The valve of energy automatic cut-off
Technical field the utility model relates to the valve of a kind of energy automatic cut-off, belongs to water supply system valve products technical field.
Background technique is at present in the high-level tank water system that uses, it is the mode of structure that adopts two tunnel water systems of one tunnel water inlet and another road water outlet, be that intake pipe and outlet pipe branch is arranged, from intake pipe to high-level tank water, supply water to user terminal from the outlet pipe water outlet then, this two tunnel water systems need be installed two road pipelines simultaneously, inconvenience is installed, the cost height, system complex, owing to there is not corresponding valve, so the high-level tank water system can't realize a road convenient and reliable water supply, application one road pipeline that promptly can't be convenient and reliable is realized water inlet and water outlet.
Summary of the invention the utility model provides a kind of valve of energy automatic cut-off of novelty, adopts the automatic cut-off technology, the purpose that makes realization one tunnel turnover water supply that the high-level tank water system can be convenient and reliable.
The technical solution adopted in the utility model is:
The valve of a kind of energy automatic cut-off, comprise: ball float, upper valve body, following valve body, valve plate, upper valve body is connected and fixed with following valve body, in the formed cavity valve plate is installed between upper valve body and the following valve body, valve plate is connected with the inwall of following valve body, sealing gasket, backguy screw rod are installed on the valve plate, and ball float is connected with valve plate with the backguy screw rod by rope or chain.
Upper valve body is a pipe joint formula structure, and following valve body is a telescoping structure, and upper valve body is tightened and is fixed on down on the valve body, and upper valve body and following valve body constitute the valve body structure of valve.
Valve plate is a disc-shaped structure, the backguy screw rod is twisted in being pressed on the valve plate on the valve plate and with sealing gasket, and valve plate is connected with following valve body by rotating shaft, installs and spring in the rotating shaft, spring is the button spring structure, and valve plate can be along the rotating shaft rotation and on the inwall of being close to following valve body under the effect of spring.
The size of ball float volume should be able to make buoyancy that ball float the produced gravity sum greater than resistance and valve plate, rope or the chain of spring in water.
The utility model beneficial effect is:
Owing to adopted the valve of energy of the present utility model automatic cut-off, solved the problem that existing high-level tank water system can't realize that a road convenient and reliable turnover is supplied water, valve that can automatic cut-off of the present utility model has low, the service-strong characteristics of simple in structure, easily manufactured cost.
Description of drawings
Fig. 1: the sectional structure chart that is the valve plate opening state of the valve that the utility model can automatic cut-off;
Fig. 2: the sectional structure chart that is the valve plate closed condition of the valve that the utility model can automatic cut-off;
Fig. 3: the working state schematic representation that is the valve of the utility model energy automatic cut-off;
Fig. 4: the sectional structure chart that is the upper valve body of the valve that the utility model can automatic cut-off;
Fig. 5: the plan view that is Fig. 4;
Fig. 6: the perspective view that is the following valve body of the valve that the utility model can automatic cut-off;
Fig. 7: the plan view that is the following valve body of the valve that the utility model can automatic cut-off;
Fig. 8: the plan view that is the following valve body of the valve that the utility model can automatic cut-off;
Fig. 9: the left view that is the following valve body of the valve that the utility model can automatic cut-off;
Figure 10: the A-A sectional view that is the following valve body of the valve that the utility model can automatic cut-off;
Figure 11: the B-B sectional view that is the following valve body of the valve that the utility model can automatic cut-off;
Figure 12: the plan view that is the valve plate of the valve that the utility model can automatic cut-off;
Figure 13: the plan view that is the valve plate of the valve that the utility model can automatic cut-off;
Figure 14: the sectional view that is the sealing gasket of the valve that the utility model can automatic cut-off;
Figure 15: the plan view that is the backguy screw rod of the valve that the utility model can automatic cut-off.
Among Fig. 1,2: 1, ball float 2, upper valve body 3, following valve body 4, valve plate 5, sealing gasket 6, backguy screw rod 7, spring 8, rotating shaft 9, rope or chain
Among Fig. 3: 1, ball float 10, water tank 11, liquid
Among Fig. 4: 2, upper valve body 21, intake-outlet
Among Fig. 5: 2, upper valve body
Among Fig. 6,7,8,9,10,11: 3, following valve body
Among Figure 12,13: 4, valve plate
Among Figure 14: 5, sealing gasket
Among Figure 15: 6, backguy screw rod
Embodiment
As Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9, Figure 10, Figure 11, Figure 12, Figure 13, Figure 14, shown in Figure 15.
The valve of energy automatic cut-off, by: ball float 1, upper valve body 2, following valve body 3, valve plate 4, sealing gasket 5, backguy screw rod 6, spring 7, rotating shaft 8, rope or chain 9 are formed.
The valve of a kind of energy automatic cut-off, comprise: ball float 1, upper valve body 2, following valve body 3, valve plate 4, upper valve body 2 is connected and fixed with following valve body 3, in the formed cavity valve plate 4 is installed between upper valve body 2 and the following valve body 3, valve plate 4 is connected with the inwall of following valve body 3, sealing gasket 5, backguy screw rod 6 are installed on the valve plate 4, ball float 1 is connected with valve plate 4 with backguy screw rod 6 by rope or chain 9, when valve plate 4 under the effect of ball float 1 during throttle down, valve plate 4 is closed fully with the intake-outlet 21 of upper valve body 2.
Upper valve body 2 is a pipe joint formula structure, and following valve body 3 is a telescoping structure, and upper valve body 2 is tightened and is fixed on down on the valve body 3, and upper valve body 2 and following valve body 3 constitute the valve body structure of valves.
Valve plate 4 is a disc-shaped structure, backguy screw rod 6 is twisted in being pressed on the valve plate 4 on the valve plate 4 and with sealing gasket 5, valve plate 4 is connected with following valve body 3 by rotating shaft 8, install and spring 7 in the rotating shaft 8, spring 7 is the button spring structure, and valve plate 4 can be along rotating shaft 8 rotations and on the inwall of being close to following valve body 3 under the effect of spring 7.
The size of ball float 1 volume should be able to make buoyancy that ball float 1 the produced gravity sum greater than resistance and valve plate 4, rope or the chain 9 of spring 7 in water.
As shown in Figure 3, be installed on valve that can automatic cut-off on the water tank 10 or approach on the pipeline of water tank 10, then rope or chain 9 are coupled together with ball float 1, the length of rope or chain 9 is decided by the height of liquid 11 liquid levels in the water tank 10, when the liquid level of liquid 11 in the water tank 10 reaches the extreme higher position, the length of rope or chain 9 should make ball float 1 can strain valve 4, and valve plate 4 can so just have been finished installment work substantially with the intake-outlet 21 complete seal closures of upper valve body 2.
When water tank 10 is empty when not having water to intake, at this moment ball float 1 is positioned at the bottom position of water tank 10, valve plate 4 and on sealing gasket 5, backguy screw rod 6 is at spring 7, under the effect of rotating shaft 8, valve plate 4 is close on the inwall of following valve body 3, liquid passes through valve body 3 down, upper valve body 2 enters in the water tank 10, rising along with liquid level in the water tank 10, ball float 1 is also along with rising, when the liquid level in the water tank 10 arrives higher liquid level, ball float 1 spurs valve plate 4 gradually by rope or chain 9 and upwards rotates, and along with the continuation of liquid level is risen and closed the intake-outlet 21 of upper valve body 2 gradually, when liquid level reached the highest liquid level or required liquid level, ball float 1 was moved valve plate 4 extreme higher position to and with intake-outlet 21 complete closed of upper valve body 2, has so just been blocked further water inlet automatically by rope or chain 9, at this moment, valve plate 4 under the effect of the pulling force of ball float 1 and intake pressure, valve plate 4 sealing intake-outlets 21, the sealing gasket 5 on the valve plate 4 plays seal action, prevent to leak, close inlet valve then and get final product.
In the time will making water, as long as open outlet valve or water tap, then water will flow out automatically, valve plate 4 can be opened under the effect of spring 7, and water will flow out from water tank 10, along with the increase of water flow, liquid level descends in the water tank 10, then ball float 1 also descends, and valve plate 4 can be opened bigger and bigger, and current will constantly flow out.
When needing to intake again in the water tank 10, as long as repeat above-mentioned steps.So just can realize well that convenient and reliable road turnover supplied water.