CN201649139U - Cast-in-place pile loading test inner force testing device - Google Patents

Cast-in-place pile loading test inner force testing device Download PDF

Info

Publication number
CN201649139U
CN201649139U CN2010201886549U CN201020188654U CN201649139U CN 201649139 U CN201649139 U CN 201649139U CN 2010201886549 U CN2010201886549 U CN 2010201886549U CN 201020188654 U CN201020188654 U CN 201020188654U CN 201649139 U CN201649139 U CN 201649139U
Authority
CN
China
Prior art keywords
test
pile
survey
pipe
adjacent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201886549U
Other languages
Chinese (zh)
Inventor
张炜
刘争宏
张继文
郑建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA JK INSTITUTE OF ENGINEERING INVESTIGATION AND DESIGN
Original Assignee
CHINA JK INSTITUTE OF ENGINEERING INVESTIGATION AND DESIGN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA JK INSTITUTE OF ENGINEERING INVESTIGATION AND DESIGN filed Critical CHINA JK INSTITUTE OF ENGINEERING INVESTIGATION AND DESIGN
Priority to CN2010201886549U priority Critical patent/CN201649139U/en
Application granted granted Critical
Publication of CN201649139U publication Critical patent/CN201649139U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a cast-in-place pile loading test inner force testing device, comprising two test pipes pre-embedded in the test pile longitudinally and symmetrically and extending out of the head of the test pile, the test pipe is formed by connecting a plurality of test pipe units, a test ring is arranged at the connection point of two adjacent test pipe units, a strain measuring probe sliding along the test pipe is arranged between two adjacent test rings. a strong all-purpose adhesive is coated at the joint of two adjacent test pipe units, a PVC electric flame-retardant adhesive tape and a high-voltage insulated self-adhesive tape are wound at the seam of two adjacent test pipe units. the change of the distance between two adjacent test rings on the test pipe embedded in the test pile is tested by the strain test probe to obtain the strain of the concrete between two test rings, then the pile side resistance and end resistance are calculated through the obtained strain according to the elastic theory. The cast-in-place pile loading test inner force testing device has simple structure, a large number of data acquisition and high reliability, is not easy to be destroyed, and is easy to be popularized.

Description

Drill-pouring pile loading test internal force testing arrangement
Technical field
The utility model relates to a kind of drill-pouring pile loading test internal force testing arrangement.
Background technology
At present, in new building thing, new construction of structures, bored pile is the base form of using always, can make Pile Foundations Design safety, economy, rationally according to the internal force test result.The internal force test of bored pile, normally adopt reinforcing bar meter method, promptly in pile body, bury reinforcing bar underground by soil depth, the concrete strain of stressed further calculating by the test result calculations reinforcing bar, obtain the size of collateral resistance and end resistance again, therefore, reinforcing bar meter method is a kind of indirect strain testing method.Have in the pile concrete filling process and to damage cable easily and test less than data, working environment and demarcation environment and inconsistently cause test error, bury negligible amounts underground and complete distribution, the calculating parameter that can not react collateral resistance such as is difficult for accurately determining at shortcoming.
The utility model content
The purpose of this utility model is to overcome above-mentioned deficiency of the prior art, and a kind of drill-pouring pile loading test internal force testing arrangement is provided.By strain testing probe test be embedded on the survey pipe in the test pile pile body adjacent two survey ring spacings from variation can draw two and survey the strains that the interannular concrete take place, calculate pile side resistance and end resistance by the strain that records by elastic theory again, it is simple in structure, easy to use, certainty of measurement is high.
For achieving the above object, the technical solution adopted in the utility model is: drill-pouring pile loading test internal force testing arrangement, comprise that vertical symmetry is embedded in the test pile pile body and two of pile crown that stretch out test pile survey pipe, described survey pipe is surveyed pipe unit by several and is formed by connecting, be provided with a survey ring in described adjacent two junctions of surveying pipe unit, being provided with at adjacent two survey interannulars can be along the strain testing probe of surveying the pipe slip.
Aforesaid drill-pouring pile loading test internal force testing arrangement, the length of described survey pipe unit is 1m.
Above-mentioned drill-pouring pile loading test internal force testing arrangement evenly is coated with strength universal glue in described adjacent two joints of surveying pipe unit, twines electric non-flammable adhesive tape of PVC and High-Voltage Insulation self-adhesive tape at described adjacent two seam crossings of surveying pipe unit.
The utility model compared with prior art has the following advantages: vertically two of symmetric arrangement are surveyed pipe in the test pile pile body, by strain testing probe test be embedded on the survey pipe in the test pile pile body adjacent two survey ring spacings from variation can draw two and survey the strains that the interannular concrete take place, calculate pile side resistance and end resistance by the strain that records by elastic theory again.Simultaneously, in surveying pipe, have one and survey ring, therefore can utilize the strain testing probe directly to measure the variation relation of strain continuous in the pile body with the degree of depth every 1m.It is big to the utlity model has the data acquisition amount, and the characteristics that the strain testing precision is high are surveyed pipe and had higher intensity, when concrete perfusion, be difficult for destroyed, good reliability.And survey being symmetrical arranged of pipes for two, the strain testing result is averaged to eliminate load eccentric influence, it is simple in structure, easy to use, be convenient to promote the use of.
Below by drawings and Examples, the technical solution of the utility model is described in further detail.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Fig. 2 surveys the structural representation of pipe for the utility model.
Fig. 3 is adjacent two structural representations of surveying the pipe unit junction of the utility model.
Fig. 4 is a connection diagram of surveying pipe and reinforcing cage when implementing the utility model.
The position of the concrete surface that pours in clear water that Fig. 5 injects in surveying pipe when being enforcement the utility model and the test pile concerns schematic diagram.
Description of reference numerals:
The 1-test pile; 2-surveys pipe; 3-surveys ring; 4-strain testing probe; The 5-pile crown;
The 6-foundation soil; 7-strength universal glue; Electric non-flammable adhesive tape of 8-PVC and High-Voltage Insulation self-adhesive tape;
The 9-reinforcing cage; The 10-clear water; The 11-concrete surface; 12-surveys pipe unit.
The specific embodiment
A kind of drill-pouring pile loading test internal force testing arrangement as shown in Figure 1, comprise that vertical symmetry is embedded in test pile 1 pile body and two of pile crown 5 that stretch out test pile 1 survey pipe 2, described test pile 1 is embedded in the foundation soil 6, and test pile 1 stretches out foundation soil 6, the end of test pile 1 is a pile crown 5, described survey pipe 2 is surveyed pipe unit 12 by several and is formed by connecting, and the length of described survey pipe unit 12 can be 1m.Be provided with a survey ring 3 in described adjacent two junctions of surveying pipe unit 12, as shown in Figure 2, survey 3 on ring at adjacent two and be provided with and manage the 2 strain testing probes 4 that slide along surveying.As shown in Figure 3, evenly be coated with strength universal glue 7, twine electric non-flammable adhesive tape of PVC and High-Voltage Insulation self-adhesive tape 8 at described adjacent two seam crossings of surveying pipe unit 12 in described adjacent two joints of surveying pipe unit 12.
The operating principle of the utility model drill-pouring pile loading test internal force testing arrangement is: when test, concrete generation strain in test pile 1 pile body, also can drive the survey ring of surveying in the pipe 23 micro-displacement takes place, the variation of measuring 3 distances of two survey rings can draw two and survey the strain that the interannular concrete takes place.During the internal force test, strain testing probe 4 is put into survey pipe 2, block two adjacent surveys and encircle the tension of 3 lower ends, can obtain the strain measurement value, slip strain testing probe 4 in surveying pipe 2 can record the change curve of strain continuous in the test pile 1 with the degree of depth continuously.Two strain values that same depth is recorded average the mean strain that promptly obtains this degree of depth place, calculate pile side resistance and end resistance by the strain that records by elastic theory again.
As shown in Figure 3, survey the precision that pipe 2 quality of burying quality underground directly have influence on test, need to guarantee to survey pipe 2 free from admixtures, not contaminated, cement paste enters and surveys pipe 2 when especially being strictly on guard against concrete spouting.Connect when surveying pipe unit 12, evenly smear strength universal glue 7, twine three circle electric non-flammable adhesive tapes of PVC and three circle High-Voltage Insulation self-adhesive tapes 8 at adjacent two seam crossings of surveying pipe unit 12 in adjacent two joints of surveying pipe unit 12; Behind the stake pore-forming, transfer in the process at reinforcing cage 9, as shown in Figure 4, will survey pipe 2 symmetrical colligations on reinforcing cage 9; Before concrete perfusion, as shown in Figure 5, in surveying pipe 2, fill with clear water 10, guarantee to survey pipe 2 interior head height greater than concrete surface 11 height.
The above; it only is preferred embodiment of the present utility model; be not that the utility model is imposed any restrictions; every according to the utility model technical spirit to any simple modification, change and equivalent structure transformation that above embodiment did, all still belong in the protection domain of technical solutions of the utility model.

Claims (3)

1. drill-pouring pile loading test internal force testing arrangement, it is characterized in that: comprise that vertical symmetry is embedded in test pile (1) pile body and two of pile crown (5) that stretch out test pile (1) survey pipe (2), described survey pipe (2) is surveyed pipe unit (12) by several and is formed by connecting, be provided with a survey in the junctions of described adjacent two survey pipe units (12) and encircle (3), survey at adjacent two and be provided with the strain testing probe (4) that to manage (2) slip along survey between ring (3).
2. drill-pouring pile loading test internal force testing arrangement according to claim 1, it is characterized in that: the length of described survey pipe unit (12) is 1m.
3. drill-pouring pile loading test internal force testing arrangement according to claim 1 and 2, it is characterized in that: evenly be coated with strength universal glue (7) in described adjacent two joints of surveying pipe unit (12), twine electric non-flammable adhesive tape of PVC and High-Voltage Insulation self-adhesive tape (8) at described adjacent two seam crossings of surveying pipe unit (12).
CN2010201886549U 2010-05-13 2010-05-13 Cast-in-place pile loading test inner force testing device Expired - Fee Related CN201649139U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201886549U CN201649139U (en) 2010-05-13 2010-05-13 Cast-in-place pile loading test inner force testing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201886549U CN201649139U (en) 2010-05-13 2010-05-13 Cast-in-place pile loading test inner force testing device

Publications (1)

Publication Number Publication Date
CN201649139U true CN201649139U (en) 2010-11-24

Family

ID=43114367

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201886549U Expired - Fee Related CN201649139U (en) 2010-05-13 2010-05-13 Cast-in-place pile loading test inner force testing device

Country Status (1)

Country Link
CN (1) CN201649139U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195112A (en) * 2013-04-18 2013-07-10 四川建筑职业技术学院 Foundation pile foundation model analyzing method and test device for same
CN103234680A (en) * 2012-12-18 2013-08-07 徐州睿丰企业管理咨询有限公司 Method for measuring stress of steel bar in well wall of inclined shaft
CN109372037A (en) * 2018-12-15 2019-02-22 机械工业勘察设计研究院有限公司 Deposited reinforced concrete pile internal force test test tube and its installation method
CN112924275A (en) * 2021-01-25 2021-06-08 武汉大学 Micro-force measuring device, preparation method thereof and in-situ mechanical testing method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103234680A (en) * 2012-12-18 2013-08-07 徐州睿丰企业管理咨询有限公司 Method for measuring stress of steel bar in well wall of inclined shaft
CN103234680B (en) * 2012-12-18 2015-03-04 朱昱 Method for measuring stress of steel bar in well wall of inclined shaft
CN103195112A (en) * 2013-04-18 2013-07-10 四川建筑职业技术学院 Foundation pile foundation model analyzing method and test device for same
CN103195112B (en) * 2013-04-18 2014-10-08 四川建筑职业技术学院 Foundation pile foundation model analyzing method and test device for same
CN109372037A (en) * 2018-12-15 2019-02-22 机械工业勘察设计研究院有限公司 Deposited reinforced concrete pile internal force test test tube and its installation method
CN112924275A (en) * 2021-01-25 2021-06-08 武汉大学 Micro-force measuring device, preparation method thereof and in-situ mechanical testing method

Similar Documents

Publication Publication Date Title
CN104452726B (en) Profundal zone soil body deep soil settlement survey device and method
CN201094020Y (en) Settlement plate and assembled laminate settlement apparatus
CN103215974B (en) Foundation pile deflection measurement method based on distributed fiber sensing technique
CN103321201B (en) Sealed liquid pressure reduction delaminating deposition takes into account that it is buried underground, measuring method
CN106706029B (en) Soil body performance monitoring device for underground structure construction and working method thereof
CN103953025A (en) Equipment for measuring layered settlement of deep soft soil or blanket and setup method thereof
CN102943493B (en) Method for measuring internal force and deformation of precast pile
CN201649139U (en) Cast-in-place pile loading test inner force testing device
CN103215975B (en) Inbuilt method for distributed type sensing cable in foundation pile
CN102635129B (en) Method for detecting steel reinforcement cage pre-buried under cast-in-place pile
CN104406568A (en) Device and method for monitoring settlement of ground surface in deep water area
CN103644892A (en) Measuring device and method for layered settlement of soil body of deep foundation pit
CN108844684A (en) A method of monitoring diaphram wall seam crossing leakage scenarios
CN103471648A (en) Disturbance construction monitoring method of top pipe tunnel
CN102839693A (en) Anchor quality monitoring device for increased resistance deformation anchor bolts/ropes and application method
CN204418149U (en) Profundal zone soil body deep soil settlement survey device
CN202548085U (en) Detection device for burial depth of dam cut-off wall
CN208254458U (en) Soft base deepwater diking settlement monitoring device
CN204214437U (en) Profundal zone surface subsidence monitoring device
CN102797268B (en) Installation method for testing tube used for testing internal force of pre-stress tubular pile with slide micrometer
CN103410136A (en) Drilling burying method of soil moisture meter
CN105971031A (en) Magnetic-induction-based pile length detection device for tubular pile construction and detection method
CN205502092U (en) Testing arrangement of bored concrete pile burden frictional resistance neutral point in deep back filling
CN102519427B (en) Method for observing settlement of full section of widened roadbed
CN103410181B (en) Burying-before-guiding type step-by-step burying method for monitoring instruments in synchronous construction with loess high fill

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101124

Termination date: 20130513