CN201875428U - Rapid gas-filling device of CNG (compressed natural gas) station with double gas sources for gas filling - Google Patents

Rapid gas-filling device of CNG (compressed natural gas) station with double gas sources for gas filling Download PDF

Info

Publication number
CN201875428U
CN201875428U CN2010206122870U CN201020612287U CN201875428U CN 201875428 U CN201875428 U CN 201875428U CN 2010206122870 U CN2010206122870 U CN 2010206122870U CN 201020612287 U CN201020612287 U CN 201020612287U CN 201875428 U CN201875428 U CN 201875428U
Authority
CN
China
Prior art keywords
gas
pressure gas
cng
gas storage
compressor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010206122870U
Other languages
Chinese (zh)
Inventor
吴宗荣
王义官
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZIGONG TONGDA MACHINERY MANUFACTURING Co Ltd
Original Assignee
ZIGONG TONGDA MACHINERY MANUFACTURING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZIGONG TONGDA MACHINERY MANUFACTURING Co Ltd filed Critical ZIGONG TONGDA MACHINERY MANUFACTURING Co Ltd
Priority to CN2010206122870U priority Critical patent/CN201875428U/en
Application granted granted Critical
Publication of CN201875428U publication Critical patent/CN201875428U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The utility model relates to a rapid gas-filling device of a CNG (compressed natural gas) station with double gas sources for gas filling, which is characterized by comprising a control cabinet, one end of a standard station compressor is connected with the control cabinet, the other end of the standard station compressor is connected with a program controlled plate, and a one-way valve is arranged between the standard station compressor and the program controlled plate; the other end of the program controlled plate is respectively connected with the inlet ends of a low-pressure gas storage unit, a medium-pressure gas storage unit and a high-pressure gas storage unit, and the outlet ends of the low-pressure gas storage unit, the medium-pressure gas storage unit and the high-pressure gas storage unit are respectively connected with the inlet end of a gas filling machine; and a natural gas trailer is connected with a gas discharging column, the gas discharging column is connected with a sub-station compressor, one end of the sub-station compressor is connected with the control cabinet, and the other end of the sub-station compressor is respectively connected with the inlet ends of the medium-pressure gas storage unit and the high-pressure gas storage unit and the inlet end of the gas filling machine. The CNG standard station and sub-stations are combined into a whole in a complementary way so that the gas discharging rate is variable while the gas filling rate is constant, and thus the investment and operating cost of CNG stations can be effectively reduced.

Description

The CNG of the dual gas supply air inlet quick aerator of standing
Technical field
The utility model is specifically related to a kind of CNG quick aerator of standing, particularly a kind of CNG of dual gas supply air inlet quick aerator of standing.
Background technique
The many modes with standard station, female station, substation in present CNG both domestic and external station are carried out separately, female station be build in from the city far away, from the nearer place of the rock gas person in charge, the standard station is to build the many cities of natural gas tube network arrangements in, and the substation is the city of building not or have less gas distributing system in.Because the self structure principle, the CNG station of prior art has the following disadvantages:
1. because the standard station separates construction with the substation, and floor space is very big, and system's input is many, cause waste and business efficiency low easily.
2. because standard station compressor mostly is the compressor of positive displacement, the air displacement of compressor is subjected to the influence of suction pressure bigger, when gas pressure in the pipeline is low, the CNG gas station does not satisfy the aerating demand, cause aerating speed slow, take place to such an extent as to add the situation of discontented gas, particularly comparatively obvious with gas peak or winter.
3. because the substation source of the gas is subjected to the influence of all many-sides such as female station equipment, transportation range, haulage device, and the substation source of the gas that has can't be guaranteed for a long time, makes the substation can't satisfy the demand of aerating, to such an extent as to can not aerating, thus cause the utilization efficiency of equipment low.
Summary of the invention
The utility model provides a kind of CNG of dual gas supply air inlet the quick aerator of standing, purpose is the technical problem that solves existing standard station and substation individualism, provide a kind of and promptly can satisfy the requirement of standard station, can satisfy simultaneously the device that the substation requires again, thereby effectively reduced the cost of investment of while construction standard station and substation, improved the utilization efficiency of equipment, improved the aerating speed at CNG station again greatly, guaranteed that CNG stands in the demand that all can fill it up with gas in any case for the CNG automobile.
The utility model technological scheme that adopts of dealing with problems is:
The CNG of the dual gas supply air inlet quick aerator of standing includes control cabinet, and standard station compressor one end links to each other with control cabinet, and the other end links to each other with program board, is provided with one-way valve between standard station compressor and program board.The other end of program board is connected with the entrance point of low pressure gas storage group, middle pressure gas storage group, high-pressure gas group respectively, and the outlet end of low pressure gas storage group, middle pressure gas storage group, high-pressure gas group links to each other with the entrance point of filling machine respectively.The rock gas trailer is connected with discharge column, and discharge column is connected with the substation compressor, and compressor one end in substation links to each other with control cabinet, and the other end is connected with middle pressure gas storage group, the entrance point of high-pressure gas group and the entrance point of filling machine respectively.
The beneficial effects of the utility model: CNG standard station and substation are united two into one, complement one another, when normal the use, use standard station compressor as far as possible, when gas pressure is not enough in gas peak or winter pipeline, replenish with the substation; Or normal when using the substation compressor, because trailer pressure is low or when not having source of the gas, replenish with the standard station; Standard station and substation compressor are worked simultaneously when the aerating peak, thereby satisfy the quick aerating of CNG gas station, accomplish that promptly air displacement is variable when air inlet is constant; Thereby effectively reduce the investment and the operating cost at CNG station.
Description of drawings
Fig. 1 is a structural representation of the present utility model
Embodiment
The CNG of the dual gas supply air inlet as shown in fig. 1 quick aerator of standing includes control cabinet 9, and standard station compressor 1 one ends link to each other with control cabinet 9, and the other end links to each other with program board 3, is provided with one-way valve 2 between standard station compressor 1 and program board 3.The other end of program board 3 is connected with the entrance point of low pressure gas storage group 4, middle pressure gas storage group 5, high-pressure gas group 6 respectively, and the outlet end of low pressure gas storage group 4, middle pressure gas storage group 5, high-pressure gas group 6 links to each other with the entrance point of filling machine 7 respectively.Rock gas trailer 10 is connected with discharge column 11, and discharge column 11 is connected with substation compressor 12, and compressor 12 1 ends in substation link to each other with control cabinet 9, and the other end is connected with the entrance point of middle pressure gas storage group 5, high-pressure gas group 6 and the entrance point of filling machine 7 respectively.
Working principle: the quick aerator technological process of dual gas supply air inlet is to improve on the basis of CNG standard station and substation aerating technological process, form through optimal design, the corresponding valve of increase with a cover CNG standard station compressor and a cover substation compressor assembly, two cover systems promptly can be distinguished independent operating, can move simultaneously again, thereby increased the tolerance that adds at whole C NG station, have more rock gas to join in the CNG automobile in the unit time, concrete workflow is:
The A:CNG standard station flow process that works alone: from the rock gas → standard station compressor 1 supercharging compression → one-way valve 2 → program board 3 of pipeline → minute be clipped to high pressure air storage group 6, middle pressure air storage group 5, low pressure air storage group 4 → filling machine 7 → CNG automobile 8, the control of whole controlled process system cabinet 9.
The B:CNG substation flow process that works alone: rock gas trailer 10 → discharge column 11 → substation compressor 12 superchargings compression → minute be clipped to high pressure air storage group 6, middle pressure air storage group 5 → filling machine 7 → CNG automobile 8, the control of whole controlled process system cabinet 9.
C: the dual gas supply air inlet is workflow simultaneously:
From the rock gas of pipeline → standard station compressor boost compression 1 → one-way valve 2 → program board 3 → minute be clipped to high-pressure gas group 6, middle pressure gas storage group 5, low pressure air storage group 4.
Rock gas trailer 10 → discharge column 11 → substation compressor boost compression 12 when work is carried out at CNG standard station → minute be clipped to high-pressure gas group 6, middle pressure gas storage group 5.
Above-mentioned CNG standard station compressor and substation compressor enter into natural gas → filling machine 7 → CNG automobile 8 that high-pressure gas group 6, pressure gas storage group 5, low pressure air storage group 4 pool together respectively; The control of whole controlled process system cabinet 9.
CNG standard station and substation are united two into one, complement one another, when normal the use, use standard station compressor as far as possible, when gas pressure is not enough in gas peak or winter pipeline, replenish with the substation; Or normal when using the substation compressor, because trailer pressure is low or when not having source of the gas, replenish with the standard station; Standard station and substation compressor are worked simultaneously when the aerating peak, thereby satisfy the quick aerating of CNG gas station, accomplish that promptly air displacement is variable when air inlet is constant; Thereby effectively reduce the investment and the operating cost at CNG station.

Claims (1)

1. the CNG of the dual gas supply air inlet quick aerator of standing, it is characterized in that: include control cabinet, standard station compressor one end links to each other with control cabinet, and the other end links to each other with program board, is provided with one-way valve between standard station compressor and program board; The other end of program board is connected with the entrance point of low pressure gas storage group, middle pressure gas storage group, high-pressure gas group respectively, and the outlet end of low pressure gas storage group, middle pressure gas storage group, high-pressure gas group links to each other with the entrance point of filling machine respectively; The rock gas trailer is connected with discharge column, and discharge column is connected with the substation compressor, and compressor one end in substation links to each other with control cabinet, and the other end is connected with middle pressure gas storage group, the entrance point of high-pressure gas group and the entrance point of filling machine respectively.
CN2010206122870U 2010-11-18 2010-11-18 Rapid gas-filling device of CNG (compressed natural gas) station with double gas sources for gas filling Expired - Fee Related CN201875428U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206122870U CN201875428U (en) 2010-11-18 2010-11-18 Rapid gas-filling device of CNG (compressed natural gas) station with double gas sources for gas filling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206122870U CN201875428U (en) 2010-11-18 2010-11-18 Rapid gas-filling device of CNG (compressed natural gas) station with double gas sources for gas filling

Publications (1)

Publication Number Publication Date
CN201875428U true CN201875428U (en) 2011-06-22

Family

ID=44163345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206122870U Expired - Fee Related CN201875428U (en) 2010-11-18 2010-11-18 Rapid gas-filling device of CNG (compressed natural gas) station with double gas sources for gas filling

Country Status (1)

Country Link
CN (1) CN201875428U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102330885A (en) * 2011-08-05 2012-01-25 山西高碳能源低碳化利用研究设计院有限公司 Automatic control method of device in hydrogen-natural gas filling station
CN102650373A (en) * 2012-06-11 2012-08-29 成都华气厚普机电设备股份有限公司 L-CNG (Liquid-Compressed Natural Gas) skid-mounted device without energy consumption
CN103256477A (en) * 2013-04-22 2013-08-21 张志卓 Method for filling prying vehicles by three-level pressure of natural gas primary stations
CN103277664A (en) * 2013-06-17 2013-09-04 贵州大学 CNG (compressed natural gas) and CNG-COG (coke oven gas) refilling method and device for
CN105156879A (en) * 2015-07-29 2015-12-16 定远县瑞安天然气技术服务有限公司 Method for rebuilding compressed natural gas (CNG) secondary gas filling station into CNG standard gas filling station
CN106439482A (en) * 2016-09-14 2017-02-22 天津华海清科机电科技有限公司 Gas circuit pressure response system

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102330885A (en) * 2011-08-05 2012-01-25 山西高碳能源低碳化利用研究设计院有限公司 Automatic control method of device in hydrogen-natural gas filling station
CN102650373A (en) * 2012-06-11 2012-08-29 成都华气厚普机电设备股份有限公司 L-CNG (Liquid-Compressed Natural Gas) skid-mounted device without energy consumption
CN103256477A (en) * 2013-04-22 2013-08-21 张志卓 Method for filling prying vehicles by three-level pressure of natural gas primary stations
CN103256477B (en) * 2013-04-22 2015-11-04 张志卓 Rock gas mother station three stage pressure fills the method for sled car
CN103277664A (en) * 2013-06-17 2013-09-04 贵州大学 CNG (compressed natural gas) and CNG-COG (coke oven gas) refilling method and device for
CN105156879A (en) * 2015-07-29 2015-12-16 定远县瑞安天然气技术服务有限公司 Method for rebuilding compressed natural gas (CNG) secondary gas filling station into CNG standard gas filling station
CN106439482A (en) * 2016-09-14 2017-02-22 天津华海清科机电科技有限公司 Gas circuit pressure response system
CN106439482B (en) * 2016-09-14 2019-10-25 天津华海清科机电科技有限公司 Airline pressure response system

Similar Documents

Publication Publication Date Title
CN201875428U (en) Rapid gas-filling device of CNG (compressed natural gas) station with double gas sources for gas filling
CN201757268U (en) CNG station quick gas filling device
CN105156892A (en) Oxygen partial pressure supply system
CN202017666U (en) Gas supercharging device
CN203097944U (en) Emergency power supply system for coal mining equipment
CN102913753B (en) Storage and gasification project output system of LNG (Liquefied Natural Gas) receiving terminal as well as method
CN203962350U (en) Associating compressor for natural gas
CN202273831U (en) Efficient energy-saving compressed air supercharging device
CN206018260U (en) A kind of charging device of gases at high pressure
CN202673875U (en) Ultrahigh pressure booster device
CN204164652U (en) A kind of LCNG gas station auxiliary gas feeder and the gas station comprising it
CN202868303U (en) Storage and gasification engineering output system of liquefied natural gas (LNG) accepting station
CN203220512U (en) Oxygen pressurization system of medical oxygen supply center
CN102102384A (en) Steady flow compensator
CN2863574Y (en) Fast-assembling type aerating sub-station device without compressor
CN202596690U (en) Pressurized water injection device
CN203963487U (en) Combined type Natural Gas Refueling System
CN203656578U (en) Wide-gas inflow constant-flow CNG compression plant
CN202252843U (en) Efficient combustible gas low-pressure supercharging conveying device
CN105484754A (en) Module type shield foaming system
CN206134828U (en) Fuel cell can fill dress formula air feed system of converging
CN101644382A (en) Civil method of natural gas
CN214968188U (en) Low-pressure oxygen cabin system adopting centralized oxygen supply
CN102691335A (en) Parallel water pump pipe cooling system
CN210831426U (en) System for conveying gas-liquid mixture of natural gas well

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110622

Termination date: 20151118