CN201952444U - Multipurpose combustion air high-temperature preheating system for hot-blast air furnace - Google Patents

Multipurpose combustion air high-temperature preheating system for hot-blast air furnace Download PDF

Info

Publication number
CN201952444U
CN201952444U CN2011200097348U CN201120009734U CN201952444U CN 201952444 U CN201952444 U CN 201952444U CN 2011200097348 U CN2011200097348 U CN 2011200097348U CN 201120009734 U CN201120009734 U CN 201120009734U CN 201952444 U CN201952444 U CN 201952444U
Authority
CN
China
Prior art keywords
air
blast
hot
furnace
hotblast stove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011200097348U
Other languages
Chinese (zh)
Inventor
李欣
张福明
毛庆武
倪苹
梅丛华
姚轼
钱世崇
银光宇
许云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang International Engineering Technology Co Ltd
Original Assignee
Beijing Shougang International Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang International Engineering Technology Co Ltd filed Critical Beijing Shougang International Engineering Technology Co Ltd
Priority to CN2011200097348U priority Critical patent/CN201952444U/en
Application granted granted Critical
Publication of CN201952444U publication Critical patent/CN201952444U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Air Supply (AREA)

Abstract

The utility model relates to a multipurpose combustion air high-temperature preheating system for a hot-blast air furnace, belonging to the technical field of hot-blast air furnaces in metallurgy industry. The multipurpose combustion air high-temperature preheating system consists of a hot-blast air furnace, a stop valve, a regulating valve, a gas pipe for the hot-blast air furnace, an air pipe for the hot-blast air furnace, a hot-blast air pipe, a flue, a cold-blast air pipe, a temporary hot-blast air valve, a temporary hot-blast air pipe, a temporary cold-blast air valve, a temporary cold-blast air pipe, a preheating furnace, a mixed air furnace, a gas pipe for the preheating furnace, an air pipe for the preheating furnace, a hot air pipe, a cold air pipe, a mixed air pipe and a fan. The multipurpose combustion air high-temperature preheating system can be applied in the major repair and reconstruction projects of blast furnaces, or in the separate maintenance or reconstruction projects of hot-blast air furnace systems, or in the new construction projects of blast furnaces. The preheating furnace can not only provide the high-temperature hot-blast air for the blast furnace but also provide the combustion air for high-temperature preheating of the blast furnace, and ensures that the influence of maintenance or reconstruction of the hot-blast air finance on the blast furnace is reduced to minimum.

Description

A kind of multiduty hotblast stove combustion air preheated in high temperature system
Technical field
The utility model belongs to metallurgy industry hotblast stove technical field, a kind of multiduty hotblast stove combustion air preheated in high temperature system particularly is provided, be applicable to the hot blast stove system that blast furnace ironmaking and fused reduction iron-smelting are used in the iron-smelting process, be specially adapted to maintenance or transformation that hot blast stove system transformation during the blast furnace overhaul transformation or hot blast stove system carry out separately.
Background technology
Along with increasingly sharpening and the environmental requirement more and more higher to iron-smelting process of steel industry competition, the blast furnace of the world and China is all quickening to large scale development.The main path that blast furnace maximizes is newly-built blast furnace and original place overhauling reform, and the blast furnace overhaul transformation is very large to the influence of iron and steel enterprise, therefore will shorten the overhaul time as far as possible, reduces the influence to enterprise.Hotblast stove is as the important component part of blast furnace system, and it mainly acts on is for blast furnace provides high-temperature hot-air, realizes strengthening smelting, reduction coke ratio, increase output for blast furnace and creates conditions.During the blast furnace (BF) expansion overhauling reform, generally all need hotblast stove is carried out corresponding upgrading, and 3~4 hotblast stoves of every blast furnace one general configuration, the construction period of hot blast stove system is greater than blast furnace, therefore hot blast stove system is generally prior to the blast-furnace body transformation that carries out large repairs, concrete grammar is that original blast furnace still keeps producing, and hotblast stove is transformed one by one, provides hot blast by the hotblast stove of not transforming or having transformed for blast furnace.Because the hotblast stove quantity of work has reduced, original wind-warm syndrome and air quantity can't satisfy simultaneously, and perhaps the checking amount is protected wind-warm syndrome, and perhaps the checking temperature is protected air quantity, and the two all can cause the blast furnace underproduction, and energy consumption increases, and enterprise is affected greatly.After hotblast stove at high temperature moves for some time in addition, may carry out bigger maintenance under the condition of not blowing out of blast furnace, this also can produce a very large impact blast furnace.
Along with the continuous development that blast furnace maximizes, the wind-warm syndrome level that blast furnace requires is also more and more higher, to improve coal powder injection ratio, the coke of saves valuable.But domestic Steel Plant generally lack high heating value gas, in the wind-warm syndrome that realizes under the condition of single fire blast furnace gas more than 1250 ℃, must carry out preheating to air or coal gas.At present, existing multiple pre-heating technique comes into operation, wherein, the super-huge blast furnace of the Shoudu Iron and Steel Co Jing Tang 5500m3 of Steel Plant adopts the technical process of combustion air two-stage preheating+blast furnace gas low-temperature prewarming, utilize low temperature heat pipe heat exchanger with about combustion air and blast furnace gas low-temperature prewarming to 200 ℃ earlier, reclaim fume afterheat simultaneously, utilize 2 little preheating ovens with more than the combustion air preheated in high temperature to 500 ℃ then, guarantee that the stable high wind-warm syndrome that provides more than 1250 ℃ of blast furnace promptly is provided hot blast stove system single fire blast furnace gas.The great advantage of this technical process is life-span length, working stability, thermo-efficiency height, preheating oven is identical with hotblast stove life, and reliable operation, there is not the problem that with the passing of time lost efficacy, needed maintenance even low temperature heat pipe heat exchanger loses efficacy, and depended merely on the preheating oven warm-up combustion-supporting air and still can guarantee higher hot blast temperature.Steel Plant such as this technical process has been successfully applied to the first Qin, moves steel, capital Tang, heat size has been contained 1200m 3, 1800m 3, 2500m 3, 4000m 3, 5500m 3Etc. a plurality of ranks, its result of use has obtained owner's general favorable comment.This technical process not only can be applicable to newly-built blast furnace engineering, more can be applicable to the blast furnace overhaul transformation, owing to after the blast furnace overhaul transformation wind-warm syndrome is required corresponding raising, therefore can utilize this technical process to meet the demands fully, simultaneously also will be in conjunction with engineering reality, the flexible combination operational path effectively utilizes old facility, and reduces the influence of overhauling reform to enterprise as much as possible.
Summary of the invention
The purpose of this utility model is to provide a kind of multiduty hotblast stove combustion air preheated in high temperature system, realizes that the single fire blast furnace gas just can be the high-temperature hot-air that blast furnace is stablized to be provided more than 1250 ℃.With this process application in the maintenance or when transforming separately of blast furnace overhaul improvement project or hot blast stove system, preheating oven can be used as temporarily hotblast stove uses, for blast furnace provides hot blast, solve because hotblast stove overhauls or transform the problem of the hot blast stove system scarce capacity that causes one by one, when hot blast stove system maintenance or transform and finish, preheating oven still normally uses as the high temperature primary heater unit of combustion air.On the other hand, in blast furnace overhaul transformation or when maintenance, this high temperature preheating technology also can combine with original hotblast stove, is the preheating of air stove with old hot-blast furnace transformation, for newly-built hotblast stove provides the combustion air of high temperature preheating, effectively utilizes old facility to realize high wind-warm syndrome.
The utility model comprises following composition: hotblast stove, trip valve, variable valve, hotblast stove gas pipe, the hotblast stove blast main, heating duct, flue, cold-air duct, interim hot blast valve, interim heating duct, interim cold blast valve, interim cold-air duct, preheating oven mixes wind furnace, the preheating oven gas pipe, preheating oven blast main, warm-air pipe, cold air pipe, mixing wind tube, blower fan.The hotblast stove gas pipe provides burning coal gas for hotblast stove; Hotblast stove between mixed wind furnace and hotblast stove, will mix wind furnace and hotblast stove couples together with blast main, for hotblast stove provides combustion air; Heating duct is carried high-temperature hot-air to blast furnace between hotblast stove and blast furnace; Flue is used to drain the useless flue gas of hotblast stove and preheating oven generation; Cold-air duct is used for to the hotblast stove transporting cold wind; Interim heating duct couples together warm-air pipe and heating duct between warm-air pipe and heating duct, is used for the hot blast of carrying preheating oven to produce to blast furnace; Interim cold-air duct couples together cold air pipe and cold-air duct between cold air pipe and cold-air duct, is used for to the preheating oven transporting cold wind; Preheating oven is used for high temperature preheating hotblast stove air; Mix the warm air that freezing air that wind furnace sends mixing wind tube here and warm-air pipe send here and mix, the temperature-stable of air of guaranteeing to infeed hotblast stove is in set(ting)value; The preheating oven gas pipe provides burning coal gas for preheating oven; The preheating oven blast main provides combustion air for preheating oven; Warm-air pipe couples together preheating oven and mixed wind furnace between preheating oven and mixed wind furnace, and the warm air that preheating oven produces is sent into mixed wind furnace; Cold air pipe is used for carrying freezing air to preheating oven; Mixing wind tube is used for carrying freezing air to mixed wind furnace; Burner blower is used for providing combustion air to preheating oven and hotblast stove.
When the utility model is used for blast furnace overhaul improvement project or independent maintenance of hot blast stove system or improvement project, difference according to job schedule, preheating oven will be brought into play different effects, reduce the hotblast stove maintenance to greatest extent and transform the influence that production causes to blast furnace, finish at overhauling reform, after putting into serial production, can guarantee also that hot blast stove system single fire blast furnace gas can be stable for blast furnace provides high-temperature hot-air more than 1250 ℃, concrete operational path is as follows.
Before blast furnace overhaul transformation or hotblast stove maintenance transformation, build two preheating ovens in advance, build during the preheating oven, but original blast furnace and hotblast stove ordinary production are unaffected.
After preheating oven builds up, one section interim heating duct is installed between the heating duct of the warm-air pipe of preheating oven and hotblast stove, interim hot blast valve is installed at two of interim heating duct; One section interim cold-air duct is installed between the cold-air duct of the cold air pipe of preheating oven and hotblast stove, and interim cold blast valve is installed at interim cold-air duct two.Like this, cold wind is infeeded preheating oven, just can utilize preheating oven directly to be the blast furnace air-supply, by controlling interim hot blast valve and interim cold blast valve dismounting temporary pipeline and do not influence blast furnace and the ordinary production of the hotblast stove that do not overhaul easily.
After preheating oven and temporary pipeline all build up, begin by seat maintenance or transformation hotblast stove.The maintenance of hotblast stove or transform during, be the blast furnace air-supply by all the other hotblast stoves and preheating oven because replenishing of preheating oven arranged, wind-warm syndrome and air quantity can not fluctuate too big, can effectively reduce the hotblast stove maintenance or transform influence to blast furnace.
If the blast furnace overhaul improvement project, when the maintenance of hotblast stove or when transforming near the middle and later periods, blast furnace has possessed the overhauling reform condition, blast furnace stopping, beginning overhauling reform.During blast furnace overhaul was transformed, hotblast stove was finished residue maintenance transformation task, and removed interim hot blast valve, interim heating duct, interim cold blast valve and interim cold-air duct, and the temporary valve of dismounting can be used as the hot blast valve of hotblast stove and the spare parts of cold blast valve.
If hot blast stove system overhauls separately or improvement project, Deng hotblast stove all overhaul or transform finish after, remove interim hot blast valve, interim heating duct, interim cold blast valve and interim cold-air duct, the temporary valve of dismounting can be used as the hot blast valve of hotblast stove and the spare parts of cold blast valve.
After maintenance or improvement project finish, hotblast stove and preheating oven formally come into operation, at this moment, preheating oven recovers one's work, adopt 1 to burn 1 working system of sending, burning phase burning blast furnace gas is the regenerator store heat, on air hotblast stove is preheated to more than 450 ℃ with combustion air, for hot blast stove system single fire blast furnace gas provides the high-temperature hot-air more than 1250 ℃ to create conditions for blast furnace is stable.
When the utility model was applied to blast furnace overhaul improvement project or independent maintenance of hot blast stove system or improvement project, the form of hotblast stove and preheating oven can be selected flexibly according to engineering is actual, and was unrestricted.The present invention also can be used with the old or newly-built low-temperature prewarming device of blast furnace, and by reclaiming fume afterheat, air and coal gas that hotblast stove and preheating oven are used carry out preheating, improve system thermal efficiency, and is energy-saving and cost-reducing, the protection environment.
The utility model also can make full use of old hotblast stove, is preheating oven with old hot-blast furnace transformation, effectively improves the hot blast stove system wind pushing temperature.
For the blast furnace overhaul transformation project of the newly-built hotblast stove that requires to change places,, huge waste will be caused if old hotblast stove do not added to utilize directly to be removed; If continue to use as hotblast stove, can't be complementary with the wind-warm syndrome blast of transforming the back blast furnace again, make enterprise feel in a dilemma.
Under this condition, can be preheating oven with old hot-blast furnace transformation fully in conjunction with the present invention, for newly-built hotblast stove provides the combustion air of high temperature preheating, concrete operational path be as follows.
Blast furnace overhaul is built newly-built hotblast stove, original blast furnace and hotblast stove ordinary production before transforming in advance.
When the construction of newly-built hotblast stove entered the middle and later periods, the overhauling reform of beginning blast furnace began the transformation of old hotblast stove simultaneously, comprises the transformation of old hotblast stove body, old heating duct transformation, and newly-built mixed wind furnace is also wanted in blast main transformations etc. in addition.
The blast furnace overhaul transformation is finished, blast furnace is put into serial production, the preheating oven (old hotblast stove) that newly-built hotblast stove and transformation are finished also formally comes into operation, provide preheating temperature greater than 450 ℃ combustion air by preheating oven for newly-built hotblast stove, for hot blast stove system single fire blast furnace gas provides the high-temperature hot-air more than 1250 ℃ to create conditions for blast furnace is stable.
Therefore the present invention has general adaptability to the blast furnace overhaul transformation project of using multi-form hotblast stove to the form of preheating oven and hotblast stove without limits.When old hot-blast furnace transformation was preheating oven, the present invention can be used with the old or newly-built low-temperature prewarming device of blast furnace equally, by reclaiming fume afterheat; air and coal gas that hotblast stove and preheating oven are used carry out preheating; improve system thermal efficiency, energy-saving and cost-reducing, the protection environment.
When the present invention was used for newly-built blast furnace project, hot blast stove system and blast furnace were gone into operation synchronously, and this moment, the high temperature preheating technical process was as follows.
Burner blower provides temperature to be about air about 35 ℃, and the air of generation is divided into three parts, and a part enters mixes wind furnace and mix wind usefulness, and a part is used for the preheating oven burning, and some is used for and the preheating oven heat exchange forms warm air.
Preheating oven from gaspipe network, enters the preheating oven burning through preheating oven with gas pipe, for the regenerator in the preheating oven provides heat with coal gas.The useless flue gas that burning produces is drained through flue.
The regenerator of preheating oven is after burning phase store heat, on air freezing air is being sent into preheating oven through cold air pipe, become warm air behind the heat of absorption regenerator, warm air enters mixed wind furnace through warm-air pipe, the freezing air that comes with mixing wind tube mixes, the hotblast stove air that formation temperature meets the demands enters hotblast stove through hotblast stove with blast main and participates in burning.
Hotblast stove from gaspipe network, enters Combustion of Hot Air Furnace through hotblast stove with gas pipe, for the regenerator in the hotblast stove provides heat with coal gas.The useless flue gas that burning produces is drained through flue.
The regenerator of hotblast stove is on air being sent into hotblast stove with cold wind through cold-air duct after burning phase store heat, become hot blast behind the heat of absorption regenerator, and hot blast is sent into blast furnace through heating duct and used.
The quantity of preheating oven is 2, adopts 1 to burn 1 working system of sending.The quantity of hotblast stove is 3 or 4, and the moderate working system of 3 hotblast stoves is that 2 burnings 1 are sent, and the moderate working system of 4 hotblast stoves is that 3 burnings 1 are sent or 2 burnings 2 are sent.The specific form of hotblast stove can be top ignition or internal combustion type or external combustion type.The form of preheating oven can be identical with hotblast stove, also can be different with hotblast stove.
Technology of the present utility model can be used with various low-temperature prewarming devices, and for example heat-pipe heat exchanger or plate-type heat exchanger etc. utilize the low-temperature prewarming device can the efficient recovery fume afterheat, and be energy-saving and cost-reducing, the protection environment.The coal gas that hotblast stove and preheating oven are used is preheated to about 200 ℃ through the low-temperature prewarming device, sends into the burning of hotblast stove and preheating oven again; The air that hotblast stove and preheating oven are used is preheated to about 200 ℃ through the low-temperature prewarming device, and the heat supply wind furnace uses after preheating oven is preheated to more than 450 ℃ again, guarantees under the condition of single fire blast furnace gas, is the stable high-temperature hot-air that provides more than 1250 ℃ of blast furnace.
In sum, the present invention is a kind of high temperature preheating technical process that can be applicable to blast furnace overhaul transformation project or the independent maintenance of hot blast stove system or transformation project or newly-built blast furnace project.At the specific requirement of different engineerings, rationally arrange sequence of construction, make full use of old facility, preheating oven is finished different process tasks in the different construction stages, guarantees the hotblast stove maintenance or transform the influence that blast furnace is produced to be reduced to minimum.After putting into serial production, the present invention can guarantee that the stable high-temperature hot-air that provides more than 1250 ℃ of blast furnace is being provided under the condition of single fire blast furnace gas hot blast stove system.
Main advantage of the present utility model comprises:
1) project adaptability is strong, and independent maintenance of blast furnace overhaul transformation project or hot blast stove system or transformation project or newly-built blast furnace project all are suitable for;
When 2) being used for the blast furnace overhaul transformation project, can MINly reducing the hotblast stove maintenance and transform the influence that blast furnace is produced, solve hotblast stove and the unmatched problem of blast furnace construction period;
When 3) being used for independent maintenance of hot blast stove system or transformation project, the preheating oven that builds up in advance can be used as interim hotblast stove and uses, and can solve because certain the insufficient problem of hot blast stove system heat storage capacity that the hotblast stove maintenance causes makes blast furnace production unaffected.
When 4) being used for the blast furnace overhaul transformation project, can make full use of old hotblast stove, transform it as preheating oven, by excavating equipment potential, the wind pushing temperature of hot blast stove system be improved greatly;
5) the stable high-temperature hot-air that provides more than 1250 ℃ of blast furnace promptly is provided the single fire blast furnace gas, has effectively utilized low calorie fuels, for the energy Conservation of Blast Furnace consumption reduction creates conditions;
6) to the form no requirement (NR) of hotblast stove and preheating oven, and the life-span is long, can not lose efficacy;
7) can with various low-temperature prewarming device flexible combination, the efficient recovery fume afterheat is realized low-carbon emission.
Description of drawings
Fig. 1 is a kind of structural representation of the present utility model.Wherein, 2, No. 3 hotblast stoves 3 of 1, No. 2 hotblast stoves of No. 1 hotblast stove, trip valve 4, variable valve 5, interim hot blast valve 6, interim heating duct 7, heating duct 8, hotblast stove with gas pipe 9, hotblast stove with blast main 10, flue 11, cold-air duct 12, interim cold blast valve 13, interim cold-air duct 14,16, No. 2 preheating ovens 17 of 15, No. 1 preheating oven of freezing air house steward trip valve, mix wind furnace 18, mixing wind tube 19, warm-air pipe 20, preheating oven with gas pipe 21, preheating oven with blast main 22, cold air pipe 23, blower fan 24.
Embodiment
Fig. 1 is a specific implementation of the present utility model.
When applying the present invention to the blast furnace overhaul transformation project, before blast furnace and hot-blast furnace transformation, build preheating oven and corresponding pipeline in advance, comprise that 16, No. 2 preheating ovens 17 of No. 1 preheating oven, warm-air pipe 20, preheating oven with blast main 22, cold air pipe 23, blower fan 24, install corresponding trip valve and variable valve with gas pipe 21, preheating oven on each pipeline.In addition, also to finish the installation of interim hot blast valve 6, interim heating duct 7, interim cold blast valve 13, interim cold-air duct 14.
Preheating oven, preheating oven corresponding pipeline, temporary pipeline and temporary valve Installation and Debugging finish, and after the preheating oven baker was finished, preheating oven can formally come into operation.16, No. 2 preheating ovens 17 of No. 1 preheating oven this moment all use as hotblast stove, and assisting hotblast stove is the blast furnace air-supply, and hotblast stove begins to enter the maintenance transformation stage.
At first transform hotblast stove 3 No. 3, during No. 3 hotblast stove 3 is transformed, by No. 1 hotblast stove of not transforming 1, No. 2 hotblast stoves 2 of Gai Zaoing not, No. 1 preheating oven 16, No. 2 preheating oven 17 is the blast furnace air-supply, during by No. 16, No. 1 preheating oven and No. 2 preheating ovens 17 air-supplies, freezing air house steward trip valve 15 cuts out, cold wind is through interim cold blast valve 13, interim cold-air duct 14, cold air pipe 23 enters No. 1 preheating oven 16 and No. 2 preheating ovens 17, become hot blast with the regenerator heat exchange in No. 1 preheating oven 16 and No. 2 preheating ovens 17, through warm-air pipe 20, interim hot blast valve 6 and interim heating duct 7 enter heating duct 8, send into blast furnace then and use.
If do not have No. 1 preheating oven 16 and No. 2 preheating ovens 17 to be the blast furnace air-supply, during No. 3 hotblast stove 3 is transformed, can only adopt 1 to burn 1 working system of sending by No. 1 hotblast stove 1 and No. 2 hotblast stoves 2, the wind-warm syndrome and the air quantity that infeed the hot blast of blast furnace will significantly reduce, and have a strong impact on blast furnace production.There are No. 1 preheating oven 16 and No. 2 preheating ovens 17 to assist No. 1 hotblast stove 1 and No. 2 hotblast stoves 2 to be the blast furnace air-supply, this influence can be reduced to minimum, guarantee the blast furnace ordinary production.
After No. 3 hotblast stove 3 transformations are finished and are come into operation, begin to transform hotblast stove 2 No. 2, during No. 2 hotblast stove 2 was transformed, No. 3 hotblast stoves 3,1, No. 1 preheating oven 16 of No. 1 hotblast stove of not transforming and No. 2 preheating ovens 17 of being finished by transformation were the blast furnace air-supply, and preheating oven air-supply flow process as hereinbefore.
No. 2 hotblast stove 2 is transformed latter stage, and blast furnace stops production, the beginning overhauling reform, and No. 1 hotblast stove 1 also begins to transform simultaneously.Because blast furnace stops production; no longer need air-supply; the beginning protectiveness is removed interim hot blast valve 6, interim heating duct 7, interim cold blast valve 13 and interim cold-air duct 14, and interim hot blast valve 6 that removes and interim cold blast valve 13 can be used as the spare parts of hotblast stove valve, can not cause waste.
Mixing the construction of wind furnace 18 and mixing wind tube 19 can carry out simultaneously with the construction of preheating oven, also can carry out simultaneously with hot-blast furnace transformation, specifically determines according to construction arrangement.
After blast furnace and hot-blast furnace transformation were finished and put into serial production, preheating oven was responsible for the combustion air that hotblast stove provides high temperature preheating.No. 1 preheating oven 16 and No. 2 preheating ovens 17 adopt 1 to burn 1 working system of sending.No. 1 preheating oven 16 is in burning during the phase, and air and coal gas enter No. 1 preheating oven 16 burnings with blast main 22 and preheating oven with gas pipe 21 through preheating oven respectively, and heat is stored in the regenerator, and the useless flue gas that burning produces is drained through flue 11.No. 1 preheating oven 16 is in burning during the phase, and No. 2 preheating oven 17 is on air, and freezing air enters preheating oven 17 No. 2 through cold air pipe 23, and absorbing heat from regenerator becomes warm air, enters through warm-air pipe 20 and sneaks into stove 18.In mixed wind furnace 18, to mix with warm air from the freezing air of mixing wind tube 19 from warm-air pipe 20, formation temperature is greater than 450 ℃ high temperature combustion air, and the high temperature combustion air enters hotblast stove through hotblast stove with blast main 10 and participates in burning.
The form of hotblast stove and preheating oven can be top ignition, internal combustion type, external combustion type or pebble stove, and the form of hotblast stove and preheating oven can be identical, also can be different, do not influence result of use.
Can be used with the low-temperature prewarming device, utilize the low-temperature prewarming device to reclaim fume afterheat, air and coal gas are carried out preheating, improve system thermal efficiency, energy-saving and cost-reducing, realize low-carbon emission.
By reasonable arrangement sequence of construction, the flexible combination technical process, realized the multifunction of preheating oven, hotblast stove is overhauled or transform the influence that blast furnace is caused dropped to minimum, realized after maintenance or the transformation that the single fire blast furnace gas promptly can be the stable target that high wind-warm syndrome more than 1250 ℃ is provided of blast furnace, be iron and steel enterprise's stably manufactured, energy-saving and emission-reduction are made.

Claims (1)

1. a multiduty hotblast stove combustion air preheated in high temperature system comprises: hotblast stove, trip valve, variable valve, the hotblast stove gas pipe, hotblast stove blast main, heating duct, flue, cold-air duct, interim hot blast valve, interim heating duct, interim cold blast valve, interim cold-air duct, preheating oven mixes wind furnace, the preheating oven gas pipe, preheating oven blast main, warm-air pipe, cold air pipe, mixing wind tube, blower fan; It is characterized in that: hotblast stove uses blast main between mixed wind furnace and hotblast stove, wind furnace will be mixed and hotblast stove couples together, heating duct is between hotblast stove and user, interim hot blast valve and interim heating duct are between warm-air pipe and heating duct, warm-air pipe and heating duct are coupled together, and interim cold-air duct couples together cold air pipe and cold-air duct between cold air pipe and cold-air duct, warm-air pipe couples together preheating oven and mixed wind furnace between preheating oven and mixed wind furnace.
CN2011200097348U 2011-01-13 2011-01-13 Multipurpose combustion air high-temperature preheating system for hot-blast air furnace Expired - Fee Related CN201952444U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200097348U CN201952444U (en) 2011-01-13 2011-01-13 Multipurpose combustion air high-temperature preheating system for hot-blast air furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200097348U CN201952444U (en) 2011-01-13 2011-01-13 Multipurpose combustion air high-temperature preheating system for hot-blast air furnace

Publications (1)

Publication Number Publication Date
CN201952444U true CN201952444U (en) 2011-08-31

Family

ID=44496565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200097348U Expired - Fee Related CN201952444U (en) 2011-01-13 2011-01-13 Multipurpose combustion air high-temperature preheating system for hot-blast air furnace

Country Status (1)

Country Link
CN (1) CN201952444U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103411232A (en) * 2013-08-15 2013-11-27 北京首钢国际工程技术有限公司 Design and transformation method for double-heat-storage combustion system suitable for coal gas with different heat values

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103411232A (en) * 2013-08-15 2013-11-27 北京首钢国际工程技术有限公司 Design and transformation method for double-heat-storage combustion system suitable for coal gas with different heat values
CN103411232B (en) * 2013-08-15 2015-08-05 北京首钢国际工程技术有限公司 A kind of applicable different calorific value of gas Two-cuff Technique Combustion System Design and remodeling method

Similar Documents

Publication Publication Date Title
CN101314811B (en) Method for using blast furnace gas to heat of large-scale walking beam type plate blank heating furnace
CN101839638B (en) Heat accumulating and preheating combined heating method of slag-drip high-temperature silicon steel plate blank heating furnace
CN202066385U (en) Novel waste heat recycling device
CN101196369A (en) Heat accumulation-exchange type heating stove and heating method thereof
CN103307889B (en) Gradient utilization method for waste heat of cupola furnace
CN102041337B (en) Multi-purpose system for high-temperature preheating of hot blast furnace combustion-supporting air
CN203373366U (en) Hot-blast stove system for achieving high blast temperature by only burning blast furnace
CN103088178B (en) Blast furnace hot-blast stove flue gas self-circulation combustion method and system
CN104101221B (en) The heating system of a kind of limit Mist heat recovering and scaling loss minimizing and method
CN201525853U (en) High-wind-temperature long-life type two-stage double-preheating device
CN203298623U (en) Cement clinker grate cold machine exhaust gas waste heat recycling and matching waste heat power generation system
CN103320561A (en) Hot-blast stove system for high air temperature by using pure blast furnace gas and method thereof
CN203980920U (en) The heating system of a kind of limit Mist heat recovering and scaling loss minimizing
CN201952444U (en) Multipurpose combustion air high-temperature preheating system for hot-blast air furnace
CN202993536U (en) Coal-fired hot blast furnace set with waste heat boiler
CN101928797A (en) High-blast-temperature energy-saving and emission-reducing combined type preheating system for blast furnace
CN101928796A (en) High wind temperature energy saving and emission reduction combined preheating method for blast furnace
CN203174129U (en) Flue gas self-circulation combustion system of blast furnace hot blast stove
CN103333976B (en) Flue gas waste heat utilization system and flue gas waste heat utilization method of hot blast furnace
CN201867081U (en) Waste heat utilization system for low-temperature smoke of heating furnace
CN202581247U (en) Waste heat utilization system for natural gas burner
CN203373367U (en) Smoke waste-heat utilization system of hot blast furnace
CN201785422U (en) High-air-temperature energy-saving emission-reduction combined preheating system of blast furnace
CN105972569B (en) Supplementary fired Waste Heat Boiler
CN204404817U (en) Fume afterheat resources shifting with utilize system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110831

Termination date: 20130113

CF01 Termination of patent right due to non-payment of annual fee