CN201674346U - Back pressure generating set - Google Patents

Back pressure generating set Download PDF

Info

Publication number
CN201674346U
CN201674346U CN2010202035854U CN201020203585U CN201674346U CN 201674346 U CN201674346 U CN 201674346U CN 2010202035854 U CN2010202035854 U CN 2010202035854U CN 201020203585 U CN201020203585 U CN 201020203585U CN 201674346 U CN201674346 U CN 201674346U
Authority
CN
China
Prior art keywords
back pressure
generating set
pressure turbine
generator
generating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202035854U
Other languages
Chinese (zh)
Inventor
陈国龙
俞文青
尹立辉
倪科莹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAOXING ZHONGCHENG THERMOELECTRICITY CO Ltd
Original Assignee
SHAOXING ZHONGCHENG THERMOELECTRICITY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAOXING ZHONGCHENG THERMOELECTRICITY CO Ltd filed Critical SHAOXING ZHONGCHENG THERMOELECTRICITY CO Ltd
Priority to CN2010202035854U priority Critical patent/CN201674346U/en
Application granted granted Critical
Publication of CN201674346U publication Critical patent/CN201674346U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Engine Equipment That Uses Special Cycles (AREA)

Abstract

The utility model discloses a back pressure generating set, belonging to the technical field of a thermoelectric device. The back pressure generating set comprises a generator, and is characterized in that a back pressure turbine is connected with the generator by a coupler; a boiler is connected with the back pressure turbine; and a heat supply mother pipe is connected with the back pressure turbine. The generating set adopting the back pressure turbine replaces the original extraction condensing steam turbine generating set, thus effectively improving the generating efficiency and reducing the generating cost and pollution.

Description

The back pressure type generating set
Technical field:
The utility model relates to a kind of back pressure type generating set, belongs to the thermoelectric device technical field.
Project background:
At present, in the pyroelectric technology field, the units with fixed attention of taking out that adopt as shown in Figure 1 more, the shortcoming of its existence is as follows: 1, along with the raw coal price rises steadily, cost of electricity-generating is more and more higher.2, national energy-saving and emission-reduction policy puts more effort, and the electricity determining by heat policy is implemented rapidly, and the outlet of thermoelectric enterprise is to enlarge heat supply, reduces energy resource consumption and pollutant emission.3, the expansion of heat demand existing takes out with fixed attention that unit is difficult to satisfy this development need.According to National Development and Reform Committee's file, little thermoelectricity will face closes down destiny, and running time can be not oversize.4, take out that with fixed attention the unit service efficiency is low.
Have based on this, make the utility model.
The utility model content:
The purpose of this utility model is to provide a kind of generating set of novel employing back pressure turbine, effectively improves generating efficiency, reduces cost of electricity-generating and pollution.
The technical scheme that the utility model is taked is as follows: a kind of back pressure type generating set, comprise generator, it is characterized in that: back pressure turbine is connected with generator by shaft coupling, and boiler links to each other with back pressure turbine, and the female pipe of heat supply links to each other with back pressure turbine.
The beneficial effects of the utility model are as follows: the utility model adopts the generating set of back pressure turbine, by with original C12-4.90/0.98 sucking condensing turbine body, condenser, vacuum system, circulation, the coagulation hydroenergy backwater system removes, keep master section, then in the concrete foundation of original steam turbine appropriate reconstruction in addition, form the generating set of novel 15MW back pressure turbine, the specified throttle flow of this type unit is 146t/h, the full admission amount is 171t/h, exhaust steam pressure 0.98MPa, 268 ℃ of exhaust temperatures, improve generating efficiency effectively, reduce cost of electricity-generating and pollution.
The utility model is described in further detail below in conjunction with the drawings and specific embodiments.
Description of drawings:
Fig. 1 is the structural representation of existing sucking condensing turbine generating set.
Fig. 2 is a structural representation of the present utility model.
Embodiment:
In conjunction with shown in Figure 2, a kind of back pressure type generating set of the present utility model, comprise generator 1, back pressure turbine 2 is connected with generator 1 by shaft coupling, boiler 4 links to each other with back pressure turbine 2 to supply with steam, the female pipe of heat supply 3 links to each other with back pressure turbine 2, and the steam that back pressure turbine 2 was done merit enters directly that heat supply is female manages 3, supplies with hot user.
Workflow of the present utility model is as follows: the steam that produces from boiler enters the back pressure turbine acting, and steam turbine high speed is rotated, and is connected with generator by positive coupling, drives generator and rotates generating, is connected to the grid; The steam that the back pressure machine was done merit directly enters the female pipe of heat supply, supplies with hot user.
The utility model becomes thermoelectric Co., Ltd to organize project reconstruction to implement in Shaoxing, obtains extraordinary economic benefit and social benefit:
1, energy-conservation situation after the project implementation;
Technology innovation project is all finished at the end of of 2008.9 months and is put into operation, and according to production report of forward and backward month of technological transformation, calculates actual energy-conservation situation after the technological transformation with product output in 2008.
Coal consumption is 340g/kWh according to production report 2007 annuals power supply mark, the mark coal consumption of on average powering 1~June in 2009 is 249g/kWh, amount of power supply was 28911.954 ten thousand kWh in 2008, but actual year feast-brand mark coal amount is after the technological transformation: 289119540* (340-249)/1000000=26310 ton
Go into stove coal low heating value 21495kJ/kg according to annual statistical average in 2008,704 yuan/ton of average of the whole year raw coal prices in 2008 are calculated and year can be increased profit and be: ten thousand yuan of 0.0704*26310* (7000*4.18)/21495=2521
According to production report water withdrawal in 2007 is 462.2 ten thousand tons, heating load is 9735015GJ, 1~June in 2009, water withdrawal was 192.7 ten thousand tons, heating load is 4268013GJ, heating load was 9759840GJ in 2008, and actual year can be economized on water and is after the technological transformation: (462.2/9735015-192.7/4268013) * 9759840=22.7 is ten thousand tons
By reality water intaking expense is 0.13 yuan/m 3Calculating year can be saved the water intaking expense:
227000*0.13=29510 unit.
2, the performance analysis after the project implementation;
Economic benefit is calculated per year, and amount of power supply is that 3.5 hundred million kWh calculate:
Because of heat supply coal consumption before and after the technological transformation differs very little, ignore temporarily, only consider the influence of net coal consumption rate, coal consumption was 345g/kWh according to 06,07 year annual statistical average power supply mark, and transforming the coal consumption of back power supply mark according to " the energy-conservation assessment report of one-tenth thermoelectric Co., Ltd improvement project in the Shaoxing " is can save mark coal amount 213.2g/kWh calculating year to be:
(345-213.2) * 3.5*10 8/ 1000000=46130 ton
Go into stove coal low heating value 21820kJ/kg according to annual statistical average in 06,07 year, the raw coal price can increase profit with 700 yuan of/ton calculating years and be:
46130*7000*4.18/21820*0.07=4330 ten thousand yuan
After the technological transformation, full factory quantity of circulating water greatly reduces, and a 12MW takes out with fixed attention that machine condenser water consumption is 1500t/h, but the circulating cooling make-up water rate is 1.5% to calculate a year water-saving amount and be:
1500*2*0.015*24*365=394200m 3
By reality water intaking expense is 0.13 yuan/m 3Calculating year can be saved the water intaking expense:
394200*0.13=51246 unit
Can maximumly increase heat capacity after the scrap build simultaneously is 182t/h, makes the maximum heat capacity of company can reach 550t/h, has alleviated the growing heat demand in industrial area, robe river greatly.

Claims (1)

1. a back pressure type generating set comprises generator, it is characterized in that: back pressure turbine is connected with generator by shaft coupling, and boiler links to each other with back pressure turbine, and the female pipe of heat supply links to each other with back pressure turbine.
CN2010202035854U 2010-05-22 2010-05-22 Back pressure generating set Expired - Fee Related CN201674346U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202035854U CN201674346U (en) 2010-05-22 2010-05-22 Back pressure generating set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202035854U CN201674346U (en) 2010-05-22 2010-05-22 Back pressure generating set

Publications (1)

Publication Number Publication Date
CN201674346U true CN201674346U (en) 2010-12-15

Family

ID=43331753

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202035854U Expired - Fee Related CN201674346U (en) 2010-05-22 2010-05-22 Back pressure generating set

Country Status (1)

Country Link
CN (1) CN201674346U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104856346A (en) * 2015-05-27 2015-08-26 上海霍雷加新材料科技有限公司 Efficient generating shoe capable of generating electricity

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104856346A (en) * 2015-05-27 2015-08-26 上海霍雷加新材料科技有限公司 Efficient generating shoe capable of generating electricity

Similar Documents

Publication Publication Date Title
CN111159624B (en) Method for calculating heat supply coal consumption rate of new steam and steam extraction combined heat supply unit
CN108036384A (en) A kind of energy source station system and operation method based on thermoelectricity unit steam extraction
CN201568948U (en) Hot water circulating device
CN110028988A (en) A kind of cogeneration cooling heating system of coupled biological matter gasification and compressed-air energy storage
CN113757762A (en) Solar energy composite energy storage heating system
CN203685320U (en) System for greatly reducing central heating temperature of heat and power cogeneration
CN203718884U (en) Heat-pump-based combined heat and power generation centralized heating system
CN202141033U (en) Generating system of absorption heat pump steam exhaust recovery steam turbine improving 1% of generating efficiency
CN201032221Y (en) Heating supply energy-saving system
CN201674346U (en) Back pressure generating set
CN201672815U (en) Device for heating waste heat generating condensation water by calcined-furnace water-jacket water
CN205156426U (en) Thermoelectric cold many cogeneration system of integrated thermochemical process
CN210088956U (en) Heating system based on optimization of circulating water flow and temperature difference of heat supply network
CN201574791U (en) Heat pump combined circulating system of small steam turbine
CN207740056U (en) A kind of CO2The machine furnace cooling of cycle can recycle and power generation and heat supply integral system
CN202747462U (en) Device for recovering waste circulating water heat of thermal power plant by using absorption heat pump
CN201138011Y (en) Renewable power source heating apparatus of cooling column recycled water at low position of thermal power plant and refrigeration enterprise
Fu et al. Photothermal-assisted scheme design and thermodynamic analysis of advanced adiabatic compressed air energy storage system
CN201836968U (en) Cogeneration energy saving device utilizing waste heat of indirect air cooling unit for heat supply
CN113091112B (en) Thermoelectric decoupling system with low back pressure cutting cylinder and compression heat pump combined
CN201611133U (en) Heating system for coke-oven plant region
CN103542445A (en) System for utilizing absorption heat pump to recycle waste heat of circulating water of thermal power plant
CN103438492A (en) Low-vacuum absorption-type composite heat pump residual heat supply system based on ultra-great-temperature-difference heat supply network
CN203533512U (en) Small-sized cogeneration device
CN201903273U (en) Waste heat generating set in production of cement

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101215

Termination date: 20140522