CN201679228U - Shell support steel mould structure of hydraulic power plant - Google Patents

Shell support steel mould structure of hydraulic power plant Download PDF

Info

Publication number
CN201679228U
CN201679228U CN2010201344530U CN201020134453U CN201679228U CN 201679228 U CN201679228 U CN 201679228U CN 2010201344530 U CN2010201344530 U CN 2010201344530U CN 201020134453 U CN201020134453 U CN 201020134453U CN 201679228 U CN201679228 U CN 201679228U
Authority
CN
China
Prior art keywords
mould
door frame
frame column
adjustable
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201344530U
Other languages
Chinese (zh)
Inventor
廖祖梁
梁涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2010201344530U priority Critical patent/CN201679228U/en
Application granted granted Critical
Publication of CN201679228U publication Critical patent/CN201679228U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a shell support steel mould structure of a hydraulic power plant, which relates to hydraulic and hydro-power engineering. The structure is composed by connecting a plurality of mould plate system units, wherein each mould plate system unit comprises a shell shaped mould plate, and a support system which is used for supporting the shaped mould plate; the shaped mould plate comprises an upper inclined mould, a top mould, a side mould and a lower inclined mould; the support system comprises a left and right H-shaped steel gantry upright posts, a gantry transversal beam, square wood, adjustable supporter and adjustable inclined supporter, wherein the left and right H-shaped steel gantry upright posts are fixed on the concrete surface of the shell bottom plate; the gantry transversal beam is connected and fixed between the left and right H-shaped steel gantry upright posts, and comprises an upper transversal beam, a middle transversal beam and a lower transversal beam; the upper transversal beam is fixed with the left and right gantry upright posts through the adjustable supporter and the adjustable inclined supporter; and the gantry upright posts and the shaped mould plates between the adjacent mould plate system units are respectively connected. The utility model has the advantages of simple and quick construction, ensured shape and quality, circulation use and low cost.

Description

A kind of power station crucible shell supports structure of steel die
Technical field
The utility model relates to Hydraulic and Hydro-Power Engineering, particularly and a kind of power station crucible shell support structure of steel die.
Background technology
Power station crucible hull shape body is similar to hodmadod, and it act as water inlet impact current and redistributes by changing modes such as fluidised form in the crucible shell, and it is imported seat ring, impacts the stator rotation and the conversion of generation magnetoelectricity.According to " powerhouse of hydropower station design specifications " (SD335-89) regulation of 4.3.21 bar, the crucible shell is divided into two kinds on metal crucible shell and steel concrete crucible shell, when head appropriate to the occasion employing metal crucible shell more than 40m; If adopt steel concrete crucible shell, the Technological Economy authentication should be arranged then.Two kinds of basic combination of steel concrete crucible shell bearing load combination branch and specific combination, basic combination: dead load+machine pier transmits load+turbine floor load+internal water pressure+external water pressure; Specific combination need consider also that the external water pressure under internal water pressure off-load under the crucible shell emptying state, the check flood state increases and the variations in temperature condition under situations such as thermal stresses variation, its critical role and bearing load situation have determined must to guarantee the smooth-going of the accuracy of crucible housing shape and body in work progress, be the emphasis and the difficult point of the construction of powerhouse of hydropower station engineering second stage concrete.
The traditional handicraft of wooden form+combined steel formwork on-site consolidation is adopted in the conventional construction of steel concrete crucible shell, and the job practices of traditional wooden model processing+combined steel assembly unit has following characteristics and shortcoming:
(1) skilled worker's professional standards of Yao Qiuing, qualification height, quantity is more, and has experience or the experience of being engaged in similar construction;
(2) technological service will put in place, can not make mistakes
To measuring setting-out, putting a required precision height, need the all-the-way tracking service; The workload of doing over again that produces of going wrong is big, causes the serious waste of duration, material resources and manpower, has a strong impact on the duration.
(3) long construction period
Because influences such as complexity, the narrow and different specialties in machine crucible construction operation place, the operation operation of crucible shell structure intersect mutually, steel concrete crucible shell is because of the temperature requirements construction in layer, it is big that interlayer is connected difficulty, adopt the method construction period of traditional wooden model processing, assembly unit inevitable longer, the COMPREHENSIVE CALCULATING separate unit crucible shell construction period is no less than 2.5 months, and it is long in time limit to take straight line.
(4) bodily form is difficult for guaranteeing
Conventional steel reinforced concrete crucible shell job practices is many owing to wooden form assembly unit slit, plank rigidity is less relatively, the limit inner corner trim is difficult for reasons such as construction, the crucible shell morphology easily produces distortion during concreting, the time faulting of slab ends arranged, run mould, quality problems such as spillage take place, later stage defect processing workload is big, the difficulty height.
(5) construction cost height
The high material consumption that the crucible shell job practices of the processing of tradition wooden model, assembly unit causes, particularly all the more so to difficult timber of regenerating, steel pipe etc., and be difficult to turnover utilization, the construction cost stand disappears greatly.
The utility model content
At the problem that above-mentioned prior art exists, the utility model purpose is to provide a kind of power station crucible shell to support structure of steel die, and the construction simple and fast, bodily form quality is guaranteed and can repeatedly have enough to meet the need use, cost is low.
The technical solution of the utility model is: a kind of power station crucible shell supports structure of steel die, connect and compose by a plurality of template systems unit, wherein each template system unit comprises crucible shell profiled template, and the support system that supports profiled template, wherein profiled template comprises the last oblique mould that from top to down forms the semi-surrounding structure from left to right around support system, backform, side form and declivity mould, support system comprises the left and right sides i iron door frame column that is fixed on the crucible shell bottom board concrete face, be connected and fixed on the door frame crossbeam between the door frame column of the left and right sides, and the lumps of wood, adjustable supports and adjustable diagonal brace, wherein the door frame crossbeam comprises top rail, middle cross beam and lower transverse beam, and top rail is fixed by adjustable supports and adjustable diagonal brace and left and right sides door frame column, between the door frame column between adjacent forms system unit and between each profiled template connection is arranged all, wherein going up oblique mould is supported on the left-hand door frame column by adjustable diagonal brace connection, backform connect to be gone up oblique mould and side form and is connected on the top rail by the channel-section steel secondary beam, side form is connected on the right door frame column by the channel-section steel secondary beam, and the declivity mould stands on the crucible shell bottom board concrete face and by the lumps of wood and left-hand door frame column and is connected and fixed.
The beneficial effects of the utility model are: the utlity model has accelerating construction progress, save duration, the bodily form, quality is guaranteed and can repeatedly have enough to meet the need distinguishing feature such as use, innovation point such as have pre-assembly unit simultaneously, can regulate, application prospect is very wide, the promotional value height.
Description of drawings
Fig. 1 is the structural representation of the utility model embodiment.
The specific embodiment
As a kind of embodiment of the present utility model, as shown in Figure 1, a kind of power station crucible shell supports structure of steel die, connect and compose by a plurality of template systems unit, wherein each template system unit comprises crucible shell profiled template, and the support system that supports profiled template, wherein profiled template comprises the last oblique mould 1 that from top to down forms the semi-surrounding structure from left to right around support system, backform 2, side form 3 and declivity mould 4, declivity mould 4 uses in advance, support system comprises the left and right sides i iron door frame column 6 that is fixed on the crucible shell bottom board concrete face 5,7, be connected and fixed on left and right sides door frame column 6,7 door frame crossbeam, and the lumps of wood 8, adjustable supports 9 and adjustable diagonal brace 10, crucible shell bottom board concrete face 5 is also built in advance, wherein the door frame crossbeam comprises top rail 11, middle cross beam 12 and lower transverse beam 13, and top rail 11 is by adjustable supports 9 and adjustable diagonal brace 10 and left and right sides door frame column 6,7 is fixing, top rail 11 can be adjusted height up and down by adjustable supports 9 and adjustable diagonal brace 10, door frame column 6 between adjacent forms system unit, between 7 and each profiled template connection is arranged all, each template system unit is constituted a crucible shell punching block integral body, wherein going up oblique mould 1 is supported on the left-hand door frame column 6 by adjustable diagonal brace 10 connections, backform 2 connects to be gone up oblique mould 1 and side form 3 and is connected on the top rail 11 by channel-section steel secondary beam 14, side form 3 is connected on the right door frame column 7 by channel-section steel secondary beam 14, and declivity mould 4 stands on the crucible shell bottom board concrete face 5 and by the lumps of wood 8 and left-hand door frame column 6 and is connected and fixed.As preferably, each ingredient monolithic weight of described profiled template is no more than 150kg.All profiled templates all by design drawing in processing factory's machine-shaping, pre-assembly unit check is carried out in processing factory in the back that completes, to guarantee that making the bodily form satisfies required precision.All profiled templates, support system member all can split into loose mail, are convenient to the demoulding and transportation, also convenient the installation.
During installation, the utility model is one-shot forming, placement layer by layer.
Its installation is carried out as follows: land clearing → measurement levelling, check → control point setting-out → door frame column 6,7 location → support system installation → template installation → adjustable supports 9 and adjustable diagonal brace 10 adjusting → moulding check → fixing → concreting in lifts → adjustable supports 9 and adjustable diagonal brace 10 demouldings → template inspection, maintenance.
The full support system load combination of this crucible shell: combination such as the deadweight+concrete lateral pressure+thick coagulation earth mulch of top 3.0m weight+reinforcing bar system peace is calculated, safety factor gets 1.5, and Form board frame adopts ∠ 63 angle bar cornerites, belly to add the requirement that shin (angle bar) has guaranteed template stiffness, flatness.Corner, corner adopt typing chamfering template, form joint to adopt measures such as adhesive plaster sealing, have avoided the generation of mass defect such as spillage, faulting of slab ends in the concreting process, have guaranteed the bodily form of building of steel concrete crucible shell.

Claims (1)

1. a power station crucible shell supports structure of steel die, it is characterized in that: connect and compose by a plurality of template systems unit, wherein each template system unit comprises crucible shell profiled template, and the support system that supports profiled template, wherein profiled template comprises the last oblique mould that from top to down forms the semi-surrounding structure from left to right around support system, backform, side form and declivity mould, support system comprises the left and right sides i iron door frame column that is fixed on the crucible shell bottom board concrete face, be connected and fixed on the door frame crossbeam between the door frame column of the left and right sides, and the lumps of wood, adjustable supports and adjustable diagonal brace, wherein the door frame crossbeam comprises top rail, middle cross beam and lower transverse beam, and top rail is fixed by adjustable supports and adjustable diagonal brace and left and right sides door frame column, between the door frame column between adjacent forms system unit and between each profiled template connection is arranged all, wherein going up oblique mould is supported on the left-hand door frame column by adjustable diagonal brace connection, backform connect to be gone up oblique mould and side form and is connected on the top rail by the channel-section steel secondary beam, side form is connected on the right door frame column by the channel-section steel secondary beam, and the declivity mould stands on the crucible shell bottom board concrete face and by the lumps of wood and left-hand door frame column and is connected and fixed.
CN2010201344530U 2010-03-18 2010-03-18 Shell support steel mould structure of hydraulic power plant Expired - Fee Related CN201679228U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201344530U CN201679228U (en) 2010-03-18 2010-03-18 Shell support steel mould structure of hydraulic power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201344530U CN201679228U (en) 2010-03-18 2010-03-18 Shell support steel mould structure of hydraulic power plant

Publications (1)

Publication Number Publication Date
CN201679228U true CN201679228U (en) 2010-12-22

Family

ID=43344278

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201344530U Expired - Fee Related CN201679228U (en) 2010-03-18 2010-03-18 Shell support steel mould structure of hydraulic power plant

Country Status (1)

Country Link
CN (1) CN201679228U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587414A (en) * 2012-03-12 2012-07-18 中天建设集团有限公司 Forming cushion combined formwork jacking method for inner rib angles of municipal structures
CN108729673A (en) * 2018-04-12 2018-11-02 五冶集团上海有限公司 A kind of tool-typed formwork hoisting die construction method at plate face difference of height

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587414A (en) * 2012-03-12 2012-07-18 中天建设集团有限公司 Forming cushion combined formwork jacking method for inner rib angles of municipal structures
CN108729673A (en) * 2018-04-12 2018-11-02 五冶集团上海有限公司 A kind of tool-typed formwork hoisting die construction method at plate face difference of height

Similar Documents

Publication Publication Date Title
CN101824800B (en) Method for construction of bridge cast-in-situ pre-stressed concrete continuous beam
CN103174166B (en) A kind of recreation facility built-in fitting of complete integral installation and mounting method thereof
CN102912900A (en) Prefabricated assembled superposed plate type concrete shear wall and construction method thereof
CN204040464U (en) A kind of slab form supporting construction
CN103938796A (en) Construction method of cast-in-situ reinforced concrete column
CN203531147U (en) Embedded type anchor bolt connecting structure for I-shaped steel column
CN211517947U (en) Bridge case roof beam is prefabricated with shaped steel pedestal
CN103266778B (en) Detachable triangular scaffold and steel truss assembly construction method
CN201924289U (en) Bracket structure for 0# block of high-pier long-span continuous rigid frame bridge
CN102493647B (en) Construction method for high-rise concrete structure
CN202925721U (en) Prefabricated superimposed sheet-type concrete shear wall structure
CN103321155B (en) Viaduct pier operation platform system and build this system and pour into a mould the method for bridge pier
CN201738597U (en) Sectional steel and steel pipe combined type support system of beam with high and large cross section
CN201679228U (en) Shell support steel mould structure of hydraulic power plant
CN201648978U (en) Tied arch support of bridge location cast-in-situ prestressed concrete continuous beam
CN103952979A (en) Bracket-free construction device and construction method for steel-concrete superposed beam top plate
CN103195200A (en) Steel bar truss buckle hanging type floor support plate
CN201011127Y (en) Suspended steel wood combined template
CN101265725A (en) Building method based on power plant steel structure great plate beam and column connected node
CN203200982U (en) Steel bar truss buckling hanging type floor support plate
CN202220439U (en) Combined steel template of integral stair plate
CN103669566B (en) The construction method of the steel reinforced concrete pedestal on large span grid roof
CN205617664U (en) Prefabricated pier stud locating rack for steel reinforcement cage
CN206646817U (en) The form bracing system of the cast-in-place decorative panel of staged Arc Stand
CN202577158U (en) Hyperbolic cable tower cross beam adjusting bracket

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101222

Termination date: 20110318