CN201738334U - Load-bearing and pressure-bearing combination type inspection shaft - Google Patents

Load-bearing and pressure-bearing combination type inspection shaft Download PDF

Info

Publication number
CN201738334U
CN201738334U CN2010202717393U CN201020271739U CN201738334U CN 201738334 U CN201738334 U CN 201738334U CN 2010202717393 U CN2010202717393 U CN 2010202717393U CN 201020271739 U CN201020271739 U CN 201020271739U CN 201738334 U CN201738334 U CN 201738334U
Authority
CN
China
Prior art keywords
circular arc
bearing
arc module
load
inspection shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202717393U
Other languages
Chinese (zh)
Inventor
宋治中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2010202717393U priority Critical patent/CN201738334U/en
Application granted granted Critical
Publication of CN201738334U publication Critical patent/CN201738334U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a load-bearing and pressure-bearing combination type inspection shaft. The inspection shaft comprises a sectional shaft formed by combing four circular arc modules (4) in uniform shapes and sizes; each circular arc module (4) is provided with at least a reinforcing rib (3); bolted connection sides (2) connected with adjacent circular arc modules (4) are arranged on axial lateral sides of each circular arc module (4); at least a pipe mouth opening (6) is formed on each circular arc module (4); and matched inserting holes are formed at the radial top and the radial bottom of each circular arc module (4). The inspection shaft disclosed by the utility model effectively bears loads and pressure, prevents leakage, and is practical and safe.

Description

A kind of load-bearing pressure-bearing combined inspection shaft tube
Technical field
The utility model discloses a kind of load-bearing pressure-bearing combined inspection shaft tube that utilizes high molecular material resin base and other material produced with combination, belong to building environmental protection field.
Background technology
At present, in the manhole of pipe-networks engineerings such as civilian construction and municipal engineering, uptown, tap water, telecommunications, electric power greatly to there being three kinds: first kind is brick mix structure; Second kind is reinforced concrete prefabricated; The third is the composite material synthesis type manhole of enabling in recent years.
First kind: brick mix structure is because of the multinomial transhipment of material and the limitation of some construction plants, and cause constructing very complicated and construction period are long; Simultaneously because the defective of material itself, this product not only appearance is coarse but also seepage is serious, and also very unstable the causing when carrying out constructing the second time easily of structure collapsed.
Second kind: reinforced concrete prefabricated this causes transhipment gruelling to a certain extent because of individual heavy, and cost of transportation is also very high simultaneously.The problem that this prefabricated component does not also have thoroughly to solve seepage and permeated, another this product need thoroughly to change in case be damaged when construction and be difficult for repairing.
The third: is though other composite material synthesis type is checked the problems such as seepage of the fine roughening that solves brick mix structure of pit shaft, concrete precast element, but owing to ignore the complexity of its construction and the polytropy of geological conditions, often intensity and stiffness are all very poor, and transportation the squeeze crack phenomenon occurs in installing easily.
The utility model content
Technical problem to be solved in the utility model provides the load-bearing pressure-bearing combined inspection shaft tube of a kind of effective load-bearing pressure-bearing and anti-leakage, practical safety.
In order to solve the problems of the technologies described above, the load-bearing pressure-bearing combined inspection shaft tube that the utility model provides, comprise the assistant warden pit shaft, circular arc module combinations block-shaped and of the same size forms described assistant warden pit shaft by four, every described circular arc module is provided with at least one reinforcing rib, the axial side of described circular arc module is provided with the bolt fillet that is connected with adjacent circular arc module, on described circular arc module, be provided with a mouth of pipe hole at least, the radial top of described circular arc module and radially the bottom be provided with the cooperation interface.
Described mouth of pipe hole is located on the bolt fillet on the described circular arc module.
Described reinforcing rib is one and is arranged on the axial middle part of described circular arc module.
Described reinforcing rib is made by the reinforcing bar of 25mm.
The radial top of described circular arc module is provided with concave ring groove, and the radially bottom of described circular arc module is provided with and the bulge loop of described groove fit to inserting.
Adopt the load-bearing pressure-bearing combined inspection shaft tube of technique scheme, made reinforcing rib, a plurality of assistant warden pit shafts are formed by pegging graft, be convenient to install, economical with materials and man-hour, thus save cost, be assembled into multistage inspection pit shaft by multimode, not only well solved seepage and by infiltration problem, and inner exquisite smooth, can the load-bearing pressure-bearing, convenient transportation, quick for installation be the inevitable substitute of current pipe-networks engineering manhole.
The utility model reaches following effect:
One, overall structure good airproof performance, leakproof and infiltration have solved thoroughly that brick mix structure and reinforced concrete precast member are coarse, seepage and the problem of being permeated.
Two, changed the synthetic problem of checking the anti-extrusion and load-bearing of pit shaft of other composite material.
Three, convenient fortune connect, quick for installation, reduced transport power and construction cost.
Four, safeguard and overhaul very conveniently, effectively reduce cost of production and construction cost.
In sum, the utility model is the load-bearing pressure-bearing combined inspection shaft tube of a kind of effective load-bearing weight and anti-leakage, practical safety.
Description of drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is along A-A line cut-away view among Fig. 1;
Fig. 3 is the utility model combining structure schematic diagram.
The specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments.
Referring to Fig. 1, Fig. 2 and Fig. 3, four circular arc modules 4 block-shaped and of the same size combine one group of assistant warden pit shaft, every circular arc module 4 axially is provided with a reinforcing rib 3 in the middle part, reinforcing rib 3 is made by the reinforcing bar of 25mm, the axial side of circular arc module 4 is provided with the bolt fillet 2 that is connected with adjacent circular arc module 4, on each the bolt fillet 2 on the circular arc module 4, be provided with mouth of pipe hole 6, the radial top of circular arc module 4 is provided with concave ring groove 1, and the radially bottom of circular arc module 4 is provided with groove 1 and cooperates slotting bulge loop 5.
Referring to Fig. 1, Fig. 2 and Fig. 3, four circular arc modules 4 combine one group of assistant warden pit shaft, pass through between the adjacent circular arc module 4 to form a cylinder with bolt connecting bolt fillet 2, two groups of assistant warden pit shafts bulge loop 5 by last one group circular arc module 4 is inserted into and finishes cooperation in the groove 1 of circular arc module 4 of next group insert group is adorned up and down, and is quick for installation.Every circular arc module 4 axially is provided with a reinforcing rib 3 in the middle part, is convenient to be provided with mouth of pipe hole 6 on each bolt fillet 2 of circular arc module 4, and mouth of pipe hole 6 is used for being connected with other pipe network, or is used to overhaul pipe-networks engineering.
Referring to Fig. 1, Fig. 2 and Fig. 3, adopt the load-bearing pressure-bearing combined inspection shaft tube of technique scheme, made reinforcing rib 3, a plurality of assistant warden pit shafts are formed by pegging graft, and are convenient to install, economical with materials and man-hour, thereby the saving cost is assembled into multistage inspection pit shaft by multimode, has not only well solved seepage and by infiltration problem, and inner exquisite smooth, can the load-bearing pressure-bearing, convenient transportation, quick for installation be the inevitable substitute of current pipe-networks engineering manhole.

Claims (5)

1. load-bearing pressure-bearing combined inspection shaft tube, comprise the assistant warden pit shaft, it is characterized in that: circular arc module block-shaped and of the same size (4) combines described assistant warden pit shaft by four, every described circular arc module (4) is provided with at least one reinforcing rib (3), the axial side of described circular arc module (4) is provided with the bolt fillet (2) that is connected with adjacent circular arc module (4), on described circular arc module (4), be provided with a mouth of pipe hole (6) at least, the radial top of described circular arc module (4) and radially the bottom be provided with the cooperation interface.
2. load-bearing pressure-bearing combined inspection shaft tube according to claim 1 is characterized in that: described mouth of pipe hole (6) is located on the bolt fillet (2) on the described circular arc module (4).
3. load-bearing pressure-bearing combined inspection shaft tube according to claim 1 and 2 is characterized in that: described reinforcing rib (3) is one and is arranged on the axial middle part of described circular arc module (4).
4. load-bearing pressure-bearing combined inspection shaft tube according to claim 1 and 2, it is characterized in that: described reinforcing rib (3) is made by the reinforcing bar of 25mm.
5. load-bearing pressure-bearing combined inspection shaft tube according to claim 1 and 2, it is characterized in that: the radial top of described circular arc module (4) is provided with concave ring groove (1), and the radially bottom of described circular arc module (4) is provided with described groove (1) and cooperates slotting bulge loop (5).
CN2010202717393U 2010-07-28 2010-07-28 Load-bearing and pressure-bearing combination type inspection shaft Expired - Fee Related CN201738334U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202717393U CN201738334U (en) 2010-07-28 2010-07-28 Load-bearing and pressure-bearing combination type inspection shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202717393U CN201738334U (en) 2010-07-28 2010-07-28 Load-bearing and pressure-bearing combination type inspection shaft

Publications (1)

Publication Number Publication Date
CN201738334U true CN201738334U (en) 2011-02-09

Family

ID=43553612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202717393U Expired - Fee Related CN201738334U (en) 2010-07-28 2010-07-28 Load-bearing and pressure-bearing combination type inspection shaft

Country Status (1)

Country Link
CN (1) CN201738334U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755767A (en) * 2018-07-12 2018-11-06 山东省水利科学研究院 It is assembled can load-bearing concentrate water meter chamber

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755767A (en) * 2018-07-12 2018-11-06 山东省水利科学研究院 It is assembled can load-bearing concentrate water meter chamber

Similar Documents

Publication Publication Date Title
CN202401473U (en) Necking plastic inspection well
CN109404224A (en) It is a kind of based on edge put more energy into combined shell wind-powered electricity generation mix tower
CN202076759U (en) Improved elastic pipeline plugging piece
CN201495558U (en) Plastic inspection chamber
CN201396248Y (en) Longitudinal flange of wind power generator tower cylinder
CN201738334U (en) Load-bearing and pressure-bearing combination type inspection shaft
AU2020200119A1 (en) Environmental protection tank for waste and hazardous liquid storage
CN201738336U (en) Composite material load- and pressure-bearing combined inspection shaft
CN201943089U (en) Load-bearing pressure-bearing combined type corrugated shaft
CN201738335U (en) Load-bearing and pressure-bearing combined tapered inspection shaft
CN201473969U (en) Pre-stressing force load-bearing and pressure-bearing combined inspection pit shaft made of composite material
CN209638561U (en) A kind of corrugated steel pipe Combined concrete push pipe
CN209398541U (en) It is a kind of based on edge put more energy into combined shell wind-powered electricity generation mix tower
CN206667596U (en) A kind of detachable assembling type concrete-filled circular steel tube column
CN215292757U (en) Fan tower cylinder prefabricated component and fan tower cylinder
CN204225558U (en) Lattice steel pipe column and power transmission tower frame
CN112922788A (en) Fan tower section of thick bamboo precast concrete component and fan tower section of thick bamboo
CN201458922U (en) Combined septic tank
CN104164995A (en) Lattice steel pipe columns, power transmission tower and construction method of lattice steel pipe columns and power transmission tower
CN101580335A (en) Combined septic tank
CN206346186U (en) Underground heat concrete-pile
CN204849808U (en) Basis is assembled in prefabrication of large -scale tower machine concrete
CN214699618U (en) Natural gas pipeline connecting structure
CN201495559U (en) Plastic inspection chamber
CN108675371A (en) A kind of quick assembled type pond body structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Changsha Wei Jia Environmental Protection Technology Co., Ltd

Assignor: Song Zhizhong

Contract record no.: 2011430000242

Denomination of utility model: Load-bearing and pressure-bearing combination type inspection shaft

Granted publication date: 20110209

License type: Exclusive License

Record date: 20111024

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110209

Termination date: 20150728

EXPY Termination of patent right or utility model