CN201546875U - Water fetching system of flow channel cover plate of bulb tubular turbine generator - Google Patents

Water fetching system of flow channel cover plate of bulb tubular turbine generator Download PDF

Info

Publication number
CN201546875U
CN201546875U CN200920237984XU CN200920237984U CN201546875U CN 201546875 U CN201546875 U CN 201546875U CN 200920237984X U CN200920237984X U CN 200920237984XU CN 200920237984 U CN200920237984 U CN 200920237984U CN 201546875 U CN201546875 U CN 201546875U
Authority
CN
China
Prior art keywords
water
cover plate
flow passage
flow channel
channel cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200920237984XU
Other languages
Chinese (zh)
Inventor
钟新友
颜志刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hongyuan Zhongli Generation Equipment Co., Ltd.
Original Assignee
Shaoguan Zhongli Generating Equipment Co Ltd Guangdong Mingzhu Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaoguan Zhongli Generating Equipment Co Ltd Guangdong Mingzhu Group filed Critical Shaoguan Zhongli Generating Equipment Co Ltd Guangdong Mingzhu Group
Priority to CN200920237984XU priority Critical patent/CN201546875U/en
Application granted granted Critical
Publication of CN201546875U publication Critical patent/CN201546875U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Hydraulic Turbines (AREA)

Abstract

The utility model relates to a water fetching system of a flow channel cover plate of a bulb tubular turbine generator, which comprises a water through channel on which the flow channel cover plate is arranged. A water fetching opening is arranged on the flow channel cover plate and communicated with a water filter tank on the flow channel cover plate by a pipe. A water inlet is arranged at the other side of the water filter tank and sequentially communicated with a water pump, a check valve, a butterfly valve I, a filter and a generator set cooling system by pipes. The flow channel cover plate is arranged on the water through channel. The water fetching opening is arranged on the flow channel cover plate. Water enters the generator set cooling system for cooling. Finally, cooled water after undergoing heat exchange is discharged into the flow channel to achieve the circulation of cooled water. The apparatus is arranged collectively. The pipes are short and do not need to be pre-buried. Assembly and disassembly and daily maintenance of a power station are convenient. The operation reliability of a generator set is improved. Automatic washing of part of the pipes can also be achieved so that a turbine generator set can operate well.

Description

Scaled bulb tubular hydraulic generator flow passage cover plate water intake system
[technical field]
The utility model belongs to the power generating equipment technical field, relate to a kind of adopt the equipment centralized arrangement concentrate water-supply method, from the scaled bulb tubular hydraulic generator flow passage cover plate water intake system of generator flow passage cover plate water intaking.
[background technique]
The water-supply method of existing water power plant cooling water mainly contains two kinds: a kind of is to fetch water from the water power plant upper pond, pressurize by water pump, water purifier filtration, entering generator set through pre-buried water pipe cools off, this water-supply method major defect is that pipeline length and major part are embedded in the concrete, long operational time, pipeline can stop up to some extent, and pipe resistance increases and bad elimination; Another kind is that cooling water recycles, " water-water " cooler by external river course cools off circulating water, pressurize by water pump then, entering generator set through pre-buried water pipe cools off, this mode major defect is that " water-water " cooler is covered by aquatic organism easily, and the radiating effect variation needs often to remove aquatic organism, especially at southern area, be exactly to need often to replenish purified water in addition to cooling system.
[model utility content]
In order to overcome the above-mentioned shortcoming of prior art, the utility model provides a kind of equipment centralized arrangement, pipeline to need not pre-buried, as to install and remove conveniently, maintain easily power station day-to-day operation, can also realize the scaled bulb tubular hydraulic generator flow passage cover plate water intake system to the automatic washing capacity of section of tubing.
The technological scheme that its technical problem that solves the utility model adopts is: a kind of scaled bulb tubular hydraulic generator flow passage cover plate water intake system, water flow passage was arranged, be furnished with flow passage cover plate on the water flow passage excessively, flow passage cover plate is provided with intake, intake links by the water filtering tank on pipeline and the flow passage cover plate, opposite side at water filtering tank is provided with water intake, and this water intake links with water pump, safety check, butterfly valve one, water filter and generator set cooling system successively by pipeline.
Described generator set cooling system links with the mistake water flow passage by pipeline and butterfly valve two.
Be furnished with pressure switch and differential pressure transmitter in described pipe-line system.
The beneficial effects of the utility model are: flow passage cover plate was arranged on the water flow passage, on flow passage cover plate, be provided with intake, by arranging that two standby each other water pumps on it pressurize, then through arranging two standby each other water filters on it, entering the generator set cooling system cools off, cooling water through heat exchange enters runner at last, has realized that cooling water comes circulation where wherefrom.Whole tubing is furnished with pressure switch and differential pressure transmitter, when intake or line clogging cause resistance excessive, pressure switch and differential pressure transmitter signal, and make up by valve and water pump to system, just can realize intake and section of tubing are carried out backwash.Equipment centralized arrangement, the day-to-day operation that pipeline is short and it is pre-buried to need not, mounting or dismounting make things convenient for the power station are safeguarded, have improved the unit operation reliability, can also realize the automatic washing capacity to section of tubing, and the hydraulic generator unit is well moved.
[description of drawings]
Fig. 1 is a structural representation of the present utility model;
Among the figure: 1-intake, 2-water intake, 3-butterfly valve one, 4-safety check, 5-water pump, 6-water filter, 7-butterfly valve two, 8-water filtering tank, 9-cross water flow passage, 10-flow passage cover plate, 11-pipeline, 12-differential pressure transmitter, 13-pressure switch.
[embodiment]
Below in conjunction with drawings and Examples the utility model is further specified:
Referring to Fig. 1, a kind of scaled bulb tubular hydraulic generator flow passage cover plate water intake system, be furnished with flow passage cover plate 10 on the water flow passage 9 excessively, flow passage cover plate 10 is provided with intake 1, this intake 1 is the starting point of whole system, water filtering tank 8 companies of linking on this intake 1 and the flow passage cover plate 10, water filtering tank 8 plays the effect of preliminary filtration, after the cooling water after preliminary the filtration is by water pump 5 pressurizations, by pipeline 11 by safety check 4, butterfly valve 1 enters water filter 6, the cooling water that is come out by water filter 6 can satisfy the cooling requirement of generator set cooling system substantially, enter the generator set cooling system from pipeline 11 then and cool off, after entered water flow passage 9 by pipeline and butterfly valve 27 after the heat exchange; Wherein fetch water, cooling and drainage path be followed successively by: the water filtering tank 8 of the water of crossing 9 li of water flow passage to the flow passage cover plate 10, again after water pump 5 pressurizations, pass through safety check 4, butterfly valve 1, water filter 6 more successively to the generator set cooling system, enter runner through the cooling water after the heat exchange by butterfly valve 27 and pipeline 11 at last.Realized that like this cooling water comes circulation where wherefrom.Be furnished with pressure switch 13 and differential pressure transmitter 12 in described pipeline 11 systems.When intake 1 or pipeline 11 stops up when causing resistance excessive, pressure switch 13 and differential pressure transmitter 12 signal, and make up by valve and water pump 5 to system, just can realize intake 1 and section of tubing are carried out backwash.

Claims (3)

1. scaled bulb tubular hydraulic generator flow passage cover plate water intake system, water flow passage was arranged, it is characterized in that: be furnished with flow passage cover plate on the water flow passage excessively, flow passage cover plate is provided with intake, intake links by the water filtering tank on pipeline and the flow passage cover plate, opposite side at water filtering tank is provided with water intake, and this water intake links with water pump, safety check, butterfly valve one, water filter and generator set cooling system successively by pipeline.
2. scaled bulb tubular hydraulic generator flow passage cover plate water intake system as claimed in claim 1 is characterized in that: described generator set cooling system links with the mistake water flow passage by pipeline and butterfly valve two.
3. scaled bulb tubular hydraulic generator flow passage cover plate water intake system as claimed in claim 1 is characterized in that: be furnished with pressure switch and differential pressure transmitter in described pipe-line system.
CN200920237984XU 2009-10-28 2009-10-28 Water fetching system of flow channel cover plate of bulb tubular turbine generator Expired - Fee Related CN201546875U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920237984XU CN201546875U (en) 2009-10-28 2009-10-28 Water fetching system of flow channel cover plate of bulb tubular turbine generator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920237984XU CN201546875U (en) 2009-10-28 2009-10-28 Water fetching system of flow channel cover plate of bulb tubular turbine generator

Publications (1)

Publication Number Publication Date
CN201546875U true CN201546875U (en) 2010-08-11

Family

ID=42602045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920237984XU Expired - Fee Related CN201546875U (en) 2009-10-28 2009-10-28 Water fetching system of flow channel cover plate of bulb tubular turbine generator

Country Status (1)

Country Link
CN (1) CN201546875U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102678425A (en) * 2012-06-11 2012-09-19 四川嘉陵江桐子壕航电开发有限公司 Primary and secondary cooling water mixing utilizing system for bulb tubular water-turbine generator set
CN103671580A (en) * 2013-12-18 2014-03-26 国家电网公司 Method and device for reducing running bearing temperature of guide bearing of water turbine
CN109701305A (en) * 2019-03-12 2019-05-03 中国电建集团中南勘测设计研究院有限公司 A kind of automatic backwash blowdown water filter

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102678425A (en) * 2012-06-11 2012-09-19 四川嘉陵江桐子壕航电开发有限公司 Primary and secondary cooling water mixing utilizing system for bulb tubular water-turbine generator set
CN102678425B (en) * 2012-06-11 2015-07-08 四川嘉陵江桐子壕航电开发有限公司 Primary and secondary cooling water mixing utilizing system for bulb tubular water-turbine generator set
CN103671580A (en) * 2013-12-18 2014-03-26 国家电网公司 Method and device for reducing running bearing temperature of guide bearing of water turbine
CN103671580B (en) * 2013-12-18 2016-03-09 国家电网公司 Reduce turbine guide bearing and run watt warm method and device
CN109701305A (en) * 2019-03-12 2019-05-03 中国电建集团中南勘测设计研究院有限公司 A kind of automatic backwash blowdown water filter

Similar Documents

Publication Publication Date Title
CN201120256Y (en) Reverse osmosis membrane cleaning apparatus
CN101983940B (en) Water-free reverse osmosis water purifying machine
CN203848705U (en) Exhausted steam recycling system
CN201546875U (en) Water fetching system of flow channel cover plate of bulb tubular turbine generator
CN201864606U (en) Reverse osmosis water purifier without waste water
CN201762185U (en) Water-saving reverse osmosis water purifier
CN102536603A (en) Hydroelectric power generating system realizing matching utilization of double-tail cooling water of thermal power plants
CN201470845U (en) Soft water cooling system of continuous casting crystallizer
CN203569148U (en) Ultrafast cooling and comprehensive water treatment device for medium and heavy plate
CN201506733U (en) Module combination horizontal-type cycling water comprehensive water treatment device
CN209308881U (en) A kind of system improving power station technical water supply reliability
CN201354770Y (en) Cooling water circulation device for pumps
CN206192182U (en) Anti - washing unit on line pressurizes
CN105174645A (en) Practical waste water treatment energy-saving equipment and waste water treatment method
CN202755210U (en) Small cheese dyeing machine wastewater and waste heat recycling device
CN205367782U (en) Imitate intelligent level pressure moisturizing degasification unit by force
CN212293070U (en) Small-size sea water desalination device based on GO membrane
CN204607721U (en) Reverse osmosis water treating equipment
CN207108678U (en) Nitrogen fertilizer plant's production cycle water system
CN107867766B (en) Membrane method water treatment process test device
CN206915833U (en) Waste Water Treatment
CN205035235U (en) Practical waste water treatment energy -saving equipment
CN214389023U (en) Filter system for forced backwashing water of reservoir
CN217567588U (en) Safe piping structure of circulating water bypass filter of air cooling tower in air separation engineering
CN204607723U (en) Reverse osmosis water purifying plant

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GUANGDONG HONGYUAN ZHONGLI POWER GENERATING EQUIPM

Free format text: FORMER OWNER: SHAOGUAN ZHONGLI POWER GENERATING EQUIPMENT CO., LTD. OF GUANGDONG MINGZHU GROUP

Effective date: 20120323

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20120323

Address after: Pavilion 512031 Guangdong province Zhenjiang District of Shaoguan City

Patentee after: Guangdong Hongyuan Zhongli Generation Equipment Co., Ltd.

Address before: Pavilion 512031 Guangdong province Zhenjiang District of Shaoguan City

Patentee before: Shaoguan Zhongli Generating Equipment Co., Ltd., Guangdong Mingzhu Group

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100811

Termination date: 20131028