CN201506696U - Vertical shaft construction sinking winch centralized control device - Google Patents
Vertical shaft construction sinking winch centralized control device Download PDFInfo
- Publication number
- CN201506696U CN201506696U CN2009202675487U CN200920267548U CN201506696U CN 201506696 U CN201506696 U CN 201506696U CN 2009202675487 U CN2009202675487 U CN 2009202675487U CN 200920267548 U CN200920267548 U CN 200920267548U CN 201506696 U CN201506696 U CN 201506696U
- Authority
- CN
- China
- Prior art keywords
- vertical shaft
- shaft construction
- well drilling
- selector button
- drilling winch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model discloses a vertical shaft construction sinking winch centralized control device which is composed of a centralized control selection button SB5 arranged in a centralized control cabinet, a local control selection button SB6, a plurality of single vertical shaft construction sinking winch selection buttons SBn and a plurality of single vertical shaft construction sinking winch control devices, one single vertical shaft construction sinking winch control device is used to lead a plurality of the single vertical shaft construction sinking winch control devices to be integrated into one body systematically, one-person operation can replace multi-person operation, the operation synchronism is good, the safety is good, and labor is saved, therefore, the vertical shaft construction sinking winch centralized control device is advanced compared with the traditional vertical shaft construction sinking winch centralized control device.
Description
Technical field
The utility model relates to a kind of control apparatus, especially a kind of well drilling winch in vertical shaft construction centralized controlling device.
Background technology
Shaft Construction adopts many sinking winch to suspend in midair simultaneously or the same equipment of tensioning, as: hanging scaffold, template etc.According to design, many sinking winch are arranged in respectively in the stable car group of pit shaft both sides, and supporting electrical control cubicles and operating system are arranged in both sides separately in the electric control chamber.
As adopt decentralised control, there is following shortcoming:
(1) both sides need many people's operations, waste of manpower, the expenditure of getting a raise in pay;
(2) sensitivity response of signal transmission and each operating personal is difficult to reach synchronously, is prone to operational confusion, even error;
(3) easily cause steel rope stressed separately, the long-term use meeting reduces the steel rope safety factor, even rope-broken accident occurs;
(4) the adjustment time long, direct influence construction repetition period, and then influence job schedule, duration and benefit.
Along with the raising of vertical level of mechanization, the improvement of construction technology, speed of application is more and more faster.In the work progress, hanging scaffold, template etc. carry more frequent, directly influence construction period, job schedule.
(1) driving is just often wanted rule, stamping die casting concrete every day once at least; Also to carry hanging scaffold before and after blowing out respectively once.
(2) the operation transition period, the freeze section external wall construction finishes, and carries dish slip casting, inner wall construction to the well head process, from the well head rule to the shaft bottom driving surface during; Engineering finishes, and promotes hanging scaffold to the well head process.
In sum, sinking winch synchronism centralized control is very important.
The utility model content
Technical problem to be solved in the utility model provides a kind of well drilling winch in vertical shaft construction centralized controlling device.
The technical scheme in the invention for solving the technical problem is:
A kind of well drilling winch in vertical shaft construction centralized controlling device, by the centralized control selector button SB5 that is arranged in the centralized control cabinet, control selector button SB6 on the spot, a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn and a plurality of separate unit well drilling winch in vertical shaft construction control setup are formed, it is characterized in that: centralized control selector button SB5, control the A that inserts power supply after selector button SB6 and a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn parallel connection on the spot, between the B end, be in series with inlet side fuse FU3.2 and centralized control stop button SBS at the A of power supply end, be in series with out end fuse FU4.2 at the B of power supply end, at centralized control selector button SB5, control on the spot on the branch road of selector button SB6 and a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn and be in series with centralized control selector button latching relay KA5 respectively, control selector button latching relay KA6 and separate unit well drilling winch in vertical shaft construction selector button latching relay KAn on the spot, centralized control selector button latching relay KA5 and to control selector button latching relay KA6 on the spot be multiple-contact relay.One termination centralized control selector button SB5 of a pair of open contact of each separate unit well drilling winch in vertical shaft construction selector button latching relay, control an end of the circuit parallel of selector button SB6 and a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn on the spot, the other end of a pair of open contact of the separate unit well drilling winch in vertical shaft construction selector button latching relay start-up control circuit of back of connecting with a pair of open contact of centralized control selector button latching relay KA5 as the separate unit well drilling winch in vertical shaft construction; Every pair of open contact controlling selector button latching relay KA6 on the spot is connected on respectively in the latching circuit of start button SB1.n of separate unit well drilling winch in vertical shaft construction control setup.
The technical scheme in the invention for solving the technical problem can also be:
The utility model is with the corresponding control housing that inserts the well drilling winch in vertical shaft construction centralized controlling device of contact of each master cock of separate unit well drilling winch in vertical shaft construction control setup.
The utility model disposes emergency stopping system in the control housing of well drilling winch in vertical shaft construction centralized controlling device, this emergency stopping system comprises that having the special-purpose main supply switch QM of the sinking winch power supply that pressure-off button function is arranged stops action button SA with the urgency that has self-retaining function.
The a pair of open contact of the utility model each relay by separate unit well drilling winch in vertical shaft construction and well drilling winch in vertical shaft construction centralized controlling device between A, the B of the power supply of well drilling winch in vertical shaft construction centralized controlling device end is parallel with the one group of indicator lamp that shows separate unit well drilling winch in vertical shaft construction and well drilling winch in vertical shaft construction centralized controlling device mode of operation.
It is that n equals 4 that the platform number of separate unit well drilling winch in vertical shaft construction control setup described in the utility model is four, and corresponding electric elements numbering uses " .1 .2 .3 .4 " to distinguish respectively.
The beneficial effects of the utility model are:
Compared with prior art, the utility model can realize controlling on the spot and remote many sinking winch single actions, how moving or complete moving control requirement, and is also simple to operate, save manpower, safety factor height, raising operating efficiency.
Description of drawings
Fig. 1 is schematic circuit diagram of the present utility model.
Fig. 2 is the schematic circuit diagram of 1# separate unit well drilling winch in vertical shaft construction control setup.
Fig. 3 is the schematic circuit diagram of 2# separate unit well drilling winch in vertical shaft construction control setup.
Fig. 4 is the schematic circuit diagram of 3# separate unit well drilling winch in vertical shaft construction control setup.
Fig. 5 is the schematic circuit diagram of 4# separate unit well drilling winch in vertical shaft construction control setup.
Fig. 6 is sudden stop schematic circuit diagram of the present utility model.
Fig. 7 is the total command switch scheme drawing after the command switch parallel connection of each separate unit well drilling winch in vertical shaft construction control setup.
The specific embodiment
A kind of well drilling winch in vertical shaft construction centralized controlling device, by the centralized control selector button SB5 that is arranged in the centralized control cabinet, control selector button SB6 on the spot, a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn and a plurality of separate unit well drilling winch in vertical shaft construction control setup are formed, centralized control selector button SB5, control the A that inserts power supply after selector button SB6 and a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn parallel connection on the spot, between the B end, be in series with inlet side fuse FU3.2 and centralized control stop button SBS at the A of power supply end, be in series with out end fuse FU4.2 at the B of power supply end, at centralized control selector button SB5, control on the spot on the branch road of selector button SB6 and a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn and be in series with centralized control selector button latching relay KA5 respectively, control selector button latching relay KA6 and separate unit well drilling winch in vertical shaft construction selector button latching relay KAn on the spot, centralized control selector button latching relay KA5 and to control selector button latching relay KA6 on the spot be multiple-contact relay.One termination centralized control selector button SB5 of a pair of open contact of each separate unit well drilling winch in vertical shaft construction selector button latching relay, control an end of the circuit parallel of selector button SB6 and a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn on the spot, the other end of a pair of open contact of the separate unit well drilling winch in vertical shaft construction selector button latching relay start-up control circuit of back of connecting with a pair of open contact of centralized control selector button latching relay KA5 as the separate unit well drilling winch in vertical shaft construction; Every pair of open contact controlling selector button latching relay KA6 on the spot is connected on respectively in the latching circuit of start button SB1.n of separate unit well drilling winch in vertical shaft construction control setup.
The corresponding control housing that inserts the well drilling winch in vertical shaft construction centralized controlling device of contact with each master cock of separate unit well drilling winch in vertical shaft construction control setup.
Dispose emergency stopping system in the control housing of well drilling winch in vertical shaft construction centralized controlling device, this emergency stopping system comprises that having the special-purpose main supply switch QM of the sinking winch power supply that pressure-off button function is arranged stops action button SA with the urgency that has self-retaining function.
The a pair of open contact of each relay by each separate unit well drilling winch in vertical shaft construction and well drilling winch in vertical shaft construction centralized controlling device between A, the B of the power supply of well drilling winch in vertical shaft construction centralized controlling device end is parallel with the one group of indicator lamp that shows separate unit well drilling winch in vertical shaft construction and well drilling winch in vertical shaft construction centralized controlling device mode of operation.
It is that n equals 4 that the platform number of described separate unit well drilling winch in vertical shaft construction control setup is four, and corresponding electric elements numbering uses " .1 .2 .3 .4 " to distinguish respectively.
Claims (5)
1. well drilling winch in vertical shaft construction centralized controlling device, by the centralized control selector button SB5 that is arranged in the centralized control cabinet, control selector button SB6 on the spot, a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn and a plurality of separate unit well drilling winch in vertical shaft construction control setup are formed, it is characterized in that: centralized control selector button SB5, control the A that inserts power supply after selector button SB6 and a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn parallel connection on the spot, between the B end, be in series with inlet side fuse FU3.2 and centralized control stop button SBS at the A of power supply end, be in series with out end fuse FU4.2 at the B of power supply end, at centralized control selector button SB5, control on the spot on the branch road of selector button SB6 and a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn and be in series with centralized control selector button latching relay KA5 respectively, control selector button latching relay KA6 and separate unit well drilling winch in vertical shaft construction selector button latching relay KAn on the spot, centralized control selector button latching relay KA5 and to control selector button latching relay KA6 on the spot be multiple-contact relay.One termination centralized control selector button SB5 of a pair of open contact of each separate unit well drilling winch in vertical shaft construction selector button latching relay, control an end of the circuit parallel of selector button SB6 and a plurality of separate unit well drilling winch in vertical shaft construction selector button SBn on the spot, the other end of a pair of open contact of the separate unit well drilling winch in vertical shaft construction selector button latching relay start-up control circuit of back of connecting with a pair of open contact of centralized control selector button latching relay KA5 as the separate unit well drilling winch in vertical shaft construction; Every pair of open contact controlling selector button latching relay KA6 on the spot is connected on respectively in the latching circuit of start button SB1.n of separate unit well drilling winch in vertical shaft construction control setup.
2. a kind of well drilling winch in vertical shaft construction centralized controlling device according to claim 1 is characterized in that: with the corresponding control housing that inserts the well drilling winch in vertical shaft construction centralized controlling device of contact of each master cock of separate unit well drilling winch in vertical shaft construction control setup.
3. a kind of well drilling winch in vertical shaft construction centralized controlling device according to claim 1 and 2, it is characterized in that: dispose emergency stopping system in the control housing of well drilling winch in vertical shaft construction centralized controlling device, this emergency stopping system comprises that having the special-purpose main supply switch QM of the sinking winch power supply that pressure-off button function is arranged stops action button SA with the urgency that has self-retaining function.
4. a kind of well drilling winch in vertical shaft construction centralized controlling device according to claim 3 is characterized in that: a pair of open contact of each relay by separate unit well drilling winch in vertical shaft construction and well drilling winch in vertical shaft construction centralized controlling device between A, the B of the power supply of well drilling winch in vertical shaft construction centralized controlling device end is parallel with the one group of indicator lamp that shows separate unit well drilling winch in vertical shaft construction and well drilling winch in vertical shaft construction centralized controlling device mode of operation.
5. a kind of well drilling winch in vertical shaft construction centralized controlling device according to claim 4, it is characterized in that: it is that n equals 4 that the platform number of described separate unit well drilling winch in vertical shaft construction control setup is four, and corresponding electric elements numbering uses " .1 .2; .3 .4 " to distinguish respectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009202675487U CN201506696U (en) | 2009-10-17 | 2009-10-17 | Vertical shaft construction sinking winch centralized control device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009202675487U CN201506696U (en) | 2009-10-17 | 2009-10-17 | Vertical shaft construction sinking winch centralized control device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201506696U true CN201506696U (en) | 2010-06-16 |
Family
ID=42467824
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009202675487U Expired - Fee Related CN201506696U (en) | 2009-10-17 | 2009-10-17 | Vertical shaft construction sinking winch centralized control device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201506696U (en) |
-
2009
- 2009-10-17 CN CN2009202675487U patent/CN201506696U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201307243Y (en) | Elevator shaft simulation device which can simulate real shaft signals | |
DE59915052D1 (en) | Apparatus for the special operation of elevator installations | |
CN101693503A (en) | Central control device of well drilling winch in vertical shaft construction | |
CN201506696U (en) | Vertical shaft construction sinking winch centralized control device | |
CN201364486Y (en) | Electrical control system used for tractor general assembly production line | |
EP1734636A3 (en) | Switchbox | |
CN109209442A (en) | Tunnel double-lining tee tube liquid level relay bomb shelter warning device | |
CN202704736U (en) | Elevator debugging device | |
CN203359712U (en) | Detecting device for integrated control cabinet of elevator | |
CN203285128U (en) | Device used for descending sliding mold platform | |
CN214573387U (en) | Quick installation device of wet joint suspended formwork bottom plate | |
CN203239294U (en) | Device for realizing remote start and stop of pumping unit | |
CN203593569U (en) | Device for independently controlling double suspension points of fixed winch hoist | |
CN102807175A (en) | Intelligent elevator | |
CN201725482U (en) | Mine lifting winch electric control system practical training device | |
CN202221534U (en) | Novel automatic control device for sewage pump | |
CN201109940Y (en) | Construction engineering water-proof structure | |
CN106032028A (en) | A combination die concrete pouring completion alarm technology | |
CN201280438Y (en) | Aluminum oxide decomposer | |
CN205117695U (en) | Water pump controller | |
CN215494027U (en) | Power supply repeated conversion test device | |
CN202924506U (en) | Lift operation simulator | |
CN202558399U (en) | Safety control system of cargo elevator for factories | |
CN102777024A (en) | Digital and intelligent lifting control device | |
CN210655797U (en) | Lower anchor head hanger convenient to go into groove |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100616 Termination date: 20111017 |