CN201770945U - Synchronous cradle moving device for continuous rigid frame bridge construction cradle - Google Patents

Synchronous cradle moving device for continuous rigid frame bridge construction cradle Download PDF

Info

Publication number
CN201770945U
CN201770945U CN2010202797881U CN201020279788U CN201770945U CN 201770945 U CN201770945 U CN 201770945U CN 2010202797881 U CN2010202797881 U CN 2010202797881U CN 201020279788 U CN201020279788 U CN 201020279788U CN 201770945 U CN201770945 U CN 201770945U
Authority
CN
China
Prior art keywords
girder
outer sliding
sliding beam
hanging basket
outer slide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010202797881U
Other languages
Chinese (zh)
Inventor
吴彪
余甦
吴旭东
官辉国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Changda Highway Engineering Co Ltd
Original Assignee
Guangdong Changda Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Changda Highway Engineering Co Ltd filed Critical Guangdong Changda Highway Engineering Co Ltd
Priority to CN2010202797881U priority Critical patent/CN201770945U/en
Application granted granted Critical
Publication of CN201770945U publication Critical patent/CN201770945U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a synchronous cradle moving device for a continuous rigid frame bridge construction cradle, which comprises a main truss, a cross girder arranged at the front end of the main truss, a longitudinal moving track fixed on a bridge deck, an outer slide girder, a cradle body and an outer slide girder frame anchored on concrete. The front end of the outer slide girder is hinged with a boom of the cross girder while the other end is supported on rollers of the outer slide girder frame, turning pulleys are respectively mounted at the rear end of the outer slide girder, a hinge position between the outer slide girder and the boom and the cross girder, an embedding ring is disposed on a cast girder section, a steel wire rope is fixed in the middle of the bottom of the outer slide beam frame, then is wound through the turning pulley at the tail of the outer slide frame, forwards wound through the turning pulley at the front end of the outer slide girder, continuously upwards wound through the turning pulley on the cross girder and finally fixed on an embedding ring of former cast box girder concrete through a chain block. The front end and the rear end of the cradle body can be moved synchronously by the synchronous cradle moving device, and the synchronous cradle moving device is safe in operation.

Description

The continuous rigid frame bridge construction Hanging Basket move basket device synchronously
Technical field
The utility model relates to the construction equipment of rigid frame bridge, and especially a kind of continuous rigid frame bridge construction is hung blue synchronous shifter.
Background technology
Continuous rigid frame bridge is to stride at present one of the most frequently used bridge type of footpath concrete-bridge greatly, has that place compliance is strong, span ability is big, the advantage that the later maintenance expense is low under the normal condition and being widely used.
At present, existing bridge construction Hanging Basket, especially continuous rigid frame bridge construction Hanging Basket, it mainly comprises bridge floor main truss, crossbeam, sliding beam, vertical shift track, sliding roof beam structure of sliding beam and Hanging Basket main body outward outward, the front end of outer sliding beam and the suspension rod of crossbeam are hinged, and the other end is undertaken on the roller of the sliding roof beam structure of outer sliding beam.The front end of Hanging Basket main body is connected with the crossbeam suspension rod in addition, and the rear end is connected with the rear suspension bar that is suspended in outer sliding beam.When moving basket, in mobile bridge floor main truss, need artificial under bridge floor, walk around outer sliding beam rear end angle pulley on the Hanging Basket by pulling and be fixed on outside wire rope below the sliding beam suspension wheel suspension rod, promote the purpose that outer sliding beam advances to reach, this kind moves the mode of outer sliding beam, be difficult to outer sliding beam of control and bridge floor main truss advanced in unison, cause the difficulty of moving basket, simultaneously manually at the following operational danger height of bridge floor, outside modular system is difficult to and whole Hanging Basket advanced in unison, cause and move the basket difficulty, falling accident often takes place simultaneously, and is dangerous high.
The utility model content
The purpose of this utility model be to provide a kind of can be with the continuous rigid frame bridge construction Hanging Basket of the front-end and back-end of moved further Hanging Basket main body, handling safety move basket device synchronously.
For achieving the above object, the technical scheme that the utility model adopted is: a kind of continuous rigid frame bridge construction Hanging Basket move basket device synchronously, comprise main couple, the crossbeam of main couple front end, be fixed on the vertical shift track of bridge floor, outer sliding beam, Hanging Basket main body and be anchored at the sliding roof beam structure of concrete outer sliding beam, main couple is fixed on the vertical shift track, the front end of outer sliding beam and the suspension rod of crossbeam are hinged, the other end is undertaken on the roller of the sliding roof beam structure of outer sliding beam, the front end of Hanging Basket main body and the lower end of suspension rod are hinged, the rear end of Hanging Basket main body is suspended on the outer sliding beam by rear suspension bar, slide the rear end of beam outside, on outer sliding beam and suspension rod hinged place and the crossbeam angle pulley is installed all, be provided with pre-buried ring in casting beams section, wire rope is fixed on centre position, outer sliding beam suspension bottom, walk around the angle pulley of outer sliding beam rear part then backward, walk around the angle pulley of outer sliding beam front end more forward, continue upwards to walk around the angle pulley on the crossbeam, finally be fixed on the concrete embedded ring of case beam of having built the last period.
The angle pulley of described outer sliding beam rear end has two, and they are on same vertical curve.
Be equipped with length-adjustment holes on described suspension rod and the rear suspension bar, can regulate the length of suspension rod, rear suspension bar, to adapt to building without thickness case beam.
The bottom of described main couple is provided with the mobile wheel that matches with the vertical shift track.
Described main couple bottom is provided with and can promotes the hydraulic jack that main couple vertically moves.
After the utility model adopts said structure, by the rear end of sliding beam outside, on sliding beam and suspension rod hinged place and the crossbeam angle pulley is set outward, be provided with pre-buried ring in casting beams section, wire rope is fixed on centre position, outer sliding beam suspension bottom, walk around the angle pulley of outer sliding beam rear part then backward, walk around the angle pulley of outer sliding beam front end more forward, the angle pulley before continuing upwards to walk around on the top rail finally is fixed on the concrete embedded ring of case beam of having built the last period; Therefore, during the reach main couple, wire rope around the crossbeam angle pulley also moves forward, then wire rope produces an outer sliding beam suspension wheel suspension rod of back pull pulling simultaneously and makes it to keep plumbness, prevent that it from moving forward with Hanging Basket external side of main body mould and lose outer sliding beam suspension wheel suspension rod, provide forward power by the externally sliding beam of this wire rope simultaneously, reach and make outer sliding beam and main couple advanced in unison, the front-end and back-end that make the Hanging Basket main body have avoided suspension rod to lose with the moved further purpose; Avoid the artificial beam of below bridge floor, sliding outside the promotion to advance, improved the safety that moves basket greatly.
Description of drawings
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail:
Fig. 1 is the utility model structure chart.
Among the figure: 1 main couple, 101 move wheel, 102 hydraulic jack, 2 crossbeams, 21 tips, 3 vertical shift tracks, 4 outer sliding beams, 5 Hanging Basket main bodys, 6 outer sliding beam suspension wheel suspension rods, 601 suspension wheels, 7 suspension rods, 8 rear suspension bars, 9,10,11 angle pulleies, 12 pre-buried rings, 13 wire rope, 14 Chain blocks, 15 length-adjustment holes.
The specific embodiment
Shown in Figure 1, continuous rigid frame bridge construction Hanging Basket of the present utility model move basket device synchronously, comprise main couple 1, the crossbeam 2 of main couple 1 front end, be fixed on the vertical shift track 3 of bridge floor, outer sliding beam 4, Hanging Basket main body 5 and be anchored at the sliding roof beam structure 6 of concrete outer sliding outer sliding beam, main couple 1 is fixed on the vertical shift track 3, the front end of outer sliding beam 4 and the suspension rod 7 of crossbeam 2 are hinged, the other end is undertaken on the roller 601 of the sliding roof beam structure 6 of outer sliding beam, the front end of Hanging Basket main body 5 and suspension rod 7) lower end is hinged, the rear end of Hanging Basket main body 5 is suspended on the outer sliding beam 4 by rear suspension bar 8, in the technical program, the rear end of sliding beam 4 is equipped with angle pulley 9 outside, sliding outside beam 4 is equipped with angle pulley 10 with suspension rod 7 hinged places, angle pulley 11 is installed on the crossbeam 2, be fixed with pre-buried ring 12 in casting beams section, wire rope 13 is fixed on centre position, outer sliding beam sliding roof beam structure bottom, walk around the angle pulley 9 of outer sliding beam 4 afterbodys then backward, walk around the angle pulley 10 of outer sliding beam 4 front ends more forward, continue upwards to walk around the angle pulley 11 on the crossbeam 2, finally be fixed on the concrete embedded ring 12 of the case beam of having built the last period.The angle pulley 9 of described outer sliding beam 4 rear ends is two, and they are located on the same vertical curve.On suspension rod 7 and rear suspension bar 8, be equipped with length-adjustment holes 14, can regulate the length of suspension rod, rear suspension bar, to adapt to building without thickness case beam.The bottom of described main couple 1 is provided with the mobile wheel 101 that matches with vertical shift track 3.Be provided with in main couple 1 bottom and can promote the hydraulic jack 102 that main couple 1 vertically moves.During mobile Hanging Basket, unclamp the set bolt of main couple 1, the main couple reach, wire rope 13 around crossbeam 2 angle pulleies 11 also moves forward simultaneously, then wire rope 13 produces an outer sliding beam suspension wheel suspension rod 6 of back pull pulling simultaneously and makes it to keep plumbness, prevent that its outer side form with Hanging Basket main body 5 from moving forward and lose outer sliding beam suspension wheel suspension rod 6, provide forward power by this wire rope 13 externally sliding beams 4 simultaneously, reach and make outer sliding beam 4 and main couple 1 advanced in unison, the front-end and back-end that make Hanging Basket main body 1 have avoided suspension rod 7 to lose with the moved further purpose; Avoid the artificial danger that sliding beam 4 advances outside the promotion below bridge floor, improved the safety that moves basket greatly.

Claims (5)

1. a continuous rigid frame bridge construction Hanging Basket moves basket device synchronously, comprise main couple (1), the crossbeam (2) of main couple (1) front end, be fixed on the vertical shift track (3) of bridge floor, outer sliding beam (4), Hanging Basket main body (5) and be anchored at the sliding roof beam structure (6) of concrete outer sliding beam, main couple (1) is fixed on the vertical shift track (3), the front end of outer sliding beam (4) and the suspension rod (7) of crossbeam (2) are hinged, the other end is undertaken on the roller (601) of the outer sliding sliding roof beam structure of beam (6), the lower end of the front end of Hanging Basket main body (5) and suspension rod (7) is hinged, the rear end of Hanging Basket main body (5) is suspended on the outer sliding beam (4) by rear suspension bar (8), it is characterized in that: the rear end of sliding beam (4) outside, on outer sliding beam (4) and suspension rod (7) hinged place and the crossbeam (2) angle pulley (9 is installed, 10,11), be provided with pre-buried ring (12) in casting beams section, wire rope (13) is fixed on centre position, outer sliding beam suspension (6) bottom, walk around the angle pulley (9) of outer sliding beam (4) afterbody then backward, walk around the angle pulley (10) of outer sliding beam (4) front end more forward, continue upwards to walk around the angle pulley (11) on the crossbeam (2), finally be fixed on the concrete embedded ring of case beam (12) of having built the last period by Chain block (14).
2. continuous rigid frame bridge construction Hanging Basket according to claim 1 move basket device synchronously, it is characterized in that: the angle pulley (9) of described outer sliding beam (4) rear end has two, and they are on same vertical curve.
3. continuous rigid frame bridge construction Hanging Basket according to claim 1 move basket device synchronously, it is characterized in that: be equipped with length-adjustment holes (15) on described suspension rod (7) and the rear suspension bar (8).
4. continuous rigid frame bridge construction Hanging Basket according to claim 1 move basket device synchronously, it is characterized in that: the bottom of described main couple (1) is provided with the mobile wheel (101) that matches with vertical shift track (3).
5. continuous rigid frame bridge construction Hanging Basket according to claim 1 move basket device synchronously, it is characterized in that: described main couple (1) bottom is provided with and can promotes the hydraulic jack (102) that main couple (1) vertically moves.
CN2010202797881U 2010-08-02 2010-08-02 Synchronous cradle moving device for continuous rigid frame bridge construction cradle Expired - Lifetime CN201770945U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202797881U CN201770945U (en) 2010-08-02 2010-08-02 Synchronous cradle moving device for continuous rigid frame bridge construction cradle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202797881U CN201770945U (en) 2010-08-02 2010-08-02 Synchronous cradle moving device for continuous rigid frame bridge construction cradle

Publications (1)

Publication Number Publication Date
CN201770945U true CN201770945U (en) 2011-03-23

Family

ID=43750788

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202797881U Expired - Lifetime CN201770945U (en) 2010-08-02 2010-08-02 Synchronous cradle moving device for continuous rigid frame bridge construction cradle

Country Status (1)

Country Link
CN (1) CN201770945U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102174795A (en) * 2011-03-28 2011-09-07 中铁一局集团有限公司 Reversible suspended basket wheel type travelling system and method
CN102220740A (en) * 2011-04-13 2011-10-19 湖南中铁五新钢模有限责任公司 Cantilever-concreting construction hanging basket for four-lane and wide-width continuous beam of high-speed rail
CN102251480A (en) * 2011-04-29 2011-11-23 湖南中铁五新钢模有限责任公司 Small pier top construction triangular hanging basket
CN102345273A (en) * 2010-08-02 2012-02-08 广东省长大公路工程有限公司 Synchronous cradle moving device for continuous rigid frame bridge construction cradle
CN104278643A (en) * 2014-10-17 2015-01-14 中铁建大桥工程局集团第五工程有限公司 Continuous rigid frame box girder construction technology applied to bridge project
CN109468955A (en) * 2018-11-12 2019-03-15 湖南金海钢结构有限公司 A kind of large size truss dismounting tooling

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102345273A (en) * 2010-08-02 2012-02-08 广东省长大公路工程有限公司 Synchronous cradle moving device for continuous rigid frame bridge construction cradle
CN102345273B (en) * 2010-08-02 2015-04-15 广东省长大公路工程有限公司 Synchronous cradle moving device for continuous rigid frame bridge construction cradle
CN102174795A (en) * 2011-03-28 2011-09-07 中铁一局集团有限公司 Reversible suspended basket wheel type travelling system and method
CN102220740A (en) * 2011-04-13 2011-10-19 湖南中铁五新钢模有限责任公司 Cantilever-concreting construction hanging basket for four-lane and wide-width continuous beam of high-speed rail
CN102220740B (en) * 2011-04-13 2012-09-26 湖南中铁五新钢模有限责任公司 Cantilever-concreting construction hanging basket for four-lane and wide-width continuous beam of high-speed rail
CN102251480A (en) * 2011-04-29 2011-11-23 湖南中铁五新钢模有限责任公司 Small pier top construction triangular hanging basket
CN102251480B (en) * 2011-04-29 2013-05-29 湖南中铁五新钢模有限责任公司 Small pier top construction triangular hanging basket
CN104278643A (en) * 2014-10-17 2015-01-14 中铁建大桥工程局集团第五工程有限公司 Continuous rigid frame box girder construction technology applied to bridge project
CN109468955A (en) * 2018-11-12 2019-03-15 湖南金海钢结构有限公司 A kind of large size truss dismounting tooling
CN109468955B (en) * 2018-11-12 2021-06-01 湖南金海钢结构有限公司 Large-scale truss demolishs frock

Similar Documents

Publication Publication Date Title
CN201770945U (en) Synchronous cradle moving device for continuous rigid frame bridge construction cradle
CN104631335B (en) Large-tonnage Bridge Erector and construction method thereof
CN105421249B (en) Dragging- hoisting combined type hanging basket structure and construction method
CN107059640A (en) The Bridge Erector and its construction method constructed by cross for precast segmental beam
CN203866715U (en) Multi-roof-truss rhombic truss hanging basket for long-cantilever box beam construction
CN102094392B (en) Lower supported hanging basket in bridge construction and application thereof
CN201003145Y (en) Upward and self-walking type mobile die carrier
CN107725078B (en) Mining face crossheading circulation self-moving advanced support system and track self-moving system
CN201250064Y (en) Front launching nose type bridge girder erection machine for bridge erection
CN109653105B (en) Main truss system of box girder bridge cantilever construction hanging basket and use method thereof
RU2381326C1 (en) Device for lifting and erecting units of superstructure
CN205223872U (en) Drag and hang novel string of basket structure of convolution
CN204551283U (en) In tunnel, large-tonnage is set a roof beam in place fortune frame system
CN206800212U (en) The Bridge Erector constructed by cross for precast segmental beam
CN205954489U (en) Stride cast -in -place space of business line steel structure construction protection on bridge and move movable support
CN102345273B (en) Synchronous cradle moving device for continuous rigid frame bridge construction cradle
CN103288002B (en) Simple combination door frame high-altitude weight hanging apparatus
CN102605720B (en) Integrated construction equipment for binding and lifting continuous beam steel reinforcement framework and construction method
CN207987749U (en) Ride cable-styled erection crane
CN105735142A (en) Bridge girder erection machine for prestressed concrete bridge precast section span-by-span splicing construction
CN108086168A (en) Ride cable-styled erection crane
CN205975365U (en) Cast -in -situ box girder combined type moving die carrier
CN210621352U (en) Suspension type manual longitudinal moving stool beam device
CN201972099U (en) Through type hanging basket in bridge construction
CN210766433U (en) Trapezoidal hanging basket structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20110323

Effective date of abandoning: 20150415

RGAV Abandon patent right to avoid regrant