CN201560517U CN2009202671448U CN200920267144U CN201560517U CN 201560517 U CN201560517 U CN 201560517U CN 2009202671448 U CN2009202671448 U CN 2009202671448U CN 200920267144 U CN200920267144 U CN 200920267144U CN 201560517 U CN201560517 U CN 201560517U
Authority
CN
China
Prior art keywords
junction plate
unit junction
hanging beam
horizontal plane
horizontal part
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009202671448U
Other languages
Chinese (zh)
Inventor
沈强
王丽芳
李京正
何进军
王友根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU HEPA CLEAN ENVIRONMENT ENGINEERING Co Ltd
Original Assignee
SUZHOU HEPA CLEAN ENVIRONMENT ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU HEPA CLEAN ENVIRONMENT ENGINEERING Co Ltd filed Critical SUZHOU HEPA CLEAN ENVIRONMENT ENGINEERING Co Ltd
Priority to CN2009202671448U priority Critical patent/CN201560517U/en
Application granted granted Critical
Publication of CN201560517U publication Critical patent/CN201560517U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a ceiling connecting structure of a cleaning room, which comprises a plurality of unit connecting plates, hanging beams extending transversely and tooth rods, wherein a male connecting port is arranged on one side end surface of each unit connecting plate; a first female connecting port is arranged on one side end surface of each unit connecting plate corresponding to the male connecting port; second female connecting ports are arranged on two side end surfaces on the unit connecting plate adjacent to the male connecting port; the male connecting ports of the unit connecting plates are matched and connected with the first female connecting ports of adjacent unit connecting plates along the transverse direction; the unit connecting plates are corresponding to the second female connecting ports of the unit connecting plates adjacent along the vertical direction to form an inserting space; the hanging beams are inserted in the inserting space; each hanging beam is provided with a first level part extending along the level and a rib part connected with the first level part; the first level parts are tightly applied to the upper side of the upper level; the rib parts extend outside the upper level; and the tooth rods are connected with the rid parts.

Description

A kind of ceiling connecting structure of toilet
Technical field
The utility model relates to a kind of ceiling connecting structure that is used for the building ceiling, especially for the ceiling connecting structure of toilet.
Background technology
In the prior art, industries such as semiconductor, photoelectron, medicine are owing to the elaborate of processing technology, and strict to the requirement of dirt degree in the processing environment, the whole production workshop is all built in the toilet.Shown in accompanying drawing 1 to 3, toilet's ceiling framework structure in the past is by the unit junction plate, middle font material, compositions such as T type hanging beam and connection tooth bar, female connector is all offered in four side end faces of unit junction plate, middle font material slightly is shorter than the spacing of T type hanging beam, middle font material is inserted in the female connector of two laterally adjacent unit junction plates, and T type hanging beam is between the female connector of two vertically adjacent row unit junction plates, when construction, at first will arrange T type hanging beam installs and fixes more, font material and unit junction plate in installing piecewise then, the horizontal part load of T type hanging beam is below the unit junction plate, the upper horizontal plane of unit junction plate is fixed on the flank of T type hanging beam by connecting corner fittings, and the flank of T type hanging beam then is connected and fixed by orchid screw and hex bolts etc. with the tooth bar of top.The shortcoming of this structure is: on the one hand, the horizontal part of T type hanging beam is exposed to the outside of the soffit of unit junction plate, not only locates the accumulation dust easily in the slit but also influence attractive in appearance; On the other hand, the cost of font material and T type hanging beam is higher in the use simultaneously.
Summary of the invention
The purpose of this utility model is to overcome deficiency of the prior art, and a kind of cost not only attractive in appearance but also cheap ceiling connecting structure are provided.
The technical scheme that the utility model adopted is: a kind of ceiling connecting structure of toilet, it comprises polylith unit junction plate, hanging beam along horizontal expansion, be used for described hanging beam is fixed on tooth bar on the ceiling of building, described unit junction plate has upper horizontal plane, lower horizontal plane, four side end faces that are connected described upper horizontal plane and lower horizontal plane, has male connector on the side end face of described unit junction plate, offer the first female connector on the side end face relative on the described unit junction plate with described male connector, offer the second female connector on two side end faces adjacent on the described unit junction plate with described male connector, the male connector of described unit junction plate matches with its first female connector along laterally adjacent unit junction plate and is connected, the relative formation of the second female connector of the unit junction plate that described unit junction plate is longitudinally adjacent with it inserts the space, described hanging beam is arranged in the described insertion space, described hanging beam has along first horizontal part of horizontal plane extension and the flank that links to each other with described horizontal part, described first horizontal part is adjacent to below described upper horizontal plane, described flank stretches out beyond the described upper horizontal plane, and described tooth bar is connected with described flank.
The utility model further technical scheme is: a pair of convergence part that described hanging beam also has second horizontal part that is parallel to described first horizontal part and connects described first horizontal part and second horizontal part, described first horizontal part, second horizontal part, a pair of convergence part surround the square shape structure.
Preferably, the slit between the lower horizontal plane of two adjacent described unit junction plates is filled with silica gel sealing.
Preferably, riveted joint mutually between the upper horizontal plane of first horizontal part and described unit junction plate.
Preferably, it includes the described hanging beam of multiple row, and each is listed as in the described hanging beam and is fixedly connected between same row's two adjacent hanging beams.
Preferably, described unit junction plate is the rock wool color steel.
The mounting method of described ceiling connecting structure comprises the steps:
A, determine hoisting point position, and at each hoisting point position place fixing tooth bar;
B, on the tooth bar much more fixing row's hanging beams, the side of multi-disc unit junction plate from hanging beam penetrated, the first female connector of unit junction plate is cooperated with closely pegging graft with the male connector of arranging adjacent unit junction plate;
C, finish after the installation of all unit junction plates established angle material around ceiling connecting structure.
The utility model has the advantages that: laterally be fixedly connected between the unit of the present utility model junction plate, many row's hanging beams link together each row unit junction plate and directly are fixed on the ceiling of building, building unit and difficulty of construction have not only been reduced, hanging beam is realized totally enclosed hiding design simultaneously, also make the furred ceiling of whole toilet become a smooth integral body, more attractive in appearance.
Description of drawings
Accompanying drawing 1 is the stereogram of ceiling connecting structure of the prior art;
Accompanying drawing 2 is along the sectional view of A-A in the accompanying drawing 1;
Accompanying drawing 3 is along the sectional view of B-B in the accompanying drawing 1;
Accompanying drawing 4 is the stereogram of ceiling connecting structure in the utility model;
Accompanying drawing 5 is the stereogram of the unit junction plate in the utility model;
Accompanying drawing 6 is the sectional view of hanging beam of the present utility model;
Accompanying drawing 7 is the first female connector of the unit junction plate in the utility model and the schematic diagram that cooperates of male connector;
Accompanying drawing 8 is the second female connector of the adjacent unit junction plate of two in the utility model and the connection diagram of hanging beam;
Wherein: 1, unit junction plate; 11, upper horizontal plane; 12, lower horizontal plane; 14, side end face; 15, the first female connector; 16, male connector; 17, the second female connector;
2, hanging beam; 21, first horizontal part; 22, second horizontal part; 23, convergence part; 24, flank;
3, tooth bar; 31, interior expansion tube; 32, horizontal adjustment frame; 34, rivet; 35, hex bolts;
4, T type hanging beam; 5, middle font material; 6, connect corner fittings; 7, tapping screw.
The specific embodiment
Referring to accompanying drawing 4 to shown in the accompanying drawing 8, a kind of ceiling connecting structure of toilet, it comprises polylith unit junction plate 1, along the hanging beam 2 of horizontal expansion, be used for described hanging beam 2 is fixed on tooth bar 3 on the ceiling of building, left and right direction in the accompanying drawing 4 be described in this manual laterally, horizontal plane is interior to be vertical perpendicular to horizontal direction, calling delegation, the polylith unit junction plate 1 of longitudinally arranging is called row along the polylith unit junction plate 1 of laterally arranging.
As shown in Figure 7, described unit junction plate 1 has upper horizontal plane 11, lower horizontal plane 12, four side end faces 14 that are connected described upper horizontal plane 11 and lower horizontal plane 12, has male connector 16 on the side end face of described unit junction plate 1, offer the first female connector 15 on the side end face 14 relative with described male connector 16, offer the second female connector 17 on two side end faces 14 adjacent with described male connector 16, wherein, this hero connector 16 is outwards to be protruded by the part of side end face 14 to form, and the first female connector and the second female connector then are that the part by side end face 14 caves inward and forms.
The male connector 16 that is positioned at the described unit junction plate 1 of each row matches with its first female connector 15 along laterally adjacent unit junction plate 1 and is connected; And between row and the row, the space is inserted in the second female connector 17 relative formation of the unit junction plate 1 that described unit junction plate 1 is longitudinally adjacent with it, and described hanging beam 2 is arranged in the described insertion space.
Shown in accompanying drawing 8, described hanging beam 2 has first horizontal part 21, second horizontal part 22 that is parallel to described first horizontal part 21, described first horizontal part 21 of connection and a pair of convergence part 23 of second horizontal part 22 and the flank 24 that links to each other with described horizontal part 21 that extends along horizontal plane, and described first horizontal part 21, second horizontal part 22, a pair of convergence part 23 surround the square shape structure.Wherein, described first horizontal part 21 is positioned at the below of described upper horizontal plane 11, and fixedlys connected the weight of first horizontal part, 21 support unit junction plates 1 by rivet between the upper horizontal plane 11 of first horizontal part 21 and described unit junction plate 1; And a pair of convergence part 23 contacts with the sandwich layer of the unit junction plate 1 of both sides respectively.The flank 24 of described hanging beam 2 stretches out beyond the described upper horizontal plane 21, and described tooth bar 3 is connected by horizontal adjustment frame 32 and hex bolts 35 etc. with described flank 24.Hanging beam 2 adopts the braced structures of square shapes that good rigidity is arranged, and material cost is lower simultaneously, and to be positioned at the part of a pair of second this connector 17 can also be I-shaped to this hanging beam or W shape structure or the like in other embodiment of the present utility model.
After installing, place, the slit silica gel sealing between the lower horizontal plane of two adjacent described unit junction plates 1.
The mounting method of ceiling connecting structure of the present utility model comprises the steps:
A, determine hoisting point position, and at each hoisting point position place fixing tooth bar, according to the construction width and the length of building, select the unit junction plate of suitable dimension and determine the length of hanging beam;
B, on the tooth bar much more fixing row's hanging beams, the side of multi-disc unit junction plate from hanging beam penetrated, the first female connector of unit junction plate is cooperated with closely pegging graft with the male connector of arranging adjacent unit junction plate;
Usually, if the construction length overall is less, the general choosing of the length of hanging beam then is slightly less than construction length, just gets final product along hanging beam of horizontally set; But if the construction length overall is longer, just need the described hanging beam of multiple row be set at the building ceiling, each is listed as in the described hanging beam and is fixedly connected by connector between same row's two adjacent hanging beams, erection sequence is: a row hanging beam is installed earlier, penetrate unit board, and then fix another row hanging beam, the end that is positioned at two hanging beams of same row in the two row hanging beams is fixed, penetrate row's unit board again, all install until the furred ceiling of whole construction length;
C, finish after the installation of all unit junction plates established angle material around ceiling connecting structure.

Claims (6)

1. the ceiling connecting structure of a toilet, it is characterized in that: it comprises polylith unit junction plate, many rows hanging beam along horizontal expansion, be used for described hanging beam is fixed on tooth bar on the ceiling of building, described unit junction plate has upper horizontal plane, lower horizontal plane, four side end faces that are connected described upper horizontal plane and lower horizontal plane, has male connector on the side end face of described unit junction plate, offer the first female connector on the side end face relative on the described unit junction plate with described male connector, offer the second female connector on two side end faces adjacent on the described unit junction plate with described male connector, the male connector of described unit junction plate matches with its first female connector along laterally adjacent unit junction plate and is connected, the second female connector of the unit junction plate that described unit junction plate and its are longitudinally adjacent connects to form and inserts the space, described hanging beam is arranged in the described insertion space, described hanging beam has along first horizontal part of horizontal plane extension and the flank that links to each other with described horizontal part, described first horizontal part is adjacent to below described upper horizontal plane, described flank stretches out beyond the described upper horizontal plane, and described tooth bar is connected with described flank.
2. the ceiling connecting structure of a kind of toilet according to claim 1, it is characterized in that: a pair of convergence part that described hanging beam also has second horizontal part that is parallel to described first horizontal part and connects described first horizontal part and second horizontal part, described first horizontal part, second horizontal part, a pair of convergence part surround the square shape structure.
3. the ceiling connecting structure of a kind of toilet according to claim 1, it is characterized in that: the slit between the lower horizontal plane of two adjacent described unit junction plates is filled with silica gel sealing.
4. the ceiling connecting structure of a kind of toilet according to claim 1 is characterized in that: riveted joint mutually between the upper horizontal plane of described first horizontal part and described unit junction plate.
5. the ceiling connecting structure of a kind of toilet according to claim 1, it is characterized in that: it includes the described hanging beam of multiple row, and each is listed as in the described hanging beam and is fixedly connected between same row's two adjacent hanging beams.
6. the ceiling connecting structure of a kind of toilet according to claim 1, it is characterized in that: described unit junction plate is the rock wool color steel.
CN2009202671448U 2009-11-16 2009-11-16 Ceiling connecting structure of cleaning room Expired - Lifetime CN201560517U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009202671448U CN201560517U (en) 2009-11-16 2009-11-16 Ceiling connecting structure of cleaning room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009202671448U CN201560517U (en) 2009-11-16 2009-11-16 Ceiling connecting structure of cleaning room

Publications (1)

Publication Number Publication Date
CN201560517U true CN201560517U (en) 2010-08-25

Family

ID=42625664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009202671448U Expired - Lifetime CN201560517U (en) 2009-11-16 2009-11-16 Ceiling connecting structure of cleaning room

Country Status (1)

Country Link
CN (1) CN201560517U (en)

Similar Documents

Publication Publication Date Title
CN101718130B (en) Ceiling connecting structure for clean room and mounting method thereof
KR100847877B1 (en) Cable tray having fixing device for elastically supporting cables
CN109208486B (en) Embedding and repairing segmented manufacturing process between steel bridge roof plates
CN101881059B (en) Folding fan-shaped hyperboloidal unit-type building curtain wall system and a construction method thereof
CN203583744U (en) Suspended ceiling structure
CN103748295A (en) Modular system for sub-cealing
CN111648498A (en) Combined partition light steel keel
KR101223458B1 (en) Coupling structure of partions
CN103649431B (en) Has crutched wall insulation system
CN201560517U (en) Ceiling connecting structure of cleaning room
CN111593836A (en) Combined light steel keel wall module and mounting method thereof
CN214575024U (en) Prefabricated roof structure
KR200446887Y1 (en) Combining structure of a cable tray
CN212534671U (en) Combined partition light steel keel
KR101195308B1 (en) Assembly type wall frame and zenith frame for house construction using said wall frame
KR101835423B1 (en) Ceiling frame for clean room
CN212534668U (en) Combined light steel keel wall module
KR20120107365A (en) Method for installing alc panel to concrete slab
KR20170057557A (en) Ceiling frame for clean room
CN108797868A (en) Top mounts curtain wall system assembled by small units
CN203347026U (en) Fixed connection structure of precast slabs
CN213539408U (en) Curtain wall mounting structure
CN109680914B (en) Aluminum alloy walkway between inner curtain wall and outer curtain wall
CN208965849U (en) Fast leveling GRG plate moulding ceiling mounting structure
CN209907780U (en) Connecting and decorating device for new wall building body

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20100825