CN201918256U - Capacitor installation structure - Google Patents

Capacitor installation structure Download PDF

Info

Publication number
CN201918256U
CN201918256U CN2010206218820U CN201020621882U CN201918256U CN 201918256 U CN201918256 U CN 201918256U CN 2010206218820 U CN2010206218820 U CN 2010206218820U CN 201020621882 U CN201020621882 U CN 201020621882U CN 201918256 U CN201918256 U CN 201918256U
Authority
CN
China
Prior art keywords
installation
chute
capacitor
capacitors
mounting panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010206218820U
Other languages
Chinese (zh)
Inventor
赵永贵
陈伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Leshan Shengjia Electric Co., Ltd.
Original Assignee
LESHAN CHENGJIA ELECTRIC CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LESHAN CHENGJIA ELECTRIC CO Ltd filed Critical LESHAN CHENGJIA ELECTRIC CO Ltd
Priority to CN2010206218820U priority Critical patent/CN201918256U/en
Application granted granted Critical
Publication of CN201918256U publication Critical patent/CN201918256U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Thermistors And Varistors (AREA)

Abstract

The utility model discloses a capacitor installation structure which is simpler and more convenient to install, the installation structure comprises an installation chute provided with buckling edges at full length, and at least one installation plate which is matched with the installation chute and can slide along the installation chute; each installation plate is fixedly connected with at least two capacitors, the installation plate and the installation chute are correspondingly provided with fixing structures, the capacitors can be fixed on the installation plate firstly, and then the installation plate slides into and is fixed in the installation chute which can be fixed on a base body such as a cabinet and the like, thus reducing workload, being more convenient, being capable of effectively reducing damage to the capacitors during installation, protecting elements, causing equipment installation space to be more flexible on the premise of meeting the requirement of technical standard, saving the installation space, reducing the workload for overhauling and maintaining the capacitors, improving the working efficiency, and being especially suitable for installation of a plurality of groups of parallel capacitors.

Description

Capacitor mounting structure
Technical field
The utility model relates to a kind of capacitor mounting structure.
Background technology
The hot stove in ore deposit is a kind of typical highly energy-consuming equipment, and in electrical system, smelting transformer and short net all are inductive loads, and being in operation needs to consume a large amount of reactive powers, causes power factor generally on the low side.Need the reactive power consumption of the hot stove in ore deposit is compensated at this phenomenon, by the low voltage parallel capacitor phase splitting compensation to reach the purpose that improves power factor and system's active power utilance.Because when carrying out filtering compensation, the Capacity Ratio of compensation is bigger, need the capacitor of many groups in parallel.
Traditional capacitor mounting structure is: capacitor vertically is arranged in order on mounting panel, installation nut by fixed capacitor is connected to a group capacitor on the good mounting panel of power distribution cabinet internal fixation one by one, workload is big, and when fixed capacitor, because the cabinet inner space is limited, to the workman wiring capacitance device is installed and is brought very big trouble, and when installation and fixed capacitor, because the operating space is narrow and small, in installation process, easily damage capacitor, simultaneously, capacitor need strengthen the cabinet size for being installed, for entering to install in the cabinet, installation personnel provides the space, increased on-the-spot erection unit space, the burden that has increased the user has also limited the equipment installation, brings difficulty for daily capacitor Maintenance and Repair.
The utility model content
In order to overcome existing capacitor mounting structure the deficiency of inconvenience is installed, technical problem to be solved in the utility model provides the more easy capacitor mounting structure of a kind of installation.
The technical scheme that its technical problem that solves the utility model adopts is: capacitor mounting structure, comprise the installation chute, and with at least one that the chute coupling is installed can be along the mounting panel that chute slides is installed, be fixedly connected with at least two capacitors on each mounting panel, correspondence is provided with fixed structure on mounting panel and the installation chute.
Described installation chute is the elongated chute of buckleing the limit that is provided with.
Be fitted with at least two mounting panels in the described same installation chute.
Fixed structure on the described mounting panel is the fixing hole that is arranged on the mounting panel end, also is provided with corresponding installing hole on the described installation chute as fixed structure.
Be fixedly connected with three capacitors on described each mounting panel.
By being installed, nut is connected between described capacitor and the mounting panel.
The beneficial effects of the utility model are: earlier capacitor is fixed on the mounting panel; again mounting panel is slipped into and is fixed in the installation chute on the matrixes such as to be fixed in cabinet in advance; can effectively reduce the workload that the workman installs; and more convenient workman installs capacitor according to the capacitor standard is installed; effectively reduce owing to the infringement of installation process capacitor; protected element; and make installation space more flexible satisfying under the prerequisite of process specification requirements; saved installing space; reduce the on-the-spot workload that capacitor is overhauled and safeguards; increase work efficiency, especially be fit to the installation of many group shunt capacitances.
Description of drawings
Fig. 1 is a front view of the present utility model.
Fig. 2 is the left view of Fig. 1.
Fig. 3 is the front view of mounting panel in the utility model.
Fig. 4 is the vertical view of Fig. 3.
Fig. 5 is the left view of Fig. 3.
Fig. 6 is the front view that chute is installed in the utility model.
Fig. 7 is the left view of Fig. 6.
Be labeled as among the figure, the 1-capacitor, the 2-mounting panel, 3-installs chute, the 4-installing hole, the 5-fixing hole, 6-detains the limit, and 7-installs nut.
Embodiment
Below in conjunction with accompanying drawing the utility model is further specified.
As Fig. 1~shown in Figure 7, capacitor mounting structure of the present utility model comprises installs chute 3, and with at least one that chute 3 couplings are installed can be along the mounting panel 2 that chute 3 slides is installed, be fixedly connected with at least two capacitors 1 on each mounting panel 2, correspondence is provided with fixed structure on mounting panel 2 and the installation chute 3.In the above-mentioned mounting structure, because mounting panel 2 and and to install between the chute 3 be dismountable syndeton, after can earlier each capacitor 1 being connected with mounting panel 2, again mounting panel 2 is slipped into and install in the chute 3, convenient and labor-saving, utilize the described corresponding fixed structure connection plate that is provided with 2 then and chute 3 is installed, promptly realized the fixing of capacitor 1, can also effectively reduce because installation process to the infringement of capacitor, has been protected element; Have two capacitors 1 on the every mounting panel 2 at least, make the cabinet internal structure compact more, reduced cabinet overall dimension, can save the installation workload in cabinet again, very easy.
As shown in Figure 6 and Figure 7, the preferably elongated chute of buckleing limit 6 that is provided with of described installation chute 3, the position-limiting action for mounting panel 2 can be played in button limit 6, makes it fixing more reliable.
As shown in Figure 1, under situation, can be fitted with at least two mounting panels 2 in the described same installation chute 3 with button limit, each piece mounting panel 2 is arranged adjacent in the same installation chute 3, form each other spacing, need only be fixed in the mounting panel 2 at two ends after, can all mounting panels 2 are fixing.
As shown in Figure 1 and Figure 2, for the purpose of making things convenient for, the fixed structure on the described mounting panel 2 is the fixing hole 5 that is arranged on mounting panel 2 ends, also is provided with corresponding installing hole 4 on the described installation chute 3 as fixed structure.Can fix by nut.
As shown in Figure 2, consider that monolithic mounting panel 2 is unsuitable long so that installation is fixedly connected with three capacitors 1 on described each mounting panel 2.
As shown in Figure 1, still can be connected between described capacitor 1 and the mounting panel 2,, in addition, also can adopt connected modes such as welding so that overhaul by nut 7 is installed.

Claims (6)

1. capacitor mounting structure, it is characterized in that: comprise chute (3) is installed, and with at least one that chute (3) coupling is installed can be along the mounting panel (2) that chute (3) slides is installed, be fixedly connected with at least two capacitors (1) on each mounting panel (2), mounting panel (2) and installation chute (3) are gone up correspondence and are provided with fixed structure.
2. capacitor mounting structure as claimed in claim 1 is characterized in that: described installation chute (3) is the elongated chute of buckleing limit (6) that is provided with.
3. capacitor mounting structure as claimed in claim 2 is characterized in that: be fitted with at least two mounting panels (2) in the described same installation chute (3).
4. capacitor mounting structure as claimed in claim 1, it is characterized in that: the fixed structure on the described mounting panel (2) also is provided with corresponding installing hole (4) as fixed structure for being arranged on the fixing hole (5) of mounting panel (2) end on the described installation chute (3).
5. capacitor mounting structure as claimed in claim 1 is characterized in that: be fixedly connected with three capacitors (1) on described each mounting panel (2).
6. capacitor mounting structure as claimed in claim 1 is characterized in that: be connected by nut (7) is installed between described capacitor (1) and the mounting panel (2).
CN2010206218820U 2010-11-24 2010-11-24 Capacitor installation structure Expired - Lifetime CN201918256U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206218820U CN201918256U (en) 2010-11-24 2010-11-24 Capacitor installation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206218820U CN201918256U (en) 2010-11-24 2010-11-24 Capacitor installation structure

Publications (1)

Publication Number Publication Date
CN201918256U true CN201918256U (en) 2011-08-03

Family

ID=44418048

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206218820U Expired - Lifetime CN201918256U (en) 2010-11-24 2010-11-24 Capacitor installation structure

Country Status (1)

Country Link
CN (1) CN201918256U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102856071A (en) * 2012-08-29 2013-01-02 永济新时速电机电器有限责任公司 Mounting structure of large-power capacitor
CN104092103A (en) * 2014-07-30 2014-10-08 国家电网公司 Capacitor mounting structure for compensation cabinet
CN112803243A (en) * 2020-12-31 2021-05-14 宁波海融电器有限公司 Integrative dry-type power electronic capacitor of cylinder formula convenient to installation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102856071A (en) * 2012-08-29 2013-01-02 永济新时速电机电器有限责任公司 Mounting structure of large-power capacitor
CN102856071B (en) * 2012-08-29 2016-06-08 永济新时速电机电器有限责任公司 High power capacitor installs structure
CN104092103A (en) * 2014-07-30 2014-10-08 国家电网公司 Capacitor mounting structure for compensation cabinet
CN112803243A (en) * 2020-12-31 2021-05-14 宁波海融电器有限公司 Integrative dry-type power electronic capacitor of cylinder formula convenient to installation

Similar Documents

Publication Publication Date Title
CN201918256U (en) Capacitor installation structure
CN2847611Y (en) Drawer type reactive power automatic compensation power box
CN202076631U (en) Heavy current shunt bar
CN103630714A (en) Mobile electrical test power box
CN203351960U (en) A universal capacitor installing board
CN203617137U (en) A capacitor modularization fixing structure
CN203654534U (en) Photovoltaic module fixing device for curtain wall
CN201542027U (en) Solar portable computer table
CN202353222U (en) Low-voltage reactive compensation cabinet
CN206636801U (en) A kind of Sledge type immersible pump being moved easily
CN201725681U (en) General-purpose capacitor installing tray
CN204244059U (en) A kind of wind electric converter cabinet power cell fixture
CN203503988U (en) High and low voltage prefabricated transformer station lightning arrester mounting structure
CN217678625U (en) Vertical supporting equipment for mounting steel structure bridge
CN203351947U (en) Connecting piece
CN203135239U (en) Assembled power distribution cabinet side door panel
CN206250596U (en) One kind is based on distribution automation integral type ring main unit
CN201994577U (en) Fast connecting device for head cover and box body of outdoor box-type substation
CN202407719U (en) Solar computer desk
CN202084947U (en) Modular active harmonic control and dynamic reactive power compensation box
CN212114423U (en) Case for power compensation equipment
CN202395640U (en) Placement structure for main circuit device in current transformer device
CN201416761Y (en) Portable solar energy lamp device
CN202217923U (en) Quickly-assembled bus bridge
CN203351981U (en) A novel door crossbeam support

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Mounting structure of large-power capacitor

Effective date of registration: 20131224

Granted publication date: 20110803

Pledgee: Leshan City Commercial Bank Limited by Share Ltd Sales Department

Pledgor: Leshan Chengjia Electric Co., Ltd.

Registration number: 2013990001021

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 614000 No. 3, west section of Lego Road, Leshan hi tech Development Zone, Sichuan

Patentee after: Leshan Shengjia Electric Co., Ltd.

Address before: 614000 No. 3, west section of Lego Road, Leshan hi tech Development Zone, Sichuan

Patentee before: Leshan Chengjia Electric Co., Ltd.

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20160309

Granted publication date: 20110803

Pledgee: Leshan City Commercial Bank Limited by Share Ltd Sales Department

Pledgor: Leshan Shengjia Electric Co., Ltd.

Registration number: 2013990001021

PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Mounting structure of large-power capacitor

Effective date of registration: 20160309

Granted publication date: 20110803

Pledgee: Leshan City Commercial Bank Limited by Share Ltd Sales Department

Pledgor: Leshan Shengjia Electric Co., Ltd.

Registration number: 2016990000187

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
PM01 Change of the registration of the contract for pledge of patent right

Change date: 20160309

Registration number: 2013990001021

Pledgor after: Leshan Shengjia Electric Co., Ltd.

Pledgor before: Leshan Chengjia Electric Co., Ltd.

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20170718

Granted publication date: 20110803

Pledgee: Leshan City Commercial Bank Limited by Share Ltd Sales Department

Pledgor: Leshan Shengjia Electric Co., Ltd.

Registration number: 2016990000187

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Mounting structure of large-power capacitor

Effective date of registration: 20170801

Granted publication date: 20110803

Pledgee: Leshan City Commercial Bank Limited by Share Ltd Sales Department

Pledgor: Leshan Shengjia Electric Co., Ltd.

Registration number: 2017510000043

PE01 Entry into force of the registration of the contract for pledge of patent right
CX01 Expiry of patent term

Granted publication date: 20110803

CX01 Expiry of patent term