CN201738441U - Double-pool type accident pool for road leakage - Google Patents

Double-pool type accident pool for road leakage Download PDF

Info

Publication number
CN201738441U
CN201738441U CN2010201780493U CN201020178049U CN201738441U CN 201738441 U CN201738441 U CN 201738441U CN 2010201780493 U CN2010201780493 U CN 2010201780493U CN 201020178049 U CN201020178049 U CN 201020178049U CN 201738441 U CN201738441 U CN 201738441U
Authority
CN
China
Prior art keywords
pool
unhurried current
accident
water
slow flow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201780493U
Other languages
Chinese (zh)
Inventor
吴东国
蒋红梅
杨斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Merchants Chongqing Communications Research and Design Institute Co Ltd
Original Assignee
China Merchants Chongqing Communications Research and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Merchants Chongqing Communications Research and Design Institute Co Ltd filed Critical China Merchants Chongqing Communications Research and Design Institute Co Ltd
Priority to CN2010201780493U priority Critical patent/CN201738441U/en
Application granted granted Critical
Publication of CN201738441U publication Critical patent/CN201738441U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model discloses a double-pool type accident pool for road leakage, comprising a slow flow pool and an emptying pool communicated with a water outlet at the lower part of the slow flow pool. The slow flow pool is communicated with a water outlet on the rod surface, and is internally provided with slow flow cavities which are arranged in parallel along the water draining direction and are formed by the dividing of at least one slow flow baffle, and the slow flow baffle is provided with a throttle hole along the water draining direction. In the utility model, a structure combining the slow flow pool and the emptying pool is adopted, when leakage accident occurs on the road suddenly, accident water flows into the slow flow pool firstly, the structure of the slow flow pool results in the slow flowing of the accident water, the accident pool is used for storing the accident water (liquid) temporarily so as to help persons handling the accident to obtain time for site processing, and slow down the spreading of toxic and harmful substances, thus effectively protecting water resources and surrounding environment; simultaneously, the accident pool precipitates rainwater, regulates and stores rainwater when in rainstorm, and decreases the peak flow of water discharged to downstream; and the double-pool type accident pool for the road leakage has simple structure and low construction cost, and is easy for maintenance.

Description

Highway leaks two ponds formula accident pool
Technical field
The utility model relates to a kind of highway supporting facility, and particularly a kind of highway leaks two ponds formula accident pool.
Background technology
Highway is owing to have stronger flexibility, thereby more and more becomes pillar of economy.Along with market economy increasing development, highway mileage constantly increases, and particularly speedway is especially to promoting that local development plays irreplaceable effect.Because the flexibility of highway itself is inevitably by water body and conservation of nature zone.The highway transportation of chemical substances such as poisonous and harmful also is a means of transportation comparatively efficiently.These danger are poisonous, hazardous substances has constituted a potential threat that tool is big to water body and conservation of natural environment.And transportation has big possibility generation leakage, if poisonous, the hazardous substances polluted-water of leakage just may cause the downstream resident to poison, urban water supply is interrupted, and causing than great society influences.
In the prior art, for poisonous, the hazardous substances that prevents to leak pollutes natural environments such as water sources, highway operated by rotary motion accident pool, the accident pool normality is in emptying state, when having an accident, by manually the surface drainage water route being switched to accident pool.When accident took place, scene of the accident personnel can initiatively not go to switch the draining water route of highway in the practice, and the highway administration personnel reach the spot and switch hysteresis on can time of occurrence, and poisonous and harmful substance is entered in water source or the environment, cause negative consequence.
Therefore, need improve existing highway accident pond, during burst leakage accident on occurring in highway, can alleviate the diffusion of poisonous and harmful substance, and be used for temporarily storing accident water (liquid), provide buffer time for handling leak materials, prevent poisonous, hazardous substances polluted source and surrounding environment.
The utility model content
In view of this, the utility model provides a kind of highway to leak two ponds formula accident pool, during burst leakage accident on occurring in highway, can alleviate the diffusion of poisonous and harmful substance, and be used for temporarily storing accident water (liquid), provide buffer time for handling leak materials, prevent poisonous, hazardous substances polluted source and surrounding environment.
Highway of the present utility model leaks two ponds formula accident pool, comprise unhurried current pond and the blow-down pit that is communicated with unhurried current pond lower drain port, described unhurried current pond is communicated in the highway pavement outfall, be set up in parallel the unhurried current chamber that forms by at least one unhurried current barrier partitions along drainage direction in the unhurried current pond, the throttle orifice along drainage direction is set on the described unhurried current baffle plate.
Further, described highway pavement outfall is over against first chamber upper opening that flows slowly along drainage direction;
Further, the throttle orifice on the described unhurried current baffle plate is provided with a row from the bottom to top at least;
Further, the throttle orifice between the adjacent unhurried current baffle plate is along the setting of staggering up and down;
Further, described blow-down pit bottom is provided with the blow-down pit outfall that is communicated in road surface rainwater treatment system, and the blow-down pit outfall is provided with the blow-down pit valve;
Further, described unhurried current pond lower drain port is provided with unhurried current pond valve;
Further, the shared pool wall of described unhurried current pond and blow-down pit, shared pool wall upper end is provided with overfall;
Further, unhurried current baffle plate upper surface is lower than unhurried current pond pool wall.
The beneficial effects of the utility model: highway of the present utility model leaks two ponds formula accident pool, adopt unhurried current pond and blow-down pit structure combining, during burst leakage accident on occurring in highway, accident water flows into the unhurried current pond earlier, because the structure in unhurried current pond causes accident water to flow slowly, and be used for temporarily storing accident water (liquid), for carrying out in-situ processing, the accident treatment personnel gain time, can alleviate the diffusion of poisonous and harmful substance, thereby effectively protect water source and surrounding environment, simultaneously, accident pool also can precipitate rainwater, when heavy rain, rainwater is regulated and stored, reduce the peak flow of draining downstream; The utility model is simple in structure, cheap, be easy to safeguard.
Description of drawings
Below in conjunction with drawings and Examples the utility model is further described.
Accompanying drawing is a structural representation of the present utility model.
The specific embodiment
Accompanying drawing is a structural representation of the present utility model, as shown in the figure: the highway of present embodiment leaks two ponds formula accident pool, comprise unhurried current pond 1 and the blow-down pit 2 that is communicated with unhurried current pond 1 lower drain port 11, described unhurried current pond 1 is communicated in highway pavement outfall 5, be set up in parallel the unhurried current chamber 3 that is separated by at least one unhurried current baffle plate 4 along drainage direction in the unhurried current pond 1, according to the size of unhurried current pond 1 volume, unhurried current chamber 3 quantity can be for a plurality of, and present embodiment adopts the structure in six unhurried current chambeies 3; Throttle orifice 41 along drainage direction is set on the described unhurried current baffle plate 4, and the direction of arrow is drainage direction among the figure; Discharge liquid by throttle orifice 41 substeps, can effectively alleviate the flow velocity of liquid, guarantee buffering effect, prolong efflux time.
In the present embodiment, described highway pavement outfall 5 makes full use of the effect in unhurried current pond over against along first unhurried current chamber upper opening of drainage direction.
In the present embodiment, the throttle orifice 41 on the described unhurried current baffle plate 4 is provided with a row from the bottom to top at least; Size according to unhurried current pond 1 is provided with row's number of throttle orifice 41, and present embodiment is provided with three rows, accident water is moved successively on gradually according to the flow size discharge from throttle orifice from down to up, prevents overflow.
In the present embodiment, the throttle orifice 41 between the adjacent unhurried current baffle plate 4 is along the setting of staggering up and down.
In the present embodiment, described blow-down pit 2 bottoms are provided with the blow-down pit outfall 21 that is communicated in road surface rainwater treatment system, and blow-down pit outfall 21 is provided with blow-down pit valve 7; In the present embodiment, described unhurried current pond 1 lower drain port 11 is provided with unhurried current pond valve 6; Flow slowly pond valve 6 normalities for closing, whole surface drainages of damming; Blow-down pit valve 7 normalities are for opening, and volume is reserved in order to collecting accident leakage liquid in the emptying pond; Take place as leakage accident, accident water (liquid) at first enters unhurried current pond savings (unhurried current pond less than) in the unhurried current pond, and perhaps slowly flow (unhurried current Chi Yiman) slows down leak liquid and flow out the accident pool time; After treating that the staff closes the blow-down pit sluice, the whole spaces of blow-down pit promptly can be used to collect accident leakage liquid.
In the present embodiment, described unhurried current pond 1 and blow-down pit 2 shared pool walls 8, shared pool wall 8 upper ends are provided with overfall 12; The accident water unhurried current that overfills can slowly flow out to blow-down pit behind the pond 1, prevents to overflow.
In the present embodiment, unhurried current baffle plate 4 upper surfaces are lower than unhurried current pond pool wall, prevent to overflow from pool wall greatly because of fluid flow.
Explanation is at last, above embodiment is only unrestricted in order to the explanation the technical solution of the utility model, although the utility model is had been described in detail with reference to preferred embodiment, those of ordinary skill in the art is to be understood that, can make amendment or be equal to replacement the technical solution of the utility model, and not breaking away from the aim and the scope of technical solutions of the utility model, it all should be encompassed in the middle of the claim scope of the present utility model.

Claims (8)

1. a highway leaks two ponds formula accident pool, it is characterized in that: comprise unhurried current pond and the blow-down pit that is communicated with unhurried current pond lower drain port, described unhurried current pond is communicated in the highway pavement outfall, be set up in parallel the unhurried current chamber that forms by at least one unhurried current barrier partitions along drainage direction in the unhurried current pond, the throttle orifice along drainage direction is set on the described unhurried current baffle plate.
2. highway according to claim 1 leaks two ponds formula accident pool, it is characterized in that: described highway pavement outfall is over against first chamber upper opening that flows slowly along drainage direction.
3. highway according to claim 2 leaks two ponds formula accident pool, and it is characterized in that: the throttle orifice on the described unhurried current baffle plate is provided with a row from the bottom to top at least.
4. highway according to claim 3 leaks two ponds formula accident pool, it is characterized in that: the throttle orifice between the adjacent unhurried current baffle plate is along the setting of staggering up and down.
5. highway according to claim 4 leaks two ponds formula accident pool, it is characterized in that: described blow-down pit bottom is provided with the blow-down pit outfall that is communicated in road surface rainwater treatment system, and the blow-down pit outfall is provided with the blow-down pit valve.
6. highway according to claim 5 leaks two ponds formula accident pool, it is characterized in that: described unhurried current pond lower drain port is provided with unhurried current pond valve.
7. highway according to claim 6 leaks two ponds formula accident pool, it is characterized in that: the shared pool wall of described unhurried current pond and blow-down pit, shared pool wall upper end is provided with overfall.
8. highway according to claim 7 leaks two ponds formula accident pool, it is characterized in that: unhurried current baffle plate upper surface is lower than unhurried current pond pool wall.
CN2010201780493U 2010-04-30 2010-04-30 Double-pool type accident pool for road leakage Expired - Fee Related CN201738441U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201780493U CN201738441U (en) 2010-04-30 2010-04-30 Double-pool type accident pool for road leakage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201780493U CN201738441U (en) 2010-04-30 2010-04-30 Double-pool type accident pool for road leakage

Publications (1)

Publication Number Publication Date
CN201738441U true CN201738441U (en) 2011-02-09

Family

ID=43553719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201780493U Expired - Fee Related CN201738441U (en) 2010-04-30 2010-04-30 Double-pool type accident pool for road leakage

Country Status (1)

Country Link
CN (1) CN201738441U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102354180A (en) * 2011-08-03 2012-02-15 交通运输部科学研究院 Hazardous chemical leakage monitoring and emergency treatment system for sensitive water body bridge section
CN102720128A (en) * 2012-06-22 2012-10-10 云南省交通规划设计研究院 Emergency disposal system for runoff accidents of bridge floor of grand road bridge
CN113957969A (en) * 2021-08-16 2022-01-21 天津市政工程设计研究总院有限公司 Drainage emergency treatment system and method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102354180A (en) * 2011-08-03 2012-02-15 交通运输部科学研究院 Hazardous chemical leakage monitoring and emergency treatment system for sensitive water body bridge section
CN102354180B (en) * 2011-08-03 2013-04-03 交通运输部科学研究院 Hazardous chemical leakage monitoring and emergency treatment system for sensitive water body bridge section
CN102720128A (en) * 2012-06-22 2012-10-10 云南省交通规划设计研究院 Emergency disposal system for runoff accidents of bridge floor of grand road bridge
CN113957969A (en) * 2021-08-16 2022-01-21 天津市政工程设计研究总院有限公司 Drainage emergency treatment system and method thereof

Similar Documents

Publication Publication Date Title
CN105130055B (en) Rainwater-collecting purified treatment reclaiming system
CN104141346B (en) Combined rainwater diafiltration tree pond
CN103739167A (en) Rain and sewage dual-purpose landscape type ecological purification system
CN201738441U (en) Double-pool type accident pool for road leakage
CN104003574A (en) Labyrinth-type ecological purification pool suitable for drainage ditch in farmland
CN105013244B (en) Multistage rainwater purification processing equipment
KR20140135140A (en) All particulate pollutants contained in rainwater and early stormwater, all the wastes coming in along with the initial stormwater, all the bound materials associated with the water molecules, and the floating substances, and then clean the waters with clean water and rainwater. Environment-friendly rainwater purification eco-friendly method that is stored in storage and reused
CN203938558U (en) Rain, dirty dual-purpose landscape type ecological purification system
CN111517496A (en) Rain sewage treatment system based on multi-point mixed drainage and regulation
CN104005470A (en) Gutter inlet structure with sewage stopping function and diversion function
CN104773898A (en) Physicochemical-artificial wetland combined process for strengthening treatment of fluorine and arsenic sewage
CN101041514A (en) Biological controlled reactor for active sludge filamentous bacterium and technique
CN205368052U (en) Ecological wet land treatment system of dirty waste water low energy consumption in rural area compact community
CN104150582A (en) Modularized energy-saving spatial formula sewage treatment device and system thereof used for multi-floor buildings
CN103437281A (en) Bridge deck runoff collection treatment and emergency system
CN203383144U (en) Bridge floor runoff collection, treatment and emergency system
CN202730707U (en) Initial-stage rainwater intercepting and shunting as well as later-stage rainwater separating system for flood drainage river channel
CN105800810A (en) Low-effect treatment method of good-quality rainwater
CN202777962U (en) Pretreatment device for applying horizontal subsurface flow constructed wetland to landscape water body purification
CN102120652B (en) Coal-based adsorption sewage treatment method and adsorption system
CN104817242A (en) Absorption treatment method for municipal scattered sludge
CN104975644B (en) Special pipe storage system for road initial rainwater
CN107354990A (en) A kind of storage for roadside oozes net row's type rainwater reuse device
CN108147618A (en) A kind of unpowered riverfront Ecology keeps cleaning treatment system
CN208684454U (en) A kind of sewage disposal device with automatic clearing function

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110209