CN201826539U CN2010202344152U CN201020234415U CN201826539U CN 201826539 U CN201826539 U CN 201826539U CN 2010202344152 U CN2010202344152 U CN 2010202344152U CN 201020234415 U CN201020234415 U CN 201020234415U CN 201826539 U CN201826539 U CN 201826539U
Authority
CN
China
Prior art keywords
support frame
bracing frame
construction
square steel
steel bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202344152U
Other languages
Chinese (zh)
Inventor
闫亦文
李宏亮
巩震
涂建永
李俊杰
冯志会
王旭生
赵剑
严福全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd
Original Assignee
Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd filed Critical Fourth Construction Co Ltd of China Construction Seventh Engineering Co Ltd
Priority to CN2010202344152U priority Critical patent/CN201826539U/en
Application granted granted Critical
Publication of CN201826539U publication Critical patent/CN201826539U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model discloses a reusable support frame for steel bar construction, which belongs to the technical field of building construction. The support frame comprises a rectangular square bar support frame; and support legs are arranged at the square bar cross-connection points at the lower part of the square bar support frame. The support frame provided by the utility model has the benefits as follows: the structure is simple, the operation is convenient, and the support height is easy to adjust; the quality problem of large deviation in the thickness of the negative moment reinforcement protecting layer of a cast-in-place concrete floor slab is solved, so that the construction quality of the cast-in-place concrete floor slab is improved; and meanwhile, a large quantity of steel bar split heads are saved, engineering cost is reduced, and construction efficiency is improved.

Description

Reusable reinforcement construction bracing frame
Affiliated technical field
The utility model relates to a kind of reusable reinforcement construction bracing frame, belongs to technical field of building construction.
Background technology
At present, the reinforced bar support system of the structural slab of existing building mainly adopts dual mode.The first, on-the-spot reinforced bar support stool with the reinforcement fabrication different size, the reinforced bar support stool can only disposablely use, and wastes a large amount of artificial and reinforcing bar materials, and the support stool quality precision that different workmans make is wayward.The second, adopt the plastic support split heads, this not environmental protection of plastic support split heads product, plastics split heads intensity can not satisfy construction requirement fully in addition, and the plastic support split heads can not be played a supporting role after damaging, and influences workmanship.
The utility model content
For the unsettled deficiency of waste of material, quality that overcomes existing building operations split heads, the utility model provides a kind of reusable reinforcement construction bracing frame.
The technical scheme that its technical problem that solves the utility model adopts is:
Reusable reinforcement construction bracing frame comprises the square steel bracing frame of rectangle, and square steel interface point place is provided with supporting leg in square steel bracing frame bottom; The square steel bracing frame is the combination of 1-4 rectangle, adopts 15mm * 15mm square steel to make.
The beneficial effects of the utility model are that simple in structure, easy to operate, bearing height is adjusted easily; Having solved influences the big quality difficult problem of cast-in-place concrete floor negative tendon protective layer thickness deviation, thereby has improved the construction quality of cast-in-place concrete floor; Save a large amount of reinforcing bar stirrups simultaneously, reduced engineering cost, improved efficiency of construction.
Description of drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is that the utility model is implemented schematic diagram;
Component and numbering among the figure:
1-square steel bracing frame; The 2-supporting leg; The 3-top mat; 4-lower floor steel mesh reinforcement.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further specified.
As shown in Figure 1, reusable reinforcement construction bracing frame comprises the square steel bracing frame 1 of rectangle, square steel bracing frame 1 bottom the welding of square steel interface point place be provided with supporting leg 2.Square steel bracing frame 1 is the combination of 1-4 rectangle, adopts the square steel of 15mm * 15mm to make.
The square steel bracing frame 1 of present embodiment is the combination of 3 rectangles, and its length of side is provided with length by the negative muscle of plate and determines; Supporting leg 2 length are the appropriate length that go out according to the concrete floor THICKNESS CALCULATION, and supporting leg 2 is Φ 12mm or Φ 16mm round steel.
As shown in Figure 2, before concreting, reusable reinforcement construction bracing frame is placed on the template, wherein supporting leg 2 is supported on the template; The square steel bracing frame 1 that sets in advance is close to the upper surface of the negative muscle of plate of top mat 3, and negative muscle of plate and 1 colligation of square steel bracing frame is firm, and lower floor's steel mesh reinforcement 4 is below top mat 3.
After this bracing frame laying colligation is finished, carry out concreting, the upper surface of the upper surface of concreting and square steel bracing frame 1 is same plane; Remove this bracing frame before the initial set, the concrete surface usefulness mortar that will remove then behind this bracing frame is floating.
Adopt this new job practices, fixed the position of the negative muscle of cast-in-place concrete floor effectively, this has just solved from root influences the big quality difficult problem of cast-in-place concrete floor negative tendon protective layer thickness deviation, thereby has improved the construction quality of cast-in-place concrete floor; Save a large amount of reinforcing bar stirrups simultaneously, brought significantly economic benefit, satisfied the construction needs of all kinds of concrete structure plates.

Claims (3)

1. a reusable reinforcement construction bracing frame is characterized in that, comprises the square steel bracing frame (1) of rectangle, is provided with supporting leg (2) at the square steel interface point place of square steel bracing frame (1) bottom.
2. reusable reinforcement construction bracing frame according to claim 1 is characterized in that described square steel bracing frame (1) is the combination of 1-4 rectangle, and described square steel bracing frame (1) is made for the square steel of 15mm * 15mm.
3. reusable reinforcement construction bracing frame according to claim 1 is characterized in that, described supporting leg (2) is Φ 12mm or Φ 16mm round steel.
CN2010202344152U 2010-06-23 2010-06-23 Reusable support frame for steel bar construction Expired - Fee Related CN201826539U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202344152U CN201826539U (en) 2010-06-23 2010-06-23 Reusable support frame for steel bar construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202344152U CN201826539U (en) 2010-06-23 2010-06-23 Reusable support frame for steel bar construction

Publications (1)

Publication Number Publication Date
CN201826539U true CN201826539U (en) 2011-05-11

Family

ID=43965085

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202344152U Expired - Fee Related CN201826539U (en) 2010-06-23 2010-06-23 Reusable support frame for steel bar construction

Country Status (1)

Country Link
CN (1) CN201826539U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104453247A (en) * 2014-12-26 2015-03-25 中建八局第四建设有限公司 Floor slab negative reinforcement support
CN104818853A (en) * 2014-08-26 2015-08-05 中国建筑第四工程局有限公司 Method and tool for retracement of floor slab hogging moment steel bars
CN107254940A (en) * 2017-07-07 2017-10-17 上海宝冶集团有限公司 A kind of reusable split heads and casting method for casting concrete

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104818853A (en) * 2014-08-26 2015-08-05 中国建筑第四工程局有限公司 Method and tool for retracement of floor slab hogging moment steel bars
CN104453247A (en) * 2014-12-26 2015-03-25 中建八局第四建设有限公司 Floor slab negative reinforcement support
CN107254940A (en) * 2017-07-07 2017-10-17 上海宝冶集团有限公司 A kind of reusable split heads and casting method for casting concrete

Similar Documents

Publication Publication Date Title
CN104631706B (en) One kind exempts from form removal concrete column and its construction method
CN203452378U (en) Post-cast strip locating structure
CN201826539U (en) Reusable support frame for steel bar construction
CN201106282Y (en) Post-irrigating band, construction joint plate side module
CN202730579U (en) Recyclable prefabricated concrete block for hardening construction plant
CN104060760A (en) Layered construction method for oversized concrete beam of structural transfer floor of high-rise building
CN205276628U (en) Combination system of superimposed sheet bottom plate truss
CN102677895A (en) Suspended formwork pouring method for concrete foundation steps
CN201531035U (en) Foundation slab late poured band and construction joint steel wire mesh isolating device
CN201649639U (en) Supporting system of post-pouring belt template on foundation soleplate
CN104295089A (en) Support system of cast-in-place concrete GBF honeycomb core dense-rib floor system
CN202064636U (en) Closed stair formwork erecting device
CN204983699U (en) Bolt locator
CN204687050U (en) A kind of mould of precast concrete rectangular beam
CN204551172U (en) A kind of prefabricated road surface of assembled steel reinforced concrete hollow
CN201027361Y (en) Superposed bidirectional pre-stress hollow slab
CN206267425U (en) A kind of device for being used in turn steel bar horse-shaped bench
CN202990415U (en) Nuclear power plant four tubular post early detaching supporting device
CN205421644U (en) Building floor prefab that 3D printed
CN204040457U (en) Wood frame plastic formwork system
CN205259555U (en) Device of adjustment reinforcing bar net piece height
CN201865250U (en) Square tube barricades support
CN203834825U (en) Connection structure of prefabricated stair of overlapped wallboard room
CN206769245U (en) A kind of combination construction component for strengthening Sloping roof construction quality
CN202530585U (en) Post-cast strip protecting construction for structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110511

Termination date: 20110623