CN201760680U - Welding equipment of two-working position electric connector - Google Patents

Welding equipment of two-working position electric connector Download PDF

Info

Publication number
CN201760680U
CN201760680U CN2010202960188U CN201020296018U CN201760680U CN 201760680 U CN201760680 U CN 201760680U CN 2010202960188 U CN2010202960188 U CN 2010202960188U CN 201020296018 U CN201020296018 U CN 201020296018U CN 201760680 U CN201760680 U CN 201760680U
Authority
CN
China
Prior art keywords
electric connector
workbench
slide rail
welding equipment
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202960188U
Other languages
Chinese (zh)
Inventor
许庆仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YOUNG TAI ELECTRONIC (DONGGUAN) Ltd
Original Assignee
YOUNG TAI ELECTRONIC (DONGGUAN) Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YOUNG TAI ELECTRONIC (DONGGUAN) Ltd filed Critical YOUNG TAI ELECTRONIC (DONGGUAN) Ltd
Priority to CN2010202960188U priority Critical patent/CN201760680U/en
Application granted granted Critical
Publication of CN201760680U publication Critical patent/CN201760680U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Resistance Welding (AREA)

Abstract

The utility model discloses welding equipment of a two-working position electric connector, which comprises a frame, a slide rail, a first working platform and a second working platform, wherein the first and the second working platforms alternately work. The slide rail is fixed on the frame; the frame is provided with an electric connector electromagnetic welding device; the first and the second working platforms which can slide along the slide rail are respectively lapped on the slide rail; the first and the second working platforms are respectively provided with a clamp; and the first and the second working platforms alternately work. The electric connector electromagnetic welding device can work continuously, the electric connector electromagnetic welding device does not need to wait for the disassembly and the clamping operations of the electric connector, and the production efficiency is improved.

Description

A kind of double electric connector welding equipment
Technical field
The utility model relates to the electric connector technical field of welding equipment, refers in particular to a kind of double electric connector welding equipment.
Background technology
In the prior art, the welding equipment of electric connector adopts the electromagnetism welding, because the electric connector welding equipment only is provided with a workbench, when carrying out welding processing, need be on workbench clamping and unloading electric connector, the electric connector electromagnetism welder of welding equipment is after finishing welding processing, need to wait for operator's unloading and clamping electric connector, the stand-by period is longer, and working (machining) efficiency is low, therefore, the electric connector welding equipment of prior art has improved needs.
Summary of the invention
The purpose of this utility model is to provide a kind of double electric connector welding equipment at the deficiencies in the prior art, and it does not need to wait for unloading, the clamping operation of electric connector, and first workbench and second workbench take turns replacement work, enhance productivity.
For achieving the above object, the utility model is achieved through the following technical solutions: a kind of double electric connector welding equipment, comprise frame, slide rail and replace first workbench and second workbench of work in turn, slide rail is fixed in frame, frame is provided with electric connector electromagnetism welder, can be overlapped in slide rail respectively along first workbench and second workbench that slide rail slides, first workbench and second workbench are respectively arranged with anchor clamps.
Described slide rail respectively to the left and right both sides extend to the outside of frame, the both sides of slide rail are provided with the electric connector load/unload stations respectively, the middle part of slide rail is provided with the electromagnetism welding post.
Described first workbench and second workbench are respectively arranged with the electric connector saddle, and the electric connector saddle is positioned at a side of anchor clamps.
The bottom of the bottom of described first workbench and second workbench is fixed with slide block respectively, and slide block set is located at slide rail.
The lateral cross section of described slide rail is " worker " font, and the lateral cross section of slide rail is " C " shape.
The beneficial effects of the utility model: the utility model comprises frame, slide rail and replace first workbench and second workbench of work in turn, slide rail is fixed in frame, frame is provided with electric connector electromagnetism welder, can be overlapped in slide rail respectively along first workbench and second workbench that slide rail slides, first workbench and second workbench are respectively arranged with anchor clamps, first workbench and second workbench take turns replacement work, electric connector electromagnetism welder can continuous operation, electric connector electromagnetism welder does not need to wait for the unloading of electric connector, the clamping operation is enhanced productivity.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Fig. 2 is the structural representation of first workbench of the present utility model.
Fig. 3 is the structural representation at first another visual angle of workbench of the present utility model.
Among the figure:
1, frame
2, slide rail
3, first workbench
4, second workbench
5, anchor clamps
6, electric connector saddle
7, slide block
8, electric connector electromagnetism welder.
The specific embodiment
The embodiment of a kind of double electric connector welding equipment of the present utility model as shown in Figures 1 to 3, comprise frame 1, slide rail 2 and replace first workbench 3 and second workbench 4 of work in turn, slide rail 2 is fixed in frame 1, frame 1 is provided with electric connector electromagnetism welder 8, can be overlapped in slide rail 2 respectively along first workbench 3 and second workbench 4 that slide rail 2 slides, first workbench 3 and second workbench 4 are respectively arranged with anchor clamps 5, and anchor clamps 5 are used for clamping and fixing electric connector to be processed.
When work, first workbench 3 and second workbench 4 are worked by turns, the operator is at the good electric connector of first workbench, 3 clampings, again first workbench 3 is moved to slide rail 2 middle parts, electric connector on 8 pairs first workbench 3 of electric connector electromagnetism welder carries out welding processing, in this magnetic discharge welding termination process, the operator is at second workbench, 4 clamping electric connectors.
After the welding processing of the electric connector on first workbench 3 is finished, first workbench 3 is moved to slide rail 2 left sides, shown in Figure 1, again with second workbench, 4 sliding slide rail 2 middle parts that move to, electric connector on 8 pairs first workbench 3 of electric connector electromagnetism welder carries out welding processing, the operator takes off the electric connector that processes on first workbench 3, again clamping electric connector to be processed.Circulation so repeatedly.
First workbench 3 and the replacement work in turn of second workbench 4, electric connector electromagnetism welder 8 can continuous operations, and electric connector electromagnetism welder 8 does not need to wait for unloading, the clamping operation of electric connector, enhances productivity.
Slide rail 2 respectively to the left and right both sides extend to the outside of frame 1, the both sides of slide rail 2 are provided with the electric connector load/unload stations respectively, the middle part of slide rail 2 is provided with the electromagnetism welding post.
First workbench 3 and second workbench 4 are respectively arranged with electric connector saddle 6, and electric connector saddle 6 is used to place the wire rod by the electric connector of anchor clamps 5 clampings, and electric connector saddle 6 is positioned at a side of anchor clamps 5.
The bottom of the bottom of first workbench 3 and second workbench 4 is fixed with slide block 7 respectively, and slide block 7 is sheathed on slide rail 2.The lateral cross section of slide rail 2 is " worker " font, and the lateral cross section of slide rail 2 is " C " shape.
It is side by side parallel that frame 1 is provided with 2, two slide rails 2 of two slide rails.
The slide block 7 that the bottom of first workbench 3 is fixed with the bottom of two rows, two row slide blocks, 7, the first workbench 3 is sheathed on two slide rails 2 respectively, increases the stability of first workbench, 3 operations.
The slide block 7 that the bottom of second workbench 4 is fixed with the bottom of two rows, two row slide blocks, 7, the second workbench 4 is sheathed on two slide rails 2 respectively, in like manner, increases the stability of second workbench, 4 operations.
Above content only is preferred embodiment of the present utility model, for those of ordinary skill in the art, according to thought of the present utility model, the part that all can change in specific embodiments and applications, this description should not be construed as restriction of the present utility model.

Claims (5)

1. double electric connector welding equipment, comprise frame and slide rail, slide rail is fixed in frame, frame is provided with electric connector electromagnetism welder, it is characterized in that: first workbench and second workbench that also comprise the work of replacing in turn, can be overlapped in slide rail respectively along first workbench and second workbench that slide rail slides, first workbench and second workbench are respectively arranged with anchor clamps.
2. a kind of double electric connector welding equipment according to claim 1, it is characterized in that: described slide rail respectively to the left and right both sides extend to the outside of frame, the both sides of slide rail are provided with the electric connector load/unload stations respectively, and the middle part of slide rail is provided with the electromagnetism welding post.
3. a kind of double electric connector welding equipment according to claim 2, it is characterized in that: first workbench and second workbench are respectively arranged with the electric connector saddle, and the electric connector saddle is positioned at a side of anchor clamps.
4. a kind of double electric connector welding equipment according to claim 3, it is characterized in that: the bottom of the bottom of described first workbench and second workbench is fixed with slide block respectively, and slide block set is located at slide rail.
5. a kind of double electric connector welding equipment according to claim 4 is characterized in that: the lateral cross section of described slide rail is " worker " font, and the lateral cross section of slide rail is " C " shape.
CN2010202960188U 2010-08-18 2010-08-18 Welding equipment of two-working position electric connector Expired - Fee Related CN201760680U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202960188U CN201760680U (en) 2010-08-18 2010-08-18 Welding equipment of two-working position electric connector

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202960188U CN201760680U (en) 2010-08-18 2010-08-18 Welding equipment of two-working position electric connector

Publications (1)

Publication Number Publication Date
CN201760680U true CN201760680U (en) 2011-03-16

Family

ID=43713283

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202960188U Expired - Fee Related CN201760680U (en) 2010-08-18 2010-08-18 Welding equipment of two-working position electric connector

Country Status (1)

Country Link
CN (1) CN201760680U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103736666A (en) * 2013-12-27 2014-04-23 昆山迈致治具科技有限公司 Double-station detecting device
CN105563226A (en) * 2015-12-16 2016-05-11 芜湖杰诺科技有限公司 Device for cleaning off cuttings in flow channels of skew tee valves
CN106425251A (en) * 2016-08-30 2017-02-22 昆山利玛赫自动化科技有限公司 Double-station automatic feeding device for silicon steel sheet welding
CN108515252A (en) * 2018-04-28 2018-09-11 中天宽带技术有限公司 A kind of welding equipment and its welding method of connector assembly
CN109551129A (en) * 2019-01-08 2019-04-02 济宁凯瑞德机械设备有限公司 A kind of bent cap skeleton welding device and its application method
CN112025160A (en) * 2020-08-10 2020-12-04 安徽斯柯瑞智能装备科技有限公司 Double-station turnover welding workstation for welding square cabinet workpieces
CN112621043A (en) * 2021-01-18 2021-04-09 芳坤智能储存(宿迁)股份有限公司 Intelligent goods shelf main body multi-station automatic welding equipment
CN113602759A (en) * 2021-10-11 2021-11-05 宁波尚进自动化科技有限公司 Material block conveying mechanism

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103736666A (en) * 2013-12-27 2014-04-23 昆山迈致治具科技有限公司 Double-station detecting device
CN103736666B (en) * 2013-12-27 2016-03-23 昆山迈致治具科技有限公司 A kind of double checkout gear
CN105563226A (en) * 2015-12-16 2016-05-11 芜湖杰诺科技有限公司 Device for cleaning off cuttings in flow channels of skew tee valves
CN105563226B (en) * 2015-12-16 2018-09-28 芜湖杰诺科技有限公司 A kind of skew T valve flowing channel chip cleaning equipment
CN106425251A (en) * 2016-08-30 2017-02-22 昆山利玛赫自动化科技有限公司 Double-station automatic feeding device for silicon steel sheet welding
CN108515252A (en) * 2018-04-28 2018-09-11 中天宽带技术有限公司 A kind of welding equipment and its welding method of connector assembly
CN109551129A (en) * 2019-01-08 2019-04-02 济宁凯瑞德机械设备有限公司 A kind of bent cap skeleton welding device and its application method
CN112025160A (en) * 2020-08-10 2020-12-04 安徽斯柯瑞智能装备科技有限公司 Double-station turnover welding workstation for welding square cabinet workpieces
CN112621043A (en) * 2021-01-18 2021-04-09 芳坤智能储存(宿迁)股份有限公司 Intelligent goods shelf main body multi-station automatic welding equipment
CN112621043B (en) * 2021-01-18 2021-08-24 芳坤智能储存(宿迁)股份有限公司 Intelligent goods shelf main body multi-station automatic welding equipment
CN113602759A (en) * 2021-10-11 2021-11-05 宁波尚进自动化科技有限公司 Material block conveying mechanism

Similar Documents

Publication Publication Date Title
CN201760680U (en) Welding equipment of two-working position electric connector
CN104043936B (en) A kind of maize harvesting machine chassis vehicle frame flexible robot welding tooling
CN203791869U (en) Automatic base welding machine
CN103624428A (en) Automatic welding machine for electric appliance element fastening thin plate
CN103624640A (en) Automatic workpiece inner circle grinding machine
CN203330593U (en) Flexible production line applied to car frame welding
CN202591872U (en) Movable car body welding holder
CN105415067A (en) Reversing module applied to connecting rod type feeding assembly line
CN106624085A (en) Improved three-head four-station pliers-cutting edge dislocation processing milling machine
CN104668873A (en) Processing die for reinforcement cage
CN205237684U (en) Steel grating through mode floating clamping mechanism feeding mechanism
CN204094358U (en) A kind of Robot Spot Welding device
CN203526756U (en) Tin soldering supporting device for induction body of inductor
CN205520672U (en) A turn over rotary die group that is used for connecting rod formula pay -off assembly line
CN101920368B (en) Electromagnetic welding equipment
CN205363059U (en) Welding device
CN203726875U (en) Mobile work table for quick die change
CN203304386U (en) Novel automatic hardware clamping and forming clamp
CN202861519U (en) Blanking device for pipe used for evaporator
CN103317264A (en) Flexible production line for vehicle frame welding
CN105081154A (en) Bolt thread rolling device
CN204183160U (en) Shaped as frame parts welding tooling
CN205254590U (en) Shifting fork bar adds clamping apparatus
CN204122949U (en) A kind of track of submerged arc welding machine
CN203109076U (en) Mechanical liquid storage cylinder riveting machine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110316

Termination date: 20170818

CF01 Termination of patent right due to non-payment of annual fee