CN201667509U - Simple cable reel supporting and lifting device - Google Patents

Simple cable reel supporting and lifting device Download PDF

Info

Publication number
CN201667509U
CN201667509U CN2010201476239U CN201020147623U CN201667509U CN 201667509 U CN201667509 U CN 201667509U CN 2010201476239 U CN2010201476239 U CN 2010201476239U CN 201020147623 U CN201020147623 U CN 201020147623U CN 201667509 U CN201667509 U CN 201667509U
Authority
CN
China
Prior art keywords
bracket
bracing frame
steel
welded
shears
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201476239U
Other languages
Chinese (zh)
Inventor
李德家
张晓峰
毛杰
胡太松
罗培
冯佑波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN2010201476239U priority Critical patent/CN201667509U/en
Application granted granted Critical
Publication of CN201667509U publication Critical patent/CN201667509U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to the field of engineering machinery, in particular to a simple cable reel supporting and lifting device. The device comprises a lifting bracket and a supporting roller which are used in pairs, wherein the lifting bracket is arranged on the two sides of a cable reel; the supporting roller passes through a central hole of the cable reel and end frames at the two ends of the supporting roller are arranged on the lifting bracket; the lifting bracket comprises a pedestal, a supporting frame, an upper bracket, a lower bracket and a jack; the pedestal is placed on ground foundation and connected with the supporting frame; the upper bracket and the lower bracket are arranged on the supporting frame from top to bottom and can be firmly clamped on the supporting frame; and the jack is arranged between the upper bracket and the lower bracket. After the cable reel is supported by device, the cable reel can be lifted to get away from the ground for a certain space by only using the jack, so the use of a crane or the purchasing of a special rack can be prevented in favor of saving the construction cost; the device has a simple overall structure, is formed by combining and welding steel pipes and channel steel on the construction field and is convenient, fast, economical and practical.

Description

Simple type cable pan arrest rises device
Technical field
The utility model relates to a kind of electric engineering construction machinery, relates in particular to a kind of simple type holder that cable pan arrest liter is used for cable laying and rises device.
Background technology
In the electric equipment installing engineering, laying of cable is one of main task in the work progress.Be to guarantee construction quality, generally need set up cable hank to make things convenient for disk body to rotate during cable laying, avoid cable impaired or influence the attractive in appearance of cable laying because of torsion.At the scene in the practical application, usually take crane lifting, special-purpose stand, manually lift mode such as remove, these methods tend to be subjected to the restriction of field environmental condition, use crane or buy special-purpose stand from also being unfavorable for saving cost economically, and because a lot of cable hanks weigh more than 5 tons, it is more inadvisable manually to lift the mode of removing.Therefore be necessary that designing a kind of simple and easy portable cable pan arrest according to the electrical installation project field condition at the deficiencies in the prior art rises device.
Summary of the invention
The purpose of this utility model is that the simple type cable pan arrest that provides a kind of simple and practical, convenient holder to rise cable hank rises device.
To achieve these goals, the technical solution of the utility model is: a kind of simple type cable pan arrest rises device, its difference is: the shears and the backing roll that include paired use, shears is arranged on the cable hank both sides, backing roll passes the cable hank centre bore and two head ends are erected on the shears, shears comprises base, bracing frame, bracket, bottom bracket and jack, base is placed on the basis, ground, be connected with bracing frame on the base, bracing frame is installed on bracket and bottom bracket from top to bottom, bracket and bottom bracket can block the jail on bracing frame, between bracket and the bottom bracket jack are set.
Support frame as described above is made up of two steel pipes that be arranged in parallel, and the steel pipe bottom is welded on the described base, is drilled with a row location hole on the steel pipe at interval, inserts steel pin in the location hole with bracket and bottom bracket locator card jail.
Described bracket and bottom bracket are welded to form by middle cross-arm and sleeve pipe, and middle cross-arm is a channel-section steel, and channel-section steel two head ends are welded on the sidewall of sleeve pipe, and casing inner diameter is greater than the external diameter of bracing frame steel pipe.
Described bracket is connected with anti-inclined to one side groove, and anti-inclined to one side groove is an arc groove, and the backing roll head end is erected in the anti-inclined to one side groove.
Described base is that channel-section steel is welded into I shape.
Be welded with the reinforcement made from channel-section steel or angle steel between described base and the bracing frame.
After the utility model is held cable hank, only need to use jack just can rise cable hank and make its overhead certain interval, avoid using crane or buy special-purpose stand, help saving construction cost; Total is simple, the steel pipe of the job site of gathering materials on the spot, channel-section steel, and Combination Welding forms, and is convenient and swift, economical and practical.
Description of drawings
Fig. 1 is the graphics of single shears among the utility model embodiment;
The schematic diagram that Fig. 2 uses for the utility model embodiment;
Among the figure, the 1-base, the 2-bottom bracket, the 3-bracing frame, the 4-jack, the 5-bracket, 6-prevents inclined to one side groove, 7-backing roll, 8-location hole, 9-steel pin, 10-reinforcement, 11-cable hank.
Embodiment
In order to understand the utility model better, below in conjunction with embodiment and accompanying drawing the technical solution of the utility model is described further, referring to Fig. 1 and Fig. 2:
Rise device by a kind of simple type cable pan arrest of the invention process, the shears that includes backing roll 7 and use in pairs, shears is placed in cable hank 11 both sides respectively, the ground of shears below should be smooth, compacting, and both sides altitude basically identical is to have kept the center of gravity of cable hank 11 in the payout process, backing roll 7 is the steel pipe of a length greater than cable hank 11 thickness, during use backing roll 7 penetrated cable hank 11 centre bores, two head ends are erected on the shears, the height that has just begun shears is concordant with cable hank 11 centre bores height overhead, shears lifting cable hank 11 certain interval overhead for convenience, the scheme that present embodiment adopts is: shears comprises base 1, bracing frame 3, bracket 5, bottom bracket 2 and jack 4, base 1 is placed on the basis, ground, base 1 is for to be welded into I-shaped structure with channel-section steel, its material generally can be a redundance channel-section steel of taking from field fabrication dish cabinet base, be welded into " worker " font in case lateral tilt, be connected with bracing frame 3 on the base 1, be welded with the reinforcement made from channel-section steel or angle steel 10 between base 1 and the bracing frame 3, be used to strengthen the intensity of bracing frame 3.Bracing frame 3 utilizes two steel pipe manufacturings, steel pipe be arranged in parallel, the bottom is welded on the base 1, the steel pipe of bracing frame 3 is installed on bracket 5 and bottom bracket 2 from top to bottom, bracket 5 and bottom bracket 2 are welded to form by middle cross-arm and sleeve pipe, middle cross-arm is a channel-section steel, channel-section steel two head ends are welded on the sidewall of sleeve pipe, casing inner diameter is slightly larger than the external diameter of bracing frame 3 steel pipes, the location of bracket 5 and bottom bracket 2 then relies on location hole 8 and steel pin 9 to fix, symmetry is drilled with location hole 8 on bracing frame 3 steel pipes, when bracket 5 and bottom bracket 2 positions need to be determined fixedly, only needs steel pin 9 insertion corresponding hole site are got final product.Backing roll 7 is erected on the bracket 5, when backing roll 7 rolls deflection takes place in order to prevent that cable hank 11 from driving, and is connected with anti-inclined to one side groove 6 on the cross-arm of bracket 5, and anti-inclined to one side groove 6 is an arc groove.For weigh 5 tons cable hank 11 of lifting, between bracket 5 and bottom bracket 2, be provided with jack 4, jack 4 is the common tools in the electrical installation project, its type selecting should consider that bearing capacity is greater than half of cable hank 11 total weights, in addition for bracket 5 and bottom bracket 2 position that falls is good, the pitch-row of bracing frame 3 steel pipes be jack 4 2/3 stroke apart from about.
Use step of the present utility model is:
(1) ground of shears below is smooth, compacting, shears is placed on cable hank 11 both sides, and backing roll 7 penetrates cable hank 11 central hole locations;
(2) respectively the bracket 5 of both sides shears is risen to 7 liang of head end positions of backing roll, utilize steel pin 9 to insert corresponding aperture position on bracing frames 3 steel pipes, last shears is carried out highly fixing;
(3) equally respectively bottom bracket 2 is utilized steel pin 9 highly to locate, bottom bracket 2 is advisable can place hydraulic jack 4 with bracket 5 spacings;
(4) two hydraulic jack 4 are placed on respectively two the cover bottom brackets 2 the center;
(5) both sides simultaneous operation hydraulic jack 4 arrives proper height with cable hank 11 jackings;
(6) utilize 9 pairs of bracket of steel pin 5 to carry out the height location;
(7) remove two hydraulic jack 4, can carry out the operation of cable hank 11 cable layings.
Above disclosed only is preferred embodiment of the present utility model, can not limit the interest field of the utility model certainly with this, and therefore the equivalence of being done according to the utility model claim changes, and still belongs to protection range of the present utility model.

Claims (6)

1. a simple type cable pan arrest rises device, it is characterized in that: the shears and the backing roll (7) that include paired use, shears is arranged on cable hank (11) both sides, backing roll (7) passes cable hank (11) centre bore and two head ends are erected on the shears, shears comprises base (1), bracing frame (3), bracket (5), bottom bracket (2) and jack (4), base (1) is placed on the basis, ground, be connected with bracing frame (3) on the base (1), bracing frame (3) is installed on bracket (5) and bottom bracket (2) from top to bottom, bracket (5) and bottom bracket (2) can block the jail on bracing frame (3), between bracket (5) and the bottom bracket (2) jack (4) are set.
2. simple type cable pan arrest according to claim 1 rises device, it is characterized in that: support frame as described above (3) is made up of two steel pipes that be arranged in parallel, the steel pipe bottom is welded on the described base (1), be drilled with a row location hole (8) on the steel pipe at interval, insert steel pin (9) in the location hole (8) bracket (5) and bottom bracket (2) locator card jail.
3. simple type cable pan arrest according to claim 2 rises device, it is characterized in that: described bracket (5) and bottom bracket (2) are welded to form by middle cross-arm and sleeve pipe, middle cross-arm is a channel-section steel, channel-section steel two head ends are welded on the sidewall of sleeve pipe, and casing inner diameter is greater than the external diameter of bracing frame (3) steel pipe.
4. simple type cable pan arrest according to claim 1 rises device, it is characterized in that: described bracket (5) is connected with anti-inclined to one side groove (6), and anti-inclined to one side groove (6) is an arc groove, and backing roll (7) head end is erected in the anti-inclined to one side groove (6).
5. simple type cable pan arrest according to claim 1 rises device, it is characterized in that: described base (1) is welded into I shape for channel-section steel.
6. simple type cable pan arrest according to claim 1 rises device, it is characterized in that: be welded with the reinforcement made from channel-section steel or angle steel (10) between described base (1) and the bracing frame (3).
CN2010201476239U 2010-03-30 2010-03-30 Simple cable reel supporting and lifting device Expired - Fee Related CN201667509U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201476239U CN201667509U (en) 2010-03-30 2010-03-30 Simple cable reel supporting and lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201476239U CN201667509U (en) 2010-03-30 2010-03-30 Simple cable reel supporting and lifting device

Publications (1)

Publication Number Publication Date
CN201667509U true CN201667509U (en) 2010-12-08

Family

ID=43268470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201476239U Expired - Fee Related CN201667509U (en) 2010-03-30 2010-03-30 Simple cable reel supporting and lifting device

Country Status (1)

Country Link
CN (1) CN201667509U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104682269A (en) * 2014-11-26 2015-06-03 武汉一冶建筑安装工程有限责任公司 Cable laying device
CN107387869A (en) * 2017-08-14 2017-11-24 新奥新能源工程技术有限公司 Indoor standpipe electronic elevator gear and the method using device installation gas pipeline

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104682269A (en) * 2014-11-26 2015-06-03 武汉一冶建筑安装工程有限责任公司 Cable laying device
CN107387869A (en) * 2017-08-14 2017-11-24 新奥新能源工程技术有限公司 Indoor standpipe electronic elevator gear and the method using device installation gas pipeline

Similar Documents

Publication Publication Date Title
CN101789570B (en) Methods for manufacturing and using cable-laying tool for cable coil in construction site
CN103730231B (en) A kind of head cover of transformer lowering or hoisting gear
CN201667509U (en) Simple cable reel supporting and lifting device
CN201914762U (en) Portable payoff bracket for cable unwinding shaft
CN109921572B (en) Penetrating method of compact rolling bearing structure motor
CN208631793U (en) A kind of cable unwinding device
CN206466801U (en) A kind of lift cable unreeling rack
CN202107373U (en) Cable and steel wire rope roller support device
CN201946914U (en) Seat frame used for supporting cable reel to be lifted up
CN212832000U (en) Large-scale cable pay-off rack
CN104882267B (en) Method for adding angle ring to transformer coil assembly
CN201823758U (en) Mechanical type vertical roll bearing box dismounting platform
CN102641919A (en) Cylinder bracket for crimping
CN204847572U (en) Support frame that cable laying used
CN204225459U (en) A kind of building site bracing frame
CN203746609U (en) Transformer top cover lifting device
CN102390755A (en) Cable and steel wire rope roller supporting device
CN204919565U (en) Steel platform of use is demolishd in shoring of trench
CN205603185U (en) Large -scale box turnover device
CN201261707Y (en) Jack fixer for adjusting workshop concrete column installation accuracy
CN204568999U (en) Cable loading tray winding apparatus
CN203599234U (en) Pneumatic jacking part for winding and unwinding
CN102797348A (en) Front-support suspension mechanism for parapet walls
CN218145568U (en) Pipe fitting installation lifting devices
CN211775584U (en) Height-adjustable's scaffold frame

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant