CN201751431U - Monitoring system of aluminium electrolysis cell crust breaker - Google Patents
Monitoring system of aluminium electrolysis cell crust breaker Download PDFInfo
- Publication number
- CN201751431U CN201751431U CN2010202113410U CN201020211341U CN201751431U CN 201751431 U CN201751431 U CN 201751431U CN 2010202113410 U CN2010202113410 U CN 2010202113410U CN 201020211341 U CN201020211341 U CN 201020211341U CN 201751431 U CN201751431 U CN 201751431U
- Authority
- CN
- China
- Prior art keywords
- unit
- signal
- supervisory system
- crust breaker
- monitoring system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Electrolytic Production Of Metals (AREA)
Abstract
The utility model discloses a monitoring system of an aluminium electrolysis cell crust breaker. The monitoring system is characterized by comprising a signal acquisition unit installed on a crust breaking cylinder, and a signal analysis unit and an alarming unit connected through leads, wherein the signal analysis unit receives the signals transmitted by the signal acquisition unit for analytical judgment and then transmits the signals to the alarming unit arranged in the monitoring occasion. The monitoring system can monitor the working condition of the electrolytic electrolysis cell crust breaking cylinder in time, when a hammer is clamped, or the threaded connection part of the hammer and the cylinder is loosened or falls off, or the hammer is adhered with too much electrolyte, the signals are transmitted to the signal analysis instrument through the signal acquisition device, then the signal analysis instrument make a judgment on the signals, and then an indicator light on site is used for alarming so as to inform the operating personnel of making corresponding treatment. For the monitoring system, not only can the emergent effects caused by hammer clamping be avoided in time and the power consumption is reduced, but also can the crust breaking cylinder is better protected, the using period of the hammer is prolonged and the virgin aluminum quality is ensured.
Description
Technical field
The utility model belongs to the Aluminium Electrolysis field, relates to a kind of novel aluminum cell crust breaker supervisory system specifically.
Background technology
Along with the development of China's electrolysis of aluminum industry, the various controls of electrolyzer are more and more become more meticulous, level of automation is also more and more higher.Multiple spot crust breaking blanking in the middle of the modernization large scale electrolytic cell generally adopts, the crust-breaking chips life cycle is short, changes the frequency height; Cause the burst effect of electrolyzer simultaneously easily because of the folder tup, cause power consumption to increase; Because tup and cylinder generally all adopt and are threaded, after using some cycles, can occur becoming flexible or coming off, if will certainly cause tup to be melted in the electrolyzer, cause the primary aluminum downgrade in case come off; Tup in use often contacts with ionogen, will certainly be stained with some ionogen on tup, if ionogen is too much sticking, can cause the cylinder operation load excessive, also enters into the inner difficulty that increases of electrolyzer to blanking simultaneously.So the crust breaker to electrolyzer is monitored in real time, prolong the work-ing life of crust breaking cylinder, prolong the replacement cycle of tup, reduce the generation of burst effect, improve the primary aluminum quality, it is necessary seeking a kind of not only simple but also economic supervisory system.
Summary of the invention
The problem that the utility model exists at above-mentioned existing large pre-baked cell crust breaker just; and a kind of science that provides, reasonable, energy-conservation, efficient, simple to operate, few, the safe and reliable monitoring device-a kind of novel aluminum cell crust breaker supervisory system of investment; this supervisory system can not only avoid in time because folder tup and the burst effect that causes; reduce power consumption; simultaneously can also the better protection crust breaking cylinder; prolong the life cycle of tup, guarantee the primary aluminum quality.
The purpose of this utility model is achieved through the following technical solutions: crust breaker supervisory system of the present utility model comprises the signal gathering unit that is installed on the crust breaking cylinder, by signal analysis unit and alarm unit that lead connects, and the signal that signal analysis unit transmits by the received signal collecting unit carries out sending alarm unit to after the analysis and judgement.
In the utility model, described signal gathering unit is the travel switch that is arranged on cylinder bottom, and travel switch is installed in cylinder bottom by retaining plate, and carries out spacing monitoring by the travel switch postive stop baffle.
Described signal analysis unit is a timing relay, and timing relay comprises timing relay normally opened contact SJ1 and timing relay coil SJ2.
Described alarm unit is pilot lamp or combined aural and visual alarm, and this pilot lamp or combined aural and visual alarm can be installed in the electrolyzer top, also can be installed in the slot control machine top.
Principle of work of the present utility model is: by install crust breaking system signal gathering device additional on electrolyzer, monitor the working condition of electrolyzer crust breaking cylinder in time, when folder tup or tup appears and become flexible the cylinder threaded connection place, when coming off, or when the sticking ionogen of tup is too much, by signal pickup assembly signal is sent on the signal analysis instrument, the signal analysis instrument is made judgement to signal, report to the police by the pilot lamp at scene again, notify the operating personnel to handle accordingly.
Advantage of the present utility model is:
1. when folder tup or tup occurring and become flexible the cylinder threaded connection place, when coming off, or glue ionogen when too much at tup, can in time report to the police, obtain respective handling;
2, time of fire alarming can suitably be regulated according to practical situation;
3, prolong the work-ing life of crust breaking cylinder;
4, prolong the replacement cycle of tup;
5, reduce the generation of burst effect;
6, improve the primary aluminum quality;
7, investment is little, easy to maintenance, simple to operate, safe and reliable.
Description of drawings
Fig. 1 is a functional block diagram of the present utility model.
Fig. 2 is a circuit connection diagram of the present utility model.
Among Fig. 2: I, II, III, IV are XLM-19 type travel switch, are installed in four crust breaking cylinder places of electrolyzer respectively, and SJ1 is the timing relay normally opened contact, and SJ2 is the timing relay coil, and ZA is a pilot lamp
Fig. 3 is the scheme of installation of travel switch in the utility model.
Among Fig. 3: 1 is the crust breaking cylinder piston rod, and 2 is crust breaking cylinder bottom bolt, and 3 is the travel switch mounting plate, and 4 is travel switch, and 5 is the travel switch postive stop baffle, and 6 is the threaded connection place, and 7 is the crust breaking hammer stem, and 8 is cylinder.
Embodiment
The utility model is described further below in conjunction with accompanying drawing and work on the spot:
As Figure 1-3: installing signal pickup assembly at four crust breaking cylinder 8 places of electrolyzer is stroke switch 4, be wired on the signal analysis device of slot control machine below, the output line road is connected on the alarm lamp ZA, pilot lamp ZA can be installed in the electrolyzer top, also can be installed in the slot control machine top, the observed position of handled easily personnel gets final product, the power supply that this covering device adopts is 220V/380V, general setting signal analysis and judgement opening time is 30s, and complete assembly comprises: signal gathering unit, signal analysis unit and alarm unit.After the crust breaker supervisory system installed, the logical power supply of going up can be realized electrolyzer crust breaker real time and on line monitoring.Travel switch 4 is installed in cylinder bottom by retaining plate 3, and carries out spacing monitoring by travel switch postive stop baffle 5.Travel switch 4 close along with crust breaking hammer stem 7 action downwards and, the timing relay energising, when surpassing setting-up time, hammer stem is not also got back to the position, time relay time-delay is closed and is moved, pilot lamp ZA reports to the police.
Claims (7)
1. aluminium cell crust breaker supervisory system, it is characterized in that: it comprises the signal gathering unit that is installed on the crust breaking cylinder, by signal analysis unit and alarm unit that lead connects, and the signal that signal analysis unit transmits by the received signal collecting unit carries out sending alarm unit to after the analysis and judgement.
2. aluminium cell crust breaker supervisory system according to claim 1 is characterized in that: signal gathering unit is for being arranged on the travel switch (4) bottom the cylinder (8).
3. aluminium cell crust breaker supervisory system according to claim 1 is characterized in that: signal analysis unit is a timing relay.
4. aluminium cell crust breaker supervisory system according to claim 1 is characterized in that: alarm unit is pilot lamp or combined aural and visual alarm.
5. aluminium cell crust breaker supervisory system according to claim 2 is characterized in that: travel switch (4) is installed in cylinder bottom by retaining plate (4), and carries out spacing monitoring by travel switch postive stop baffle (5).
6. aluminium cell crust breaker supervisory system according to claim 3 is characterized in that: timing relay comprises timing relay normally opened contact SJ1 and timing relay coil SJ2.
7. aluminium cell crust breaker supervisory system according to claim 4 is characterized in that: pilot lamp or combined aural and visual alarm are installed in the electrolyzer top, perhaps are installed in the slot control machine top.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010202113410U CN201751431U (en) | 2010-06-02 | 2010-06-02 | Monitoring system of aluminium electrolysis cell crust breaker |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010202113410U CN201751431U (en) | 2010-06-02 | 2010-06-02 | Monitoring system of aluminium electrolysis cell crust breaker |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201751431U true CN201751431U (en) | 2011-02-23 |
Family
ID=43601837
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010202113410U Expired - Fee Related CN201751431U (en) | 2010-06-02 | 2010-06-02 | Monitoring system of aluminium electrolysis cell crust breaker |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201751431U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104178779A (en) * | 2014-08-22 | 2014-12-03 | 中南大学 | Method and system for diagnosing working state of aluminum cell unloader |
CN104264188A (en) * | 2014-09-25 | 2015-01-07 | 中国铝业股份有限公司 | Control type intelligent crust breaking system and control type intelligent crust breaking method |
-
2010
- 2010-06-02 CN CN2010202113410U patent/CN201751431U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104178779A (en) * | 2014-08-22 | 2014-12-03 | 中南大学 | Method and system for diagnosing working state of aluminum cell unloader |
CN104178779B (en) * | 2014-08-22 | 2016-09-07 | 中南大学 | The diagnostic method of a kind of aluminum cell supplying device duty and system |
CN104264188A (en) * | 2014-09-25 | 2015-01-07 | 中国铝业股份有限公司 | Control type intelligent crust breaking system and control type intelligent crust breaking method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202492591U (en) | Control system for intelligent crust breaking of aluminum cell | |
CN201638376U (en) | Energy consumption monitoring system based on Internet of things | |
CN102541019B (en) | Automatic drainage device and control method thereof | |
CN102592878A (en) | Intelligent device and method for monitoring switch-on spring performance of vacuum circuit breaker | |
CN102409362B (en) | Aluminium cell is through-flow body do not have a power failure welding control system | |
CN206684949U (en) | The traffic lights that a kind of running status independently additionally monitors | |
CN201751431U (en) | Monitoring system of aluminium electrolysis cell crust breaker | |
CN201716398U (en) | On-line monitoring device of vacuum circuit breaker | |
CN202898565U (en) | Intelligent control device of aluminum cell pneumatic system | |
CN103272794A (en) | Traffic signal lamp intelligent washing device and washing methods thereof | |
CN1995465B (en) | Prebaked aluminum electrolytic tank crust breaking cylinder | |
CN201993374U (en) | Intelligent on-line speed monitoring device for vacuum circuit breaker | |
CN201522959U (en) | Intelligent high pressure vacuum circuit breaker | |
CN104597852A (en) | Wireless automatic water supply system | |
CN216774834U (en) | Automatic on-line monitoring device for recognizing switch state | |
CN201503463U (en) | Centralized-type fault alarm unit of LED signal controller | |
CN205855870U (en) | A kind of tower crane sensor safe operating monitoring system | |
CN201512589U (en) | Large-scale electrolytic cell shell breaking monitoring device | |
CN112769143B (en) | Intelligent safety management and control method based on ubiquitous power distribution Internet of things | |
CN209652449U (en) | A kind of aluminium cell intelligence crust breaking auxiliary system | |
CN207828426U (en) | Intelligent crust breaking system | |
CN212128319U (en) | Intelligent crust breaking control system applied to aluminum electrolysis production process | |
CN204570059U (en) | A kind of electrolyzer energy saving pneumatic system control device | |
CN201716577U (en) | Cable tunnel integrated control system | |
CN205249562U (en) | Take change over switch's urban illumination intelligent control host computer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110223 Termination date: 20110602 |