CN202063630U CN2011201621222U CN201120162122U CN202063630U CN 202063630 U CN202063630 U CN 202063630U CN 2011201621222 U CN2011201621222 U CN 2011201621222U CN 201120162122 U CN201120162122 U CN 201120162122U CN 202063630 U CN202063630 U CN 202063630U
Authority
CN
China
Prior art keywords
bracket
steel strand
hardware
balance sling
metal structural
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201621222U
Other languages
Chinese (zh)
Inventor
张为明
熊高峡
杨军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Co Ltd
Original Assignee
China Gezhouba Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CN2011201621222U priority Critical patent/CN202063630U/en
Application granted granted Critical
Publication of CN202063630U publication Critical patent/CN202063630U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

A hoisting device for large-scale metal structural members is characterized in that at least two lower brackets are arranged at the lower end of a metal structural member, and upper brackets are arranged in corresponding positions at the upper end of the metal structural member; the upper brackets are connected with the lower brackets through a plurality of steel stranded wires; an anchorage device is arranged at one end of each of the steel stranded wires, and an oil cylinder is arranged at the other end of each of the steel stranded wires; at least one baffle block is arranged on the upper bracket in a position close to the steel stranded wires, two lifting eye plates with the interval of B are arranged in the middle of the upper brackets, and balancing hoisting tools are connected with the lifting eye plates through pin shafts; lifting jacks are arranged between the balancing hoisting tools and the baffle block and used for enabling the balancing hoisting tools to move along the axial lines of the pin shafts; and the thicknesses of the balancing hoisting tools are smaller than the interval B between the two lifting eye plates. By adopting the structure (particularly the structure between the upper brackets and the balancing hoisting tools), the hoisting device for large-scale metal structural members has the advantage that the fine adjustment of gravity center can be achieved by finely adjusting the positions of the balancing hoisting tools through the lifting jacks, so as to the prevent the inclination of the metal structural member during hoisting.

Description

Large-scale hardware lifting appliance
Technical field
The utility model relates to a kind of lifting appliance, particularly a kind of large-scale hardware lifting appliance that is applicable to that the large-scale hard ware in the hydrojunction or in the other industry is installed.Also be fit to large-scale, complicated, irregular, can't weld the metal steel structure spare of Heave Here.
Background technology
To the suspension centre design of metal steel structure lifting, existingly adopt the welded steel structure suspension centre usually, with steel rope or highstrenghtpiston's nylon tape binding packing, mode such as special hanger be set when making carry out.The large-scale hardware of certain ship lock, for example miter gate highly reaches 38.5m, the wide 17.5m of reaching, the thick 3.2m of reaching, and the length ratio is seriously asymmetric.Because of complex structure, its center of gravity also is difficult to accurate calculating; As adopt welding hanger mode, because of the gate ton surplus in the of 900 that weighs, then the hanger size is difficult to greatly arrange, even if can arrange, also can be out of shape because of the welding job amount cause miter gate greatly; As adopt the packing structure, because of the miter gate enormous size, center of gravity is difficult to accurate calculating, can't pack.And the miter gate in this engineering is not to lift simply, set back again after raising 10m but mounted miter gate sling, and the concentricity accuracy requirement of Bottom Hinge for Miter lock Gate and top pivot adopts method and apparatus of the prior art can't solve the lifting and the return problem of this miter gate for being not more than 1mm.
Summary of the invention
Technical problem to be solved in the utility model provides a kind of large-scale hardware lifting appliance, can solve the medium-and-large-sized hardware of prior art upgrades suspension centre problem is set, guaranteed the lifting safety of hardware, deflection is little in the lifting process, guaranteed accurately resetting of miter gate top, end pivot, precision reaches in the 1mm, and can dynamically adjust the position of Heave Here in the lifting process.
For solving the problems of the technologies described above, the technical scheme that the utility model adopted is: a kind of large-scale hardware lifting appliance, and the hardware lower end is provided with at least two bottom brackets, and hardware upper end opposite position is provided with bracket;
Connect by many steel strand between bracket and the bottom bracket, steel strand one end is provided with ground tackle, and the other end is provided with oil cylinder;
Position near steel strand on the described bracket is provided with at least one block, the shackle plate that it is B that the middle part is provided with two spacings, and balance sling is connected with shackle plate by bearing pin;
Be provided with between balance sling and the block and be used to jack that balance sling is moved along the bearing pin axis.
Spacing B's between the thickness of described balance sling and two shackle plates is poor, in more than 1/4 of balance sling thickness, and is not more than 40mm.
Also be provided with strain gauge between described bottom bracket or bracket and the hardware.
Described block is two, lays respectively at the position of bracket two ends near steel strand.
Described balance sling two ends are provided with and hoist cable bonded assembly hole, and the below, middle part is provided with arc, and arc is provided with pin shaft hole.
Described bracket two ends are provided with and steel strand bonded assembly hole, are provided with block with the side in steel strand bonded assembly hole, and the middle part is provided with two shackle plates.
The inclination of hardware on positive facade can overcome by a plurality of Heave Heres are set, but the inclination on side elevation then is difficult to overcome, and be particularly remarkable in the hardware lifting that this technical barrier is big in flakiness ratio, weight is big and accuracy requirement is high.
A kind of large-scale hardware lifting appliance that the utility model provides, by adopting above-mentioned structure, the structure between bracket and the balance sling particularly, thus position that can be by jack micro-adjustment balance sling is to realize center of gravity fine setting, the inclination of hardware when preventing to lift by crane.Center of gravity is adjusted back in place and gate can be sling by balance sling and hoist cable, and guarantees to lift concentricity in 1mm.The strain gauge that is provided with is monitored in the steel strand tension process, prevents the hardware distortion.Benefit is especially remarkable in the lifting construction of the large-scale hardware that device of the present utility model is big in flakiness ratio, weight is big and accuracy requirement is high.
Description of drawings
The utility model is described in further detail below in conjunction with drawings and Examples:
Fig. 1 is the integral structure lateral plan of the utility model device.
Fig. 2 is the integral structure front view of the utility model device.
Fig. 3 is the front view of bracket in the utility model device.
Fig. 4 is the birds-eye view of bracket in the utility model device.
Fig. 5 is the birds-eye view of balance sling in the utility model device.
Fig. 6 is the front view of balance sling in the utility model device.
Fig. 7 is the partial enlarged drawing at A place among Fig. 1.
The specific embodiment
In Fig. 1, Fig. 2, a kind of large-scale hardware lifting appliance, hardware 1 lower end is provided with at least two bottom brackets 2, and hardware 1 upper end opposite position is provided with bracket 3;
Connect by many steel strand 4 between bracket 3 and the bottom bracket 2, steel strand 4 one ends are provided with ground tackle 5, and the other end is provided with oil cylinder 6; In this example, bracket 3 and bottom bracket 2 are symmetrically arranged with four groups of apertures, are used to install steel strand 4, according to hardware 1, are the rigidity requirement of miter gate in this example, determine the diameter and the radical of steel strand.Steel strand one end is fixing with ground tackle 5, and for ease of operation, ground tackle 5 is arranged on the lower end of steel strand usually, and every group of steel strand are selected the size of oil cylinder 6 for use according to the tension force size, and oil cylinder 6 is arranged on the bracket and is connected with steel strand 4.Two covers are after totally eight groups of clamping systems deploy, start electrical controller and carry out integral tension, front and back position between every group of bracket 3 or bottom bracket 2 and hardware 1 is furnished with strain gauge, monitors in stretching process, prevents hardware 1 distortion.For ease of timely adjustment, electrical controller both can whole be controlled, and also can control separately.For preventing that steel strand and member direct contact from causing damage, between steel strand and member, be aided with wood block filler and support.
Position near steel strand on the described bracket 3 is provided with at least one block 9, the shackle plate 8 that it is B that the middle part is provided with two spacings, and the balance sling 11 on the hoist cable 12 is connected with shackle plate 8 by bearing pin 13.
In Fig. 7, spacing B's between the thickness of described balance sling 11 and two shackle plates 8 is poor, in more than 1/4 of balance sling 11 thickness, and be not more than 40mm, be that balance sling 11 also has a bigger gap between two shackle plates 8, be provided with between balance sling 11 and the block 9 and be used to jack 10 that balance sling 11 is moved along bearing pin 13 axis.Block 9 is the stressed bases as jack 10, by jack 10 positions of fine setting balance sling 11 on bearing pin 13, perhaps making balance sling 11 drive bearing pin 13 moves in the hole of shackle plate 8, promptly finely tune the relative position between balance sling 11 and the shackle plate 8, thereby make distance C between the center of gravity line of the plumb bob vertical of balance sling 11 and hardware 1 as far as possible for minimum, thereby adjust hardware 1, it in this example the attitude of miter gate, miter gate tilts when preventing to lift by crane, and center of gravity is adjusted back in place and miter gate can be sling by balance sling and hoist cable.
The scheme of optimizing is that described block 9 is two, lays respectively at the position of bracket 3 two ends near steel strand.
In Fig. 5, Fig. 6, described balance sling 11 two ends are provided with and hoist cable 12 bonded assembly holes, and the below, middle part is provided with arc, and arc is provided with pin shaft hole.
In Fig. 3, Fig. 4, described bracket 3 two ends are provided with and steel strand 4 bonded assembly holes, are provided with block 9 with the side in steel strand 4 bonded assembly holes, and the middle part is provided with two shackle plates 8.
Concrete lifting step is:
1, according to the weight and the version of miter gate 1, design bracket 3 and 2 liang of covers of bottom bracket promote with 11 liang of covers of balance sling.Balance sling 11 adopts bearing pin 13 to be connected with bracket 3 by shackle plate 8.For realizing the fine setting of miter gate center of gravity, on bracket 3, be welded with block 9, between block 9 and balance sling 11, jack 10 is installed.Be arranged with totally four circular holes at the two ends of each bracket 3 and bottom bracket 2, be used for fixing stretch-draw steel strand 4 and oil cylinder 6.According to gate structure and weight, adopt 8 groups of steel strand 4 altogether, symmetric arrangement 8 group oil cylinders 6 are used for stretch-draw packer word strobe on bracket 3.
2, make bottom bracket 2 and bracket 3.In originating firm, made carriage 2 and bracket 3, and be up to the standards, steel strand 4 and the oil cylinder 6 selected for use have been checked that it is qualified to confirm by the program and the method for correlated quality administrative provisions by design paper.
3, packing apparatus is installed.Install carriage 3, bottom bracket 2, steel strand 4, ground tackle 5 and oil cylinder 6 according to design paper, and between miter gate and bracket 3 front and back positions, arrange pressure sensor 7, avoid steel strand 4 directly to contact in the miter gate front and back with an amount of wooden unit of location arrangements between the steel strand 4, in order to avoid damage steel strand 4 with miter gate; The ground tackle 5 and oil cylinder 6 and steel strand tension detecting device of steel strand are installed then;
4, start electrical controller driving oil cylinder 6 with steel strand 4 tensionings, every group of steel strand load is no more than 200 tons.Detect the tension force size in the stretching process, in order to avoid miter gate distortion and break steel strand 4 in good time.
5, try to hang behind the whole installation qualifications of whole device.Miter gate can put down miter gate, allow hoisting wirerope not stress if any inclination, uses the relative position of jack 10 fine setting balance slings 11 and shackle plate 8 then according to the miter gate direction of tilt, and micro-adjustment is made in the Heave Here.
6, in whole miter gate lifting and the decline process, design has special detecting device that miter gate and tackling system are detected in real time.

Claims (6)

1. one kind large-scale hardware lifting appliance, it is characterized in that: hardware (1) lower end is provided with at least two bottom brackets (2), and hardware (1) upper end opposite position is provided with bracket (3);
Connect by many steel strand (4) between bracket (3) and the bottom bracket (2), steel strand (4) one ends are provided with ground tackle (5), and the other end is provided with oil cylinder (6);
The position that described bracket (3) goes up near steel strand is provided with at least one block (9), the shackle plate that it is B that the middle part is provided with two spacings (8), and balance sling (11) is connected with shackle plate (8) by bearing pin (13);
Be provided with between balance sling (11) and the block (9) and be used to jack (10) that balance sling (11) is moved along bearing pin (13) axis.
2. a kind of large-scale hardware lifting appliance according to claim 1, it is characterized in that: the spacing B's between the thickness of described balance sling (11) and two shackle plates (8) is poor, in more than 1/4 of balance sling (11) thickness, and be not more than 40mm.
3. a kind of large-scale hardware lifting appliance according to claim 1 is characterized in that: also be provided with strain gauge (7) between described bottom bracket (2) or bracket (3) and the hardware (1).
4. a kind of large-scale hardware lifting appliance according to claim 1, it is characterized in that: described block (9) is two, lays respectively at the position of bracket (3) two ends near steel strand.
5. a kind of large-scale hardware lifting appliance according to claim 1 is characterized in that: described balance sling (11) two ends are provided with and hoist cable (12) bonded assembly hole, and the below, middle part is provided with arc, and arc is provided with pin shaft hole.
6. a kind of large-scale hardware lifting appliance according to claim 1, it is characterized in that: described bracket (3) two ends are provided with and steel strand (4) bonded assembly hole, be provided with block (9) with a side in steel strand (4) bonded assembly hole, the middle part is provided with two shackle plates (8).
CN2011201621222U 2011-05-20 2011-05-20 Hoisting device for large-scale metal structural members Expired - Lifetime CN202063630U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201621222U CN202063630U (en) 2011-05-20 2011-05-20 Hoisting device for large-scale metal structural members

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201621222U CN202063630U (en) 2011-05-20 2011-05-20 Hoisting device for large-scale metal structural members

Publications (1)

Publication Number Publication Date
CN202063630U true CN202063630U (en) 2011-12-07

Family

ID=45057500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201621222U Expired - Lifetime CN202063630U (en) 2011-05-20 2011-05-20 Hoisting device for large-scale metal structural members

Country Status (1)

Country Link
CN (1) CN202063630U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102190242A (en) * 2011-05-20 2011-09-21 中国葛洲坝集团股份有限公司 Hoisting device of large-size metal structural member
CN104709810A (en) * 2013-12-16 2015-06-17 无锡泛亚环保科技有限公司 Wood wool cement board sling with adjustable height

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102190242A (en) * 2011-05-20 2011-09-21 中国葛洲坝集团股份有限公司 Hoisting device of large-size metal structural member
CN102190242B (en) * 2011-05-20 2013-04-03 中国葛洲坝集团股份有限公司 Hoisting device of large-size metal structural member
CN104709810A (en) * 2013-12-16 2015-06-17 无锡泛亚环保科技有限公司 Wood wool cement board sling with adjustable height

Similar Documents

Publication Publication Date Title
CN102190242B (en) Hoisting device of large-size metal structural member
CN202063630U (en) Hoisting device for large-scale metal structural members
CN111532991A (en) Crane overload monitoring system and monitoring method
CN105149965A (en) General assembling technology for crane
CN107303941B (en) Derrick of marine drilling ship and centering installation method thereof
CN110846463A (en) Integral hoisting method for super-huge converter shell
CN102381623B (en) Special lifting tool for circuit breaker
EP3083391B1 (en) Saddle and hook system
KR20170002977A (en) crane block loader
CN109132837B (en) Steel wire rope winding system capable of automatically adjusting balance of lifting appliance
CN201534747U (en) Gantry crane rope difference adjusting mechanism
CN211444689U (en) General hoist based on bridge segment promotes
CN201961917U (en) Broken rope protection device of construction lifting device
CN107235413A (en) A kind of component Current Collector Sleave
CN106596081A (en) Swing test method for splay cable saddle of suspension bridge
CN210340074U (en) Three-dimensional adjustment hydraulic lifting appliance
CN110790121A (en) General hoist based on bridge segment promotes
CN102785067B (en) Device and method for assembling and disassembling heavy hydraulic cylinder fast
CN203811477U (en) Single-beam bearing force detection load applying system
JP2017036114A (en) Method for hoisting pump system and pump system
CN112359804A (en) Hoisting and mounting method for bolt type pile leg
CN217972341U (en) Installation device of double T plates
CN201980848U (en) Rotary distributable moment balancing device
CN203877682U (en) Detection instrument for elevator overload protection device
CN112013827B (en) Steel strand hydraulic elevator perpendicularity detection device and detection method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20111207

Effective date of abandoning: 20130403

RGAV Abandon patent right to avoid regrant