CN201950397U - Safe operation platform for welding door frame of wind turbine tower frame - Google Patents
Safe operation platform for welding door frame of wind turbine tower frame Download PDFInfo
- Publication number
- CN201950397U CN201950397U CN201120056770XU CN201120056770U CN201950397U CN 201950397 U CN201950397 U CN 201950397U CN 201120056770X U CN201120056770X U CN 201120056770XU CN 201120056770 U CN201120056770 U CN 201120056770U CN 201950397 U CN201950397 U CN 201950397U
- Authority
- CN
- China
- Prior art keywords
- platform
- welding
- safe operation
- wind turbine
- turbine tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Wind Motors (AREA)
Abstract
The utility model relates to a safe operation platform for welding the door frame of a wind turbine tower frame, which comprises a wind turbine tower barrel, and is characterized in that: a first platform and a second platform are arranged on two sides in the center of the door frame of the wind turbine tower barrel respectively and are connected with each other through a connecting plate; and at least one permanent magnet is arranged at the contact positions of the first platform and the second platform and the wind turbine tower barrel. The safe operation platform has the advantages that: the safety level during welding is improved, the life safety of welders and welding quality are ensured, the labor intensity of the welders is reduced, and production efficiency is improved.
Description
Technical field
The utility model relates to a kind of arc-shaped surface safe operation platform, relates in particular to a kind of security platform that is used for the welding of windmill tower frame doorframe.
Background technology
Wind resource is very abundant on the earth, and wind energy more and more is subject to people's attention as a kind of cleaning, non-pollution of renewable energy, thereby wind-power electricity generation becomes one of regenerative resource exploration project of countries in the world common concern.
The section diameter is general more than 4 meters at the bottom of the MW class Large-scale Wind Turbines pylon, national Specification: " all eminences that (containing 2m) might fall more than height of fall datum level 2m are carried out operation, all are called high-rise working." to stand on the cylindrical shell more than 4 meters the welding doorframe very dangerous for the welder; accidentally personnel are easy to fall from the cylinder of eminence; cause casualties; for the condition of work of improving the welder and guarantee welding quality, are necessary to design a kind of security platform that is used for the welding of windmill tower frame doorframe.
Summary of the invention
The utility model technical issues that need to address have provided a kind of safe operation platform that is used for the welding of windmill tower frame doorframe, are intended to solve the above problems.
In order to solve the problems of the technologies described above, the utility model is achieved through the following technical solutions:
The utility model comprises: wind energy conversion system tower tube; Doorframe central authorities both sides at described wind energy conversion system tower tube are settled first platform and second platform respectively; Described first platform and second platform join by a plate; Contact position at first platform and second platform and wind energy conversion system tower tube is settled at least one permanent magnet respectively.
Compared with prior art, the beneficial effects of the utility model are: both improved the safe class when welding, guaranteed welder's life security, guaranteed the quality of welding again, reduced welder's labour intensity, improved production efficiency.
Description of drawings
Fig. 1 is a front view of the present utility model.
Fig. 2 is a vertical view of the present utility model.
Fig. 3 is a side view of the present utility model.
The specific embodiment
Below in conjunction with the accompanying drawing and the specific embodiment the utility model is described in further detail:
By Fig. 1, Fig. 2, Fig. 3 as seen: the utility model comprises: wind energy conversion system tower tube 9; Doorframe central authorities both sides at described wind energy conversion system tower tube 9 are settled first platform 1 and second platform 2 respectively; Described first platform 1 and second platform 2 join by a plate 3; Settle at least one permanent magnet 5 at first platform 1 and second platform 2 respectively with the contact position of wind energy conversion system tower tube 9.
Described first platform 1 and second platform 2 are respectively a framework.
Screw with first platform 1 and second platform, 2 different distance is set respectively on described connecting plate 3, forms the width of integral platform in order to regulate first platform 1 and second platform 2.
Described permanent magnet 5 is placed on the adjustable plate 4; Described adjustable plate 4 is connected with wind energy conversion system tower tube 9.
The doorframe welding process is as follows:
1, at first polishing must be cleared up with scale removal in the weld metal zone, and rust staining, gas cutting slag, grease and other dirts also keep dry.
2, begin to require before the welding that doorframe and tower body are welded the abundant preheating of two sides and reach welding process requirement to guarantee preheat temperature.
3, the welding method of doorframe and tower body adopts manual electric arc welding or gas shielded arc welding; because doorframe and end section tower body thickness are thicker; welding procedure generally is multi-pass welding and connects, and behind the weld defect of one deck, descends the welding of one deck again before must repairing earlier since the 2nd layer.Require the complete penetration of weld seam, do not have leak weld, burn, defective such as crackle, slag inclusion and face of weld should be smooth, smooth, be shaped well.
4, the welding of doorframe must be in horizontal level, to help guaranteeing weldquality, improves speed of welding.
In sum, doorframe and tower body welding requirements height, workload is big, the time is long.The welder stands on the circular cylinder body for a long time, and more than 4 meters, potential safety hazard is very big again for diameter.
The structure of the utility model security platform:
1, security platform by about 2 platforms connect into an integral platform (as shown in Figure 3) by connecting plate and bolt 6, nut 7 and packing ring 8.
2, two platforms respectively have 4 apertures about, by the width of connecting plate 3 adjustable platform, to adapt to the width requirement of different door frames.
3, whole security platform is held on the cylindrical shell about doorframe by two permanent magnets, with fixing whole security platform above the pylon cylindrical shell.
4, because tower tube diameter has nothing in common with each other, and the short transverse of magnet 5 can be adjusted, it is the adjustment that realizes the magnet short transverse by the slotted hole in the adjustable plate that welds together with magnet.Thereby guarantee that magnet holds cylindrical shell.
Claims (4)
1. a safe operation platform that is used for the welding of windmill tower frame doorframe comprises: wind energy conversion system tower tube; It is characterized in that: the doorframe central authorities both sides at described wind energy conversion system tower tube are settled first platform and second platform respectively; Described first platform and second platform join by a plate; Contact position at first platform and second platform and wind energy conversion system tower tube is settled at least one permanent magnet respectively.
2. the safe operation platform that is used for the welding of windmill tower frame doorframe according to claim 1, it is characterized in that: described first platform and second platform are respectively a framework.
3. the safe operation platform that is used for the welding of windmill tower frame doorframe according to claim 1, it is characterized in that: the screw with first platform and the second platform different distance is set respectively on described connecting plate, forms the width of integral platform in order to regulate first platform and second platform.
4. the safe operation platform that is used for the welding of windmill tower frame doorframe according to claim 1, it is characterized in that: described permanent magnet is placed on the adjustable plate; Described adjustable plate is connected with wind energy conversion system tower tube.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201120056770XU CN201950397U (en) | 2011-03-04 | 2011-03-04 | Safe operation platform for welding door frame of wind turbine tower frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201120056770XU CN201950397U (en) | 2011-03-04 | 2011-03-04 | Safe operation platform for welding door frame of wind turbine tower frame |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201950397U true CN201950397U (en) | 2011-08-31 |
Family
ID=44494524
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201120056770XU Expired - Lifetime CN201950397U (en) | 2011-03-04 | 2011-03-04 | Safe operation platform for welding door frame of wind turbine tower frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201950397U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102653040A (en) * | 2011-03-04 | 2012-09-05 | 上海泰胜风能装备股份有限公司 | Safety operation platform for welding door frame of wind turbine tower |
CN108907577A (en) * | 2018-08-30 | 2018-11-30 | 湖南恒岳重钢钢结构工程有限公司 | It is a kind of for welding the operating platform of wind power tower door frame |
-
2011
- 2011-03-04 CN CN201120056770XU patent/CN201950397U/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102653040A (en) * | 2011-03-04 | 2012-09-05 | 上海泰胜风能装备股份有限公司 | Safety operation platform for welding door frame of wind turbine tower |
CN108907577A (en) * | 2018-08-30 | 2018-11-30 | 湖南恒岳重钢钢结构工程有限公司 | It is a kind of for welding the operating platform of wind power tower door frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104028878B (en) | A kind of assembling exempting from back chipping T-shaped penetration welding point and welding method | |
CN102865177B (en) | A kind of structure of knockdown impingement type hydraulic generator runner and manufacture method | |
CN104526282B (en) | Method for establishing large floating type wind power station tower drum | |
CN106112203B (en) | A kind of method of slab tubular structure longitudinal seam welding control crackle | |
CN201950397U (en) | Safe operation platform for welding door frame of wind turbine tower frame | |
CN201385181Y (en) | Fillet weld dedicated welding bracket for manufacturing wind generating set tower | |
CN102653040A (en) | Safety operation platform for welding door frame of wind turbine tower | |
CN102198553A (en) | Automatic bevel cutting machine | |
CN204751878U (en) | Hydroelectric set hydraulic turbine main shaft and runner hoist and mount specialized tool | |
CN209094820U (en) | A kind of offshore wind farm tubular pole girth joint General welding platform | |
CN202963886U (en) | Hydraulic inclinable idler wheel shelf for basic ring welding of wind power tower tube | |
CN202946323U (en) | Wind generating set tower cylinder platform connecting device | |
CN106271404A (en) | A kind of manufacture method of large-scale Water distribution circular pipe | |
CN113146109B (en) | Manufacturing method of eccentric jacket | |
CN206329446U (en) | A kind of guide flange structure | |
CN202284525U (en) | Tower platform mounting structure for wind generator | |
CN205464881U (en) | Wind power tower cylinder welding stent | |
CN204122911U (en) | Blower foundation ring lower flange combination angle seam welding device | |
CN209532398U (en) | A kind of A seating resistance spot weld anti-splashing device | |
CN202170848U (en) | Rear frame of wind power generation unit | |
CN203583472U (en) | Automatic anchor cable lowering equipment | |
CN201815823U (en) | Special butt positioning welding tool for wind power mainframe rotor lock | |
CN206605186U (en) | A kind of production fixture of generating set | |
CN213798180U (en) | Medium-deep layer interference-free geothermal well heat exchange tube installation device | |
CN204075583U (en) | Arc doorframe assembling device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20110831 |
|
CX01 | Expiry of patent term |