CN201671318U - Vertical tenon and cross mortise socket-fastening connecting scaffold - Google Patents

Vertical tenon and cross mortise socket-fastening connecting scaffold Download PDF

Info

Publication number
CN201671318U
CN201671318U CN2010201765775U CN201020176577U CN201671318U CN 201671318 U CN201671318 U CN 201671318U CN 2010201765775 U CN2010201765775 U CN 2010201765775U CN 201020176577 U CN201020176577 U CN 201020176577U CN 201671318 U CN201671318 U CN 201671318U
Authority
CN
China
Prior art keywords
socket joint
tenon
vertical rod
socket
projection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201765775U
Other languages
Chinese (zh)
Inventor
蔡雪峰
周继忠
郑莲琼
郑永乾
庄金平
聂小龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou Construction Engineering (Group) General Corporation
Fujian University of Technology
Original Assignee
Fujian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian University of Technology filed Critical Fujian University of Technology
Priority to CN2010201765775U priority Critical patent/CN201671318U/en
Application granted granted Critical
Publication of CN201671318U publication Critical patent/CN201671318U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model relates to a vertical tenon and cross mortise socket-fastening connecting scaffold which comprises cross bars and vertical poles, wherein grooves and lugs are uniformly arranged around the connecting parts of the vertical poles, one ends of the cross bars are provided with grooves which are matched and socketed with the lugs around the connecting parts of the vertical poles, the cross bars are connected with the lugs around the connecting parts of the vertical poles by the grooves at one ends of the cross bars, and clamp rings are sheathed above the connecting parts of the vertical poles. The vertical tenon and cross mortise socket-fastening connecting scaffold has simple structure and good overall stability, and can be disassembled and assembled quickly and used conveniently; the accessories thereof are not easy to lose; and the application cost is low; and compared with the traditional fastener type steel pipe scaffold, the bearing capacity of the vertical tenon and cross mortise socket-fastening connecting scaffold is greatly improved.

Description

The upright horizontal fourth of the twelve Earthly Branches of tenon socket joint buckle connects scaffold
Technical field
The utility model relates to the horizontal fourth of the twelve Earthly Branches of a kind of upright tenon socket joint buckle and connects scaffold.
Background technology
Use traditional fastener type steel pipe scaffold in the building site at present, but there are the following problems for it: (1) fastener (particularly screw rod) is lost easily more; (2) rod member at node place is eccentric the connection, and frictionally transmits load, thereby has reduced its supporting capacity; (3) influence of the quality of quality of connection fastener of fastener node own and workman operation is remarkable.
Summary of the invention
The utility model provides the horizontal fourth of the twelve Earthly Branches of a kind of upright tenon socket joint buckle to connect scaffold, it is simple in structure, resistance to overturning is good, dismounting is quick, easy to use, application cost is low, and the fastener that has solved traditional fastener type steel pipe scaffold existence is lost easily, supporting capacity is not high, the significant problem of influence of the quality of quality of connection fastener of fastener node own and workman's operation.
The horizontal fourth of the twelve Earthly Branches of a kind of upright tenon of the utility model socket joint buckle connects scaffold, comprise cross bar and vertical rod, the all sides of described vertical rod connecting portion are equipped with projection, one end of described cross bar be provided with can with the be complementary groove of socket joint of vertical rod connecting portion week side projection, described cross bar is connected with the projection socket joint of all sides of described vertical rod connecting portion by the groove of an end, and the top of described vertical rod connecting portion also is arranged with snap ring.
Advantage of the present utility model is: the tie point that this horizontal fourth of the twelve Earthly Branches of upright tenon socket joint buckle connects scaffold not only can effectively connect all rod members, and because the socket joint plug is to be packed in the vertical rod, each center line of the bar intersects at a bit, whole axially loadeds, no subsidiary stress, mechanical property is good, connects reliably the scaffold good integrity of composition.In addition, the tie point of this scaffold also has good strength and stiffness, vertical rod is connected with cross bar not and can causes vertical rod and being connected of other cross bar to go to pot because of the destruction that a cross bar wherein is connected with vertical rod, and with respect to tradition carrying fastener type steel pipe scaffold, its supporting capacity has had significantly raising; Because connection fittings of the present utility model are fixed on the bar, have avoided losing of accessory, have improved repeat usage, reduced use cost, and the connection reliability of rod member are reduced greatly by the probability of artificial on-site construction operations factor affecting.
Description of drawings
Fig. 1 the utility model schematic diagram;
The upright horizontal fourth of the twelve Earthly Branches of tenon of Fig. 2 socket joint buckle connects scaffold and connects preceding schematic diagram;
Fig. 3 tenon socket joint socket organigram;
Fig. 4 mortise joint schematic diagram;
Fig. 5 snap ring schematic diagram;
Fig. 6 snap ring vertical view.
The specific embodiment
The horizontal fourth of the twelve Earthly Branches of a kind of upright tenon of the utility model socket joint buckle connects scaffold, comprise cross bar and vertical rod, the all sides of described vertical rod connecting portion are equipped with projection, one end of described cross bar be provided with can with the be complementary groove of socket joint of vertical rod connecting portion week side projection, described cross bar is connected with the projection socket joint of all sides of described vertical rod connecting portion by the groove of an end, and the top of described vertical rod connecting portion also is arranged with snap ring.
The horizontal fourth of the twelve Earthly Branches of described a kind of upright tenon socket joint buckle connects scaffold, described vertical rod connecting portion week the projection of side be a trapezoidal projection, the groove of described cross bar one end be can with the be complementary inverted trapezoidal groove of socket joint of the trapezoidal projection of vertical rod connecting portion week side.
The horizontal fourth of the twelve Earthly Branches of described a kind of upright tenon socket joint buckle connects scaffold, and the inboard of described snap ring is provided with arc bump, and the outside of described snap ring is provided with the rectangle projection.
Be fixed with tenon socket joint socket in the described vertical rod, all sides of described tenon socket joint socket are provided with projection, and top is provided with grab.
Arc bump by the snap ring inboard is interlockingly connected with the grab on tenon socket joint socket top snap ring and tenon socket joint socket is linked closely mutually.
The projection that all sides of described vertical rod connecting portion are provided with is the projection on the tenon socket joint socket that is installed in the vertical rod.
Further specify the utility model below in conjunction with drawings and the specific embodiments.
The horizontal fourth of the twelve Earthly Branches of a kind of upright tenon socket joint buckle connects scaffold, comprises cross bar 1 and vertical rod 2, and the vertical rod connecting portion is fixed with tenon socket joint socket 4, and all sides of tenon socket joint socket are provided with trapezoidal projection 5, and top is provided with grab 6; The end of cross bar is welded with mortise joint 7, mortise joint 7 one sides are provided with and are packed in the be complementary inverted trapezoidal groove 8 of socket joint of socket joint socket on the vertical rod tenon, the inverted trapezoidal groove 8 of cross bar by end mortise joint 7 is connected with trapezoidal projection 5 socket joints of tenon socket joint socket 4 on being packed in vertical rod 1, the top of vertical rod connecting portion also is arranged with snap ring 3, the inboard of snap ring 3 is provided with arc bump 9, and the outside is provided with rectangle projection 10.
On the above basis that the utility model is specified, the making to it is described further below.
Earlier at cross bar 1 two ends of certain specification length welding mortise joint 7, and in vertical rod 2, install tenon socket joint socket 4(and can weld or be threaded), and above the tenon socket joint socket 4 of vertical rod 1, put snap ring 3, so that connect at the scene.When connecting at the scene, the snap ring 3 that will be placed in earlier in the vertical rod 1 is pulled upwardly (upwards sliding along vertical rod), the inverted trapezoidal groove 8 of the cross bar 1 end mortise joint 7 of all directions is aimed at the back socket joint with the trapezoidal projection 5 of tenon on the tenon socket joint socket 4, subsequently snap ring 3 is slided along vertical rod, and knock the outside rectangular projection 10 of snap ring 3 clockwise or counterclockwise with hammer, make the arc bump of the arc connecting section 9(snap ring inboard of snap ring inboard) be positioned at grab 6 belows on tenon socket joint socket 4 tops, so that snap ring 3 links closely mutually with tenon socket joint socket 4, reach the purpose that snap ring 3 is withheld the mortise joint 7 of cross bar 1.
Cross bar in the utility model adopts the tenon fourth of the twelve Earthly Branches to be connected with vertical rod, cross bar can not break away from vertical rod under horizontal force action, simultaneously, the tenon fourth of the twelve Earthly Branches is shaped as up-small and down-big, can guarantee that cross bar can bear load action straight down, and, then can withhold crossbar end by the snap ring in the vertical rod if cross bar is subjected to load action straight up, make cross bar can not come off.It is pointed out that snap ring is that the grab on arc connecting section by the inboard and tenon socket joint socket top links closely mutually and realizes that connecting portion is fixing.
The above only is preferred embodiment of the present utility model, and all equalizations of being done according to the utility model claim change and modify, and all should belong to covering scope of the present invention.

Claims (6)

1. the horizontal fourth of the twelve Earthly Branches of a upright tenon socket joint buckle connects scaffold, comprise cross bar and vertical rod, it is characterized in that: all sides of described vertical rod connecting portion are equipped with projection, one end of described cross bar be provided with can with the be complementary groove of socket joint of vertical rod connecting portion week side projection, described cross bar is connected with the projection socket joint of all sides of described vertical rod connecting portion by the groove of an end, and the top of described vertical rod connecting portion also is arranged with snap ring.
2. the horizontal fourth of the twelve Earthly Branches of a kind of upright tenon according to claim 1 socket joint buckle connects scaffold, it is characterized in that: described vertical rod connecting portion week the projection of side be a trapezoidal projection, the groove of described cross bar one end be can with the be complementary inverted trapezoidal groove of socket joint of the trapezoidal projection of vertical rod connecting portion week side.
3. the horizontal fourth of the twelve Earthly Branches of a kind of upright tenon according to claim 1 socket joint buckle connects scaffold, and it is characterized in that: the inboard of described snap ring is provided with arc bump, and the outside of described snap ring is provided with the rectangle projection.
4. the horizontal fourth of the twelve Earthly Branches of a kind of upright tenon according to claim 1 socket joint buckle connects scaffold, it is characterized in that: be fixed with tenon socket joint socket in the described vertical rod, all sides of described tenon socket joint socket are provided with projection, and top is provided with grab.
5. be connected scaffold according to claim 1,3 with the horizontal fourth of the twelve Earthly Branches of 4 described a kind of upright tenons socket joint buckle, it is characterized in that: the arc bump by the snap ring inboard is interlockingly connected with the grab on tenon socket joint socket top snap ring and tenon socket joint socket is linked closely mutually.
6. the horizontal fourth of the twelve Earthly Branches of a kind of upright tenon according to claim 4 socket joint buckle connects scaffold, it is characterized in that: described vertical rod connecting portion week side to be provided with projection be projection on the tenon socket joint socket that is installed in the vertical rod.
CN2010201765775U 2010-04-30 2010-04-30 Vertical tenon and cross mortise socket-fastening connecting scaffold Expired - Fee Related CN201671318U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201765775U CN201671318U (en) 2010-04-30 2010-04-30 Vertical tenon and cross mortise socket-fastening connecting scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201765775U CN201671318U (en) 2010-04-30 2010-04-30 Vertical tenon and cross mortise socket-fastening connecting scaffold

Publications (1)

Publication Number Publication Date
CN201671318U true CN201671318U (en) 2010-12-15

Family

ID=43328730

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201765775U Expired - Fee Related CN201671318U (en) 2010-04-30 2010-04-30 Vertical tenon and cross mortise socket-fastening connecting scaffold

Country Status (1)

Country Link
CN (1) CN201671318U (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103032551A (en) * 2011-10-05 2013-04-10 株式会社椿本链条 Change gear sprocket
CN103032552A (en) * 2011-10-05 2013-04-10 株式会社椿本链条 Change gear sprocket
CN103147567A (en) * 2013-03-21 2013-06-12 湖南金峰建达科技发展有限公司 Self-locking type scaffold fixing device
CN104358405A (en) * 2014-11-11 2015-02-18 天津大学 Heavy load full formwork support system
CN104389441A (en) * 2014-12-10 2015-03-04 云南大力神金属构件有限公司 Frame support system
CN105317207A (en) * 2014-07-18 2016-02-10 湖南金峰金属构件有限公司 Multi-angle adjustable scaffold steel tube and steel tube scaffold
CN105317208A (en) * 2014-07-18 2016-02-10 湖南金峰金属构件有限公司 Angle-adjustable socket and spigot type key groove type scaffold steel pipe
CN105625749A (en) * 2014-10-23 2016-06-01 湖南金峰金属构件有限公司 Steel pipe scaffold early-demounting component and device
CN105715038A (en) * 2014-08-11 2016-06-29 湖南金峰建达科技发展有限公司 Socket base special for pressure welding
CN105715037A (en) * 2014-08-16 2016-06-29 湖南金峰建达科技发展有限公司 Disc buckle for steel pipe scaffold
CN106013767A (en) * 2016-06-27 2016-10-12 浙江中南建设集团钢结构有限公司 Mortise joint bearing supporting frame
CN107514132A (en) * 2017-10-05 2017-12-26 杨靖 One kind is anti-to collapse de- plug
CN112343329A (en) * 2020-11-21 2021-02-09 张静 Construction frame
CN113651212A (en) * 2021-08-31 2021-11-16 浙江德为建材科技股份有限公司 People goods ladder protection platform

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103032552B (en) * 2011-10-05 2017-08-01 株式会社椿本链条 Change tooth sprocket
CN103032552A (en) * 2011-10-05 2013-04-10 株式会社椿本链条 Change gear sprocket
CN103032551A (en) * 2011-10-05 2013-04-10 株式会社椿本链条 Change gear sprocket
CN103147567A (en) * 2013-03-21 2013-06-12 湖南金峰建达科技发展有限公司 Self-locking type scaffold fixing device
CN105317207B (en) * 2014-07-18 2018-01-19 湖南金峰金属构件有限公司 A kind of multi-angle adjustable scaffold steel pipe and steel pipe scaffold
CN105317208B (en) * 2014-07-18 2018-01-19 湖南金峰金属构件有限公司 A kind of adjustable angle socket joint type key slot type scaffolding steel pipe
CN105317208A (en) * 2014-07-18 2016-02-10 湖南金峰金属构件有限公司 Angle-adjustable socket and spigot type key groove type scaffold steel pipe
CN105317207A (en) * 2014-07-18 2016-02-10 湖南金峰金属构件有限公司 Multi-angle adjustable scaffold steel tube and steel tube scaffold
CN105715038B (en) * 2014-08-11 2018-05-15 湖南金峰金属构件有限公司 A kind of socket joint type key slot type steel pipe support
CN105715038A (en) * 2014-08-11 2016-06-29 湖南金峰建达科技发展有限公司 Socket base special for pressure welding
CN105715037A (en) * 2014-08-16 2016-06-29 湖南金峰建达科技发展有限公司 Disc buckle for steel pipe scaffold
CN105625749B (en) * 2014-10-23 2018-01-19 湖南金峰金属构件有限公司 A kind of steel pipe scaffold early-dismantling device
CN105625749A (en) * 2014-10-23 2016-06-01 湖南金峰金属构件有限公司 Steel pipe scaffold early-demounting component and device
CN104358405B (en) * 2014-11-11 2016-08-24 天津大学 The full hall pattern board supporting system of a kind of heavy duty
CN104358405A (en) * 2014-11-11 2015-02-18 天津大学 Heavy load full formwork support system
CN104389441A (en) * 2014-12-10 2015-03-04 云南大力神金属构件有限公司 Frame support system
CN106013767A (en) * 2016-06-27 2016-10-12 浙江中南建设集团钢结构有限公司 Mortise joint bearing supporting frame
CN106013767B (en) * 2016-06-27 2019-05-14 浙江中南建设集团钢结构有限公司 A kind of joggle bearing supporting frame
CN107514132A (en) * 2017-10-05 2017-12-26 杨靖 One kind is anti-to collapse de- plug
CN112343329A (en) * 2020-11-21 2021-02-09 张静 Construction frame
CN113651212A (en) * 2021-08-31 2021-11-16 浙江德为建材科技股份有限公司 People goods ladder protection platform

Similar Documents

Publication Publication Date Title
CN201671318U (en) Vertical tenon and cross mortise socket-fastening connecting scaffold
CN201671391U (en) Light line repair tower
CN204850389U (en) Wedge draw -in groove formula steel pipe scaffold
CN201671319U (en) Anti-slipping scaffold
CN102444273B (en) Connecting member of socket and spigot type tenon-mortise self-locked steel pipe scaffold
CN201802058U (en) Novel insertion disk fastener scaffold
CN201671320U (en) Novel transverse-tenon vertical-mortise socket buckle type scaffold connecting mechanism
CN204401808U (en) Bolt-ball net frame assembly structure
CN201661066U (en) Scaffold connecting mechanism
CN202248845U (en) Socket and spigot joint type connecting piece for mortise and tenon joint self-locking steel tube scaffold
CN201687192U (en) Scaffold
CN202117307U (en) Steel pipe scaffold connected through dovetail tenon-mortises and screws or pins,
CN206992487U (en) A kind of modular breaker erection scaffolding
CN105463989A (en) Bridge plate frame manufacturing process
CN201943330U (en) Pin-on-disc type scaffold
CN205171684U (en) Connecting piece is used to precast concrete spare
CN201730308U (en) Novel scaffold
CN203603450U (en) Clamping slot type steel pipe scaffold
CN204163197U (en) The cross circumference steel pipe connected node of reinforcing ring is established in a kind of
CN208088514U (en) A kind of Membrane of Tensile Buildings strengthening of foundation device
CN201344356Y (en) Aluminium section component structure for movie devices
CN203487853U (en) Connecting component of multiple sections of conical concrete poles
CN209066993U (en) A kind of Combined type cement electric pole
CN201521034U (en) Light steel pipe net rack node member
CN202064816U (en) Folding type fixing device for herringbone ladders

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: FUZHOU CONSTRUCTION ENGINEERING (GROUP) COMPANY

Effective date: 20120328

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20120328

Address after: 350108 Department of civil engineering, Fujian University of Technology, 3 campus road, Minhou, Fuzhou, Fujian

Co-patentee after: Fuzhou Construction Engineering (Group) General Corporation

Patentee after: Fujian University of Technology

Address before: 350108 Department of civil engineering, Fujian University of Technology, 3 campus road, Minhou, Fuzhou, Fujian

Patentee before: Fujian University of Technology

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101215

Termination date: 20180430

CF01 Termination of patent right due to non-payment of annual fee