the stove coal when carrying out fragmentation 1 pair of disintegrating machine like this; The dust and the coal dust material that produce together get into belt conveying room 4, transfer out through belt, and the dust in belt conveying room 4 is discharged through dust shield 5, main sweep-up pipe 3; Its weak point is: in running, two disintegrating machines 1 are that one of a job is subsequent use, and disintegrating machine 1 tup of rotation can produce very big air-flow at a high speed; A large amount of dust are floating in air, and most of dust can get into sack cleaner through the main sweep-up pipe 3 of dedusting fan, in this process; Wherein a part of dust deposits in main sweep-up pipe 3, and easy blocking master's sweep-up pipe 3 influences dust removing effects; And another part dust can be gone out belt housing, and dust escapes the operating environment that has both worsened belt porch, and also the atmosphere to periphery pollutes.
Summary of the invention
The purpose of the utility model be to provide a kind of simple in structure, need not to clear up dust sucting pipeline, go into the fragmentation of stove coal and use the high-effective dust-removing device and reach the good coke-oven plant of dust removing effects.
In order to reach above purpose, the technical scheme that the utility model adopted is: go into the fragmentation of stove coal and use the high-effective dust-removing device this coke-oven plant, comprises two disintegrating machines, feed pipe, main sweep-up pipe, belt conveying room and dust shield; Two disintegrating machines are connected with corresponding feed pipe respectively, and its discharge nozzle is connected with the belt conveying room respectively, and the belt conveying room is provided with belt housing; Dust shield is connected with main sweep-up pipe; On the belt conveying room, be provided with dust shield, it is characterized in that: the two ends of circulation air path are connected with two feed pipes respectively, on main sweep-up pipe, are provided with dust suction and are in charge of; Dust suction is in charge of with secondary dust shield and is connected, and secondary dust shield is located on the belt conveying room.
The utility model is also implemented through following measure: described dust shield is located at the middle part of belt conveying room, and described secondary dust shield is provided with two, and symmetry is located at the both sides of dust shield respectively.
The beneficial effect of the utility model is: compare with present dust arrester; Formed balanced pressure in the whole broken dust pelletizing system; Thereby reduced the pressure of whole system, so the dust stopping state in the sweep-up pipe has significantly reduced, dust escapes also and has obviously reduced; Thereby purified the operating environment of belt porch, reduced pollution surrounding environment.
Description of drawings
Fig. 1 is the structural representation of the dust arrester of prior art;
Fig. 2 is the structural representation of the utility model;
Among the figure: 1, disintegrating machine; 2, feed pipe; 3, main sweep-up pipe; 4, belt conveying room; 5, dust shield; 6, dust suction is in charge of; 7, secondary dust shield; 8, circulation air path.
The specific embodiment
Make the utility model with reference to accompanying drawing 2.Go into the fragmentation of stove coal and use the high-effective dust-removing device this coke-oven plant, comprises that two disintegrating machines 1, feed pipe 2, main sweep-up pipe 3, belt conveying room 4 and 5, two disintegrating machines 1 of dust shield are connected with corresponding feed pipe 2 respectively; Its discharge nozzle is connected with belt conveying room 4 respectively, and belt conveying room 4 is provided with belt housing, leaks to prevent dust; Dust shield 5 is connected with main sweep-up pipe 3; On belt conveying room 4, be provided with dust shield 5, it is characterized in that: the two ends of circulation air path 8 are connected with two feed pipes 2 respectively, on main sweep-up pipe 3, are provided with dust suction and are in charge of 6; Dust suction is in charge of 6 and is connected with secondary dust shield 7; Secondary dust shield 7 is located on the belt conveying room 4, absorbs the dust of belt conveying room 4 simultaneously through dust shield 5 and secondary dust shield 7, and dedusting is not more thoroughly totally like this.
Described dust shield 5 is located at the middle part of belt conveying room 4, and described secondary dust shield 7 is provided with two, and symmetry is located at the both sides of dust shield 5 respectively.
The utility model is to be provided with circulation air path 8 through the middle part at the feed pipe 2 of two disintegrating machines 1, and air-flow formation circulated air in two disintegrating machines (opens is equipped with) that the tup of rotation is at a high speed produced makes disintegrating machine 1 dedusting fan housing internal pressure relative equilibrium; Disintegrating machine 1 tup of running produces powerful air-flow simultaneously, and air-flow is from disintegrating machine 1 most of belt conveying room 4 that gets into, and a part gets into circulation air path 8; Get into another disintegrating machine 1, get into belt conveying room 4 at last, form circulated air; And two secondary dust shields 7 setting up; With dust shield 5 balanced pressure in the belt conveying room 4, cause that outside pressure also reduces thereupon in the belt conveying room 4, stopped dust and escaped.

Claims (2)

1. go into the fragmentation of stove coal and use the high-effective dust-removing device coke-oven plant; Comprise two disintegrating machines (1), feed pipe (2), main sweep-up pipe (3), belt conveying room (4) and dust shield (5); Two disintegrating machines (1) are connected with corresponding feed pipe (2) respectively, and its discharge nozzle is connected with belt conveying room (4) respectively, and belt conveying room (4) is provided with belt housing; Dust shield (5) is connected with main sweep-up pipe (3); On belt conveying room (4), be provided with dust shield (5), it is characterized in that: the two ends of circulation air path (8) are connected with two feed pipes (2) respectively, on main sweep-up pipe (3), are provided with dust suction and are in charge of (6); Dust suction is in charge of (6) and is connected with secondary dust shield (7), and secondary dust shield (7) is located on the belt conveying room (4).
2. go into the fragmentation of stove coal and uses the high-effective dust-removing device coke-oven plant according to claim 1, it is characterized in that: described dust shield (5) is located at the middle part of belt conveying room (4), and described secondary dust shield (7) is provided with two, and symmetry is located at the both sides of dust shield (5) respectively.
CN201120098014U 2011-04-07 2011-04-07 High-efficiency dust collection device for crushing as-fired coal of coking plant Expired - Fee Related CN202137169U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201120098014U CN202137169U (en) 2011-04-07 2011-04-07 High-efficiency dust collection device for crushing as-fired coal of coking plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201120098014U CN202137169U (en) 2011-04-07 2011-04-07 High-efficiency dust collection device for crushing as-fired coal of coking plant

Publications (1)

Publication Number Publication Date
CN202137169U true CN202137169U (en) 2012-02-08

Family

ID=45548248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201120098014U Expired - Fee Related CN202137169U (en) 2011-04-07 2011-04-07 High-efficiency dust collection device for crushing as-fired coal of coking plant

Country Status (1)

Country Link
CN (1) CN202137169U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103381386A (en) * 2012-05-04 2013-11-06 江苏腾达建筑机械有限公司 Symmetric integrated crushing system
CN103506364A (en) * 2013-10-24 2014-01-15 昆山市盛兴设备安装有限公司 Crusher dust removing system
CN103909003A (en) * 2014-03-27 2014-07-09 芜湖恒杰膨润土科技有限公司 Novel grinding mill for producing bentonite
CN112871406A (en) * 2021-01-12 2021-06-01 黑龙江龙煤双鸭山矿业有限责任公司 Deep screening and crushing process for raw coal system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103381386A (en) * 2012-05-04 2013-11-06 江苏腾达建筑机械有限公司 Symmetric integrated crushing system
CN103381386B (en) * 2012-05-04 2015-03-04 江苏腾达建筑机械有限公司 Symmetric integrated crushing system
CN103506364A (en) * 2013-10-24 2014-01-15 昆山市盛兴设备安装有限公司 Crusher dust removing system
CN103909003A (en) * 2014-03-27 2014-07-09 芜湖恒杰膨润土科技有限公司 Novel grinding mill for producing bentonite
CN103909003B (en) * 2014-03-27 2016-06-22 芜湖恒杰膨润土科技有限公司 Make the new flour miller of bentonite
CN112871406A (en) * 2021-01-12 2021-06-01 黑龙江龙煤双鸭山矿业有限责任公司 Deep screening and crushing process for raw coal system

Similar Documents

Publication Publication Date Title
CN202137169U (en) High-efficiency dust collection device for crushing as-fired coal of coking plant
CN104444233A (en) Dust cleaning device for belt conveyor belt surface
CN203108360U (en) Wet-type dust collector
CN202438233U (en) Self-flow type unloading device of dust removal and powder feed system
CN201988283U (en) Dust collection device in feed mill
CN204714072U (en) A kind of Pneumatic conveyer
CN208177655U (en) A kind of white carbon black exclusion device
CN202188737U (en) Drying and dedusting system with powder recovery device
CN204710525U (en) A kind of disintegrating machine dust pelletizing system of high-efficiency environment friendly
CN104294036A (en) Iron ore pellet roasting device
CN203091382U (en) Dust recycling device of coating production workshop
CN204280612U (en) A kind of belt of belt conveyor surface dust cleaning plant
CN203530816U (en) Exhaust gas chamber of plant-mix asphalt thermal regeneration equipment
CN202329052U (en) Dedusting exhaust system of tube bundle drying machine
CN105128153A (en) Concrete-dust centralized recycling system
CN202943068U (en) Environment-friendly recovery system of flaker
CN102022918A (en) Reheating kiln furnace dust remover
CN104438269A (en) Stock yard dust removal device
CN204398176U (en) The air retracting device of all sides of banbury
CN203183821U (en) Dust remover air inlet system
CN205518142U (en) Integrated form milling machine
CN102654352B (en) Drying dust removal system with powder recovery device and powder recovery method
CN203971682U (en) The hot flue gas processing device of a kind of fine cleaned coal drying system
CN104147884B (en) The hot flue gas treating process of a kind of fine cleaned coal drying system
CN206184189U (en) Electric automated dust removal device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120208