CN201569609U - Cast iron pipe hydraulic testing machine - Google Patents
Cast iron pipe hydraulic testing machine Download PDFInfo
- Publication number
- CN201569609U CN201569609U CN2009202662078U CN200920266207U CN201569609U CN 201569609 U CN201569609 U CN 201569609U CN 2009202662078 U CN2009202662078 U CN 2009202662078U CN 200920266207 U CN200920266207 U CN 200920266207U CN 201569609 U CN201569609 U CN 201569609U
- Authority
- CN
- China
- Prior art keywords
- barricade
- bellmouth
- pull bar
- testing machine
- retaining wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
Abstract
The utility model disclose a cast iron pipe hydraulic testing machine which comprises a bellmouth retaining wall, a jack retaining wall, a main oil cylinder, and a plurality of tension rods used for connecting the bellmouth retaining wall and the jack retaining wall; each tension rod is respectively provided with an outer side nut and an outer side lock nut on the outer side of the bellmouth retaining wall and the outer side of the jack retaining wall; and each tension rod is respectively provided with an inner side nut and an inner side lock nut on the inner side of the bellmouth retaining wall and the inner side of the jack retaining wall. After the technical scheme is adopted, the retaining wall and the tension rods of the cast iron pipe hydraulic testing machine are pre-tensioned and installed so that the tension rods and the retaining walls form an organic whole, thereby shortening the deformation distance of the tension rods, reducing the alternating stress amplitude of the tension rods of the hydraulic testing machine and improving the stress status of the tension rods, so as to greatly improve the safety and the reliability of a system, effectively prolong the service life of the tension rods, and improve the service life of the complete hydraulic testing machine.
Description
Technical field
The utility model belongs to the technical field of metallurgical industry production equipment, relates to the production technology equipment of ductile iron pipe, and more particularly, the utility model relates to a kind of cast-iron pipe hydrostatic testing machine.
Background technology
Ductile iron pipe is the tubing that adopts centrifugal casting technique to produce, have good mechanical performance, save characteristics such as metal, easy construction, cost economic, reliability height, corrosion resistance and good, long service life, be widely used in pipework such as water supply, fire-fighting, blowdown, gas transmission.In recent years, along with the raising of people to the product cognitive ability, all be greatly improved with point and consumption, the output of centrifugal ductile cast iron pipes obtains swift and violent development, and national output was continuously above 2,000,000 tons in nearly 3 years.
The cast tube hydrostatic testing machine is the visual plant of check ductile iron pipe mechanical property on the ductile iron pipe finishing line.Pipe for different size will carry out other hydraulic pressure withstand voltage test of different pressures level, the barricade of water pressure engine bears bigger thrust, this thrust finally also will pass on the pull bar, therefore the stressed maximum of pull bar of water pressure engine reaches more than the 1000T, pull bar is under the bigger fatigue stress effect of amplitude, pull bar ruptures easily, can not reach expected life.
The utility model content
First problem to be solved in the utility model provides a kind of cast-iron pipe hydrostatic testing machine and pull bar pretension installation method thereof, its objective is by the hydrostatic testing machine pull bar is carried out pretension, make pull bar and barricade become organic whole, reduce water pressure engine pull bar alterante stress amplitude, improve hydrostatic testing machine pull bar force-bearing situation.
To achieve these goals, the technical scheme taked of the utility model is:
Cast-iron pipe hydrostatic testing machine provided by the utility model, comprise bellmouth barricade, socket barricade, master cylinder and connect a plurality of pull bars of described bellmouth barricade and socket barricade, on described pull bar, be positioned at bellmouth barricade and the socket barricade outside, establish outboard nut and outside locknut respectively, on described pull bar, be positioned at bellmouth barricade and socket barricade inboard, establish inboard nut and inboard locknut respectively.
It is stifled that bellmouth frock end is established in the inboard of described bellmouth barricade, establishes pipe die at described bellmouth frock end between the stifled and socket barricade.
Described pull bar is that coaxial multistage divides body structure, connects by the attaching nut between mutually, or connects by welded structure.
Second problem to be solved in the utility model provides above-described cast-iron pipe hydrostatic testing machine and adopts pull bar pretension installation method, and its goal of the invention is identical with technique scheme.Described pull bar pretension installation method may further comprise the steps:
Pretension is installed and is prepared: install hydrostatic testing machine body equipment, comprise base, described bellmouth barricade, socket barricade, master cylinder and hydraulic system etc.; Pretension frock part is installed, is comprised that socket frock end is stifled, bellmouth frock end is stifled, pipe die;
Test technology calculation of parameter: calculate the tensile elongation of described pull bar under the maximum weighted state; Calculate the maximum pressure that hydraulic system can provide; Calculate the maximum working pressure (MWP) that master cylinder will provide;
Pretension is installed: pre-install described pull bar, adjust the position of the inboard nut at pull bar two ends respectively, make bellmouth barricade and the socket barricade surplus that adjusting is axially arranged at pull bar; Adjust bellmouth barricade and socket barricade spacing, the inboard nut and the outboard nut of bellmouth barricade and socket barricade both sides is threaded to the precalculated position; Then the outside locknut at pull bar two ends is locked; The inboard nut of pretension barricade makes to be adjacent to the barricade sleeve pipe; Hydraulic system pressure is adjusted low-pressure state, improve hydraulic system pressure then gradually, and reach scheduled pressure value; The inboard nut of fastening two barricades, and respectively with inboard locknut locking.
The utility model adopts technique scheme, carrying out pretension by the barricade pull bar to the cast-iron pipe hydrostatic testing machine installs, make pull bar and barricade become an organic whole, shortened the pull bar deformation distance, reduce the alterante stress amplitude of hydrostatic testing machine pull bar, improve the pull bar force-bearing situation, thereby improved the security and the reliability of system greatly, effectively prolong pull bar serviceable life, improve the machine life of hydrostatic testing machine.
Description of drawings
Below expressed content of the accompanying drawing of this instructions and the mark among the figure are made brief description:
Fig. 1 is a structural representation of the present utility model.
Be labeled as among the figure:
1, master cylinder, 2, the bellmouth barricade, 3, bellmouth frock end is stifled, 4, pipe die, 5, pull bar, 6, inboard locknut, 7, inboard nut, 8, the socket barricade, 9, outboard nut, 10, outside locknut.
Embodiment
Contrast accompanying drawing below, by description to embodiment, to effect and principle of work, the manufacturing process of the mutual alignment between the shape of embodiment of the present utility model such as related each member, structure, the each several part and annexation, each several part and manipulate method etc., be described in further detail, inventive concept of the present utility model, technical scheme had more complete, accurate and deep understanding to help those skilled in the art.
As the expressed structure of the present utility model of Fig. 1 is a kind of cast-iron pipe hydrostatic testing machine and pull bar pretension installation method thereof, comprise bellmouth barricade 2, socket barricade 8, master cylinder 1 and connect a plurality of pull bars 5 of described bellmouth barricade 2 and socket barricade 8, on described pull bar 5, be positioned at the bellmouth barricade 2 and socket barricade 8 outsides, establish outboard nut 9 and outside locknut 10 respectively.
Hydraulic system provides the power source that makes master cylinder 1 produce thrust, and the thrust that hydraulic cylinder produces can normally to carry out bulge test pressure suitable with the cast carbon steel water pressure engine.
In order to solve the defective that the described prior art of this instructions background technology part exists, realization reduces water pressure engine pull bar alterante stress amplitude, improves the goal of the invention of hydrostatic testing machine pull bar force-bearing situation, and the utility model has been taked following technical scheme and corresponding embodiment:
One, the improvement of Tiebar structure:
Cast-iron pipe hydrostatic testing machine described in the utility model is positioned at bellmouth barricade 2 and socket barricade 8 inboards on pull bar 5, establish inboard nut 6 and inboard locknut 7 respectively.
The main thought of described water pressure engine pretension installation method is to effectively reduce the stressed strain amplitude of pull bar, applies a prestress.
The utility model carries out pretension by the barricade pull bar to the cast-iron pipe hydrostatic testing machine and installs, make pull bar 5 and barricade become an organic whole, shortened the pull bar deformation distance, reduce the alterante stress amplitude of hydrostatic testing machine pull bar, improve the pull bar force-bearing situation, thereby improved the security and the reliability of system greatly, and effectively prolong pull bar serviceable life, improve the machine life of hydrostatic testing machine.
It is to rely on to apply tension in advance pull bar 5 that described pull bar 5 strain amplitudes reduce.
Described prestressed maintenance relies on inboard locknut 6 and outside locknut 10 on the barricade pull bar 5 to carry out fastening enforcement function.
Dependence is carried out pretension to cast tube water pressure engine pull bar and is installed, pull bar 5 is produced answer pulling force in advance, so that when ductile iron pipe is carried out bulge test, pull bar 5 is influenced by alterante stress no longer, thereby improved the force-bearing situation of bellmouth barricade 2 and socket barricade 8 part pull bars, the serviceable life of having improved pull bar 5.
Two, the test unit of cast-iron pipe hydrostatic testing machine:
The inboard of bellmouth barricade 2 described in the utility model is established bellmouth frock end and is blocked up 3, establishes pipe die 4 between described bellmouth frock end stifled 3 and socket barricade 8.
Give the barricade applied thrust by means of equipments such as water pressure engine apparatus body bellmouth barricade 2, socket barricade 8, master cylinder 1, pipe die 4, bellmouth frock end stifled 3 and hydraulic systems, make pull bar produce prestress.
Three, the one-piece construction of pull bar:
Pull bar described in the utility model 5 divides body structure for coaxial multistage, connects by the attaching nut between mutually, or connects by welded structure.
Said structure has reduced the manufacture difficulty of pull bar 5.
Four, the cast-iron pipe hydrostatic testing machine adopts pull bar pretension installation method:
Problem to be solved in the utility model provides a kind of cast tube water pressure engine pretension installation method, its objective is the water pressure engine pull bar is carried out fastening installation, make pull bar and barricade become organic whole, reduce water pressure engine pull bar alterante stress amplitude, improve water pressure engine pull bar force-bearing situation, effectively prolong pull bar serviceable life, improve the water pressure engine service life of equipment.
This cast tube water pressure engine pretension installation method provided by the utility model: be divided into three phases, promptly pretension is installed the preparatory stage; Parameter calculation phase; The pretension installation phase.
In sum: install by cast tube water pressure engine barricade pull bar being carried out pretension, make barricade become an integral body with pull bar.Shorten the pull bar deformation distance, reduced the strain amplitude of pull bar, thereby improved the security and the reliability of system greatly, improved the life-span of equipment.
Five, pull bar pretension installation method described in the utility model may further comprise the steps:.
1, pretension is installed and is prepared: install hydrostatic testing machine body equipment, comprise base, described bellmouth barricade 2, socket barricade 8, master cylinder 1 and hydraulic system etc.; Pretension frock part is installed, is comprised that socket frock end is stifled, bellmouth frock end is stifled 3, pipe die 4.
At pretension be installed the preparatory stage: install water pressure engine body equipment, comprise base, socket barricade, bellmouth barricade, master cylinder, hydraulic system etc.; Pretension frock part is installed, is comprised that socket frock end is stifled, bellmouth frock end is stifled, pipe die etc.
2, test technology calculation of parameter: calculate the tensile elongation of described pull bar 5 under the maximum weighted state; Calculate the maximum pressure that hydraulic system can provide; Calculate the maximum working pressure (MWP) that master cylinder 1 will provide.
In parameter calculation phase: calculate the tensile elongation of pull bar under the maximum weighted state; Calculate the maximum pressure that hydraulic system can provide; Calculate the maximum pressure that master cylinder will provide.
3, pretension is installed: pre-install described pull bar 5, adjust the position of the inboard nut 7 at pull bar 5 two ends respectively, make bellmouth barricade 2 and the surplus that adjusting axially arranged of socket barricade 8 at pull bar 5; Adjust bellmouth barricade 2 and socket barricade 8 spacings, the inboard nut 7 and the outboard nut 9 of bellmouth barricade 2 and socket barricade 8 both sides is threaded to the precalculated position; Then the outside locknut 10 at pull bar two ends is locked; The inboard nut 7 of pretension barricade makes to be adjacent to the barricade sleeve pipe; Hydraulic system pressure is adjusted low-pressure state, improve hydraulic system pressure then gradually, and reach scheduled pressure value; The inboard nut 7 of fastening two barricades, and respectively with inboard locknut 6 lockings.
At the pretension installation phase: the prepackage pull bar, adjust pull bar two end nuts to the precomputation position, adjust bell and spigot barricade spacing, the pull-rod nut of socket barricade and bellmouth barricade both sides is fixed to the precalculated position then the locknut at pull bar two ends is locked; , the inboard nut of pretension barricade, make to be adjacent to the barricade sleeve pipe; Hydraulic system pressure is adjusted low-pressure state, improve hydraulic system pressure then gradually, and reach scheduled pressure value; Confine the inboard nut of barricade, and lock with locknut.
In conjunction with the accompanying drawings the utility model has been carried out exemplary description above; obviously the utility model specific implementation is not subjected to the restriction of aforesaid way; as long as adopted the improvement of the various unsubstantialities that method of the present utility model design and technical scheme carry out; or design of the present utility model and technical scheme are directly applied to other occasion without improving, all within protection domain of the present utility model.
Claims (3)
1. cast-iron pipe hydrostatic testing machine, comprise bellmouth barricade (2), socket barricade (8), master cylinder (1) and connect described bellmouth barricade (2) and a plurality of pull bars (5) of socket barricade (8), on described pull bar (5), be positioned at the bellmouth barricade (2) and socket barricade (8) outside, establish outboard nut (9) and outside locknut (10) respectively, it is characterized in that: on described pull bar (5), be positioned at bellmouth barricade (2) and socket barricade (8) inboard, establish inboard nut (6) and inboard locknut (7) respectively.
2. according to the described cast-iron pipe hydrostatic testing machine of claim 1, it is characterized in that: bellmouth frock end stifled (3) is established in the inboard of described bellmouth barricade (2), establishes pipe die (4) between described bellmouth frock end stifled (3) and socket barricade (8).
3. according to the described cast-iron pipe hydrostatic testing machine of claim 2, it is characterized in that: described pull bar (5) divides body structure for coaxial multistage, connects by the attaching nut between mutually, or connects by welded structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009202662078U CN201569609U (en) | 2009-11-12 | 2009-11-12 | Cast iron pipe hydraulic testing machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009202662078U CN201569609U (en) | 2009-11-12 | 2009-11-12 | Cast iron pipe hydraulic testing machine |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201569609U true CN201569609U (en) | 2010-09-01 |
Family
ID=42661903
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009202662078U Expired - Lifetime CN201569609U (en) | 2009-11-12 | 2009-11-12 | Cast iron pipe hydraulic testing machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201569609U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101738344B (en) * | 2009-11-12 | 2011-04-20 | 芜湖新兴铸管有限责任公司 | Hydraulic pressure tester for cast-iron pipe and method for pretightening and mounting pull rods thereof |
CN102095641A (en) * | 2010-12-01 | 2011-06-15 | 新兴河北工程技术有限公司 | Frame-type hydraulic pressure testing machine for large-diameter pipe fittings |
CN103278394A (en) * | 2013-05-28 | 2013-09-04 | 新兴河北工程技术有限公司 | Comprehensive test device for joint sealing and hydraulic circulating of pipe body |
CN104655368A (en) * | 2015-02-25 | 2015-05-27 | 托普工业(江苏)有限公司 | Novel pressure test device for furnace tubes |
CN110542607A (en) * | 2019-10-17 | 2019-12-06 | 无锡市创新低温环模设备科技有限公司 | Bellows pressure test frock |
CN111451577A (en) * | 2020-04-08 | 2020-07-28 | 河北新兴铸管有限公司 | Auxiliary device for chamfering operation of nodular cast iron pipe and using method thereof |
-
2009
- 2009-11-12 CN CN2009202662078U patent/CN201569609U/en not_active Expired - Lifetime
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101738344B (en) * | 2009-11-12 | 2011-04-20 | 芜湖新兴铸管有限责任公司 | Hydraulic pressure tester for cast-iron pipe and method for pretightening and mounting pull rods thereof |
CN102095641A (en) * | 2010-12-01 | 2011-06-15 | 新兴河北工程技术有限公司 | Frame-type hydraulic pressure testing machine for large-diameter pipe fittings |
CN103278394A (en) * | 2013-05-28 | 2013-09-04 | 新兴河北工程技术有限公司 | Comprehensive test device for joint sealing and hydraulic circulating of pipe body |
CN104655368A (en) * | 2015-02-25 | 2015-05-27 | 托普工业(江苏)有限公司 | Novel pressure test device for furnace tubes |
CN110542607A (en) * | 2019-10-17 | 2019-12-06 | 无锡市创新低温环模设备科技有限公司 | Bellows pressure test frock |
CN111451577A (en) * | 2020-04-08 | 2020-07-28 | 河北新兴铸管有限公司 | Auxiliary device for chamfering operation of nodular cast iron pipe and using method thereof |
CN111451577B (en) * | 2020-04-08 | 2021-11-30 | 河北新兴铸管有限公司 | Auxiliary device for chamfering operation of nodular cast iron pipe and using method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101738344B (en) | Hydraulic pressure tester for cast-iron pipe and method for pretightening and mounting pull rods thereof | |
CN201569609U (en) | Cast iron pipe hydraulic testing machine | |
CN202402815U (en) | Split mounting type concrete lined metal corrugated pipe | |
CN107559543B (en) | Bearing structure, support, joint assembly and pipe joint assembly | |
CN104440758B (en) | Portable pressure device and application thereof in interference fit part disassembly | |
CN101788422A (en) | Main oil cylinder support bracket and pressing device for cast-iron pipe hydrostatic testing machine | |
CN104440766B (en) | A kind of disassembling fixture of interference bolt and method | |
CN103241683B (en) | Under a kind of ocean pipeline balance weight production line, the rail mounted of pipe lifts pipe device | |
CN202644620U (en) | Self-dismounting apparatus of excavator counterweight | |
CN102530693A (en) | Rope-binding prevention device for quickly changing head rope of mine hoist | |
CN209820937U (en) | Shield tunnel bolted joint tensile property test device | |
CN210050404U (en) | Pressure-resistant stainless steel single-wall corrugated pipe | |
CN209781866U (en) | Special multi-functional fixed pipe strap of ocean hydraulic pressure pipeline | |
CN111549686A (en) | Stay cable positioner and bridge stay cable replacing method | |
CN203843463U (en) | Thrust bearing oil cooler disassembling tool for water turbine generator set | |
CN102019550B (en) | A heavy-duty pin shaft opening device | |
CN215717539U (en) | Unearthed ramp steel sheet pile reinforcing support | |
CN104097182A (en) | Companion flange tightener | |
CN204279419U (en) | Monkey car preventing wire rope from falling rope device | |
CN2589597Y (en) | Prefabricated aramid fiber reinforced tube concrete component | |
CN217296988U (en) | Crane matrix type bearing, pulling, embedding and load balancing structure | |
CN216038173U (en) | Steel pipe hoisting accessory | |
CN212536939U (en) | Spring limiting device for steam pipeline of power plant | |
CN220007645U (en) | Overhauling and dismounting device for sleeve telescopic joint | |
CN219082588U (en) | Pipeline protection driving operation platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20100901 Effective date of abandoning: 20091112 |