Prior art keywords
column
link plate
upright post
secondary beam
connection fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009200469343U
Other languages
Chinese (zh)
Inventor
倪骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU CROWNHOMES CO., LTD.
Original Assignee
SUZHOU CROWNHOMES CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU CROWNHOMES CO Ltd filed Critical SUZHOU CROWNHOMES CO Ltd
Priority to CN2009200469343U priority Critical patent/CN201447767U/en
Application granted granted Critical
Publication of CN201447767U publication Critical patent/CN201447767U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a column-type combination house beam, which belongs to the technical field of the building, and comprises an upright post, wherein two sides of the upright post are provided with a secondary beam corresponding to each other, and is characterized in that two sides of the upright post are provided with a U-shaped connection fastener which corresponds to each other, and the connection end of the secondary beam is provided with a link plate. When the upright post and the secondary beams are assembled, the link plate is connected with the U-shaped connection fasteners. Therefore, through the connection of the link plate and the U-shaped connection fasteners, the best bearing and earthquake-resistant effect when assembling the upright post and the secondary beams can be ensured; moreover, the integral assembling way is simple and rapid, and the column type combination house beam is easy to be popularized in the field.

Description

Upright post type combined beam
Technical field
The utility model relates to a kind of combination house beam, relates in particular to a kind of upright post type combined beam, belongs to technical field of buildings.
Background technology
In the house beam of institute's widespread usage, the combining structure of its secondary beam and column is often too simple in existing building, lacks preferable load-bearing and shock resistance.And the integral body manufacturing of house beam and the step of installation are also more loaded down with trivial details, occur the tightness degree of error effect necessity easily, do not meet convenient in the existing building field, safe, theory demand efficiently.Moreover existing house beam lacks the combining structure between effective beam and the column.
Summary of the invention
The purpose of this utility model is to overcome the above problem that prior art exists, and a kind of upright post type combined beam is provided.
For realizing the purpose of this utility model, upright post type combined beam, include column, the column both sides are equipped with the secondary beam of position correspondence, wherein: described column both sides are provided with corresponding " U " type connection fastener that distributes, the link of secondary beam is provided with link plate, and when column, secondary beam combination, link plate links to each other with " U " type connection fastener.
Further, above-mentioned upright post type combined beam, wherein, the link of described secondary beam is provided with mounting groove, is extended with the installation fin on the link plate, fin is installed is embedded in the mounting groove.
Further, above-mentioned upright post type combined beam wherein, is equipped with the corresponding installation pin-and-hole in position on the link of described secondary beam and the link plate, installs in the pin-and-hole and is equipped with alignment pin, and secondary beam is connected with the link plate pin.
Further, above-mentioned upright post type combined beam wherein, is equipped with the corresponding screw hole in position on the back of the body end of described " U " type connection fastener and the column, is connected with bolt in the screw hole, and the end of bolt is equipped with nut, and connection fastener is connected with the column bolt.
Further, above-mentioned upright post type combined beam, wherein, the both sides of described " U " type connection fastener are provided with the corresponding installation pin-and-hole in position with link plate, when column, secondary beam combination, install in the pin-and-hole and be provided with alignment pin, " U " type connection fastener is connected with the mutual pin of link plate.
Again further, above-mentioned upright post type combined beam, wherein, the bottom of described " U " type connection fastener is provided with the installation salient point, and corresponding position, link plate bottom is provided with bayonet socket, and when column, secondary beam combination, bayonet socket is articulated on the salient point.
Adopt technical solutions of the utility model, rely on link plate and link to each other, have best load-bearing and anti seismic efficiency when having guaranteed column, secondary beam combination with " U " type connection fastener.And the overall package mode is simple and efficient, is easy to promote in the art.
The purpose of this utility model, advantage and characteristics will illustrate by the non-limitative illustration of following preferential embodiment and explain that these embodiment only provide as an example with reference to accompanying drawing.
Description of drawings
Fig. 1 is the decomposition explosion schematic diagram of upright post type combined beam;
Fig. 2 is the organigram of link plate;
Fig. 3 is the organigram of secondary beam link;
Fig. 4 is the organigram of " U " type connection fastener;
Fig. 5 is the organigram of salient point.
The implication of each Reference numeral is as follows among the figure:
1 column, 2 secondary beams
3 " U " type connection fastener, 4 link plates
5 alignment pins, 6 bolts
7 nuts 8 are installed pin-and-hole
9 bayonet sockets, 10 mounting grooves
11 screw holes, 12 salient points
The specific embodiment
Upright post type combined beam, include column 1, column 1 both sides are equipped with the secondary beam 2 of position correspondence, its unusual part is: described column 1 both sides are provided with corresponding " U " type connection fastener 3 that distributes, the link of secondary beam 2 is provided with link plate 4, when column 1, secondary beam 2 combinations, link plate 4 links to each other with " U " type connection fastener 3.
Specifically, promptly as Fig. 2, shown in Figure 3: at first can carry out firm combining in advance in order to ensure secondary beam 2 with the installation fin, the link of secondary beam 2 is provided with mounting groove 10, is extended with the installation fin on the link plate 4, fin is installed is embedded in the mounting groove 10.Simultaneously, combine with the firm of fin is installed for the ease of secondary beam 2, be equipped with the corresponding installation pin-and-hole 8 in position on the link of secondary beam 2 and the link plate 4, be equipped with alignment pin 5 in the installation pin-and-hole 8, secondary beam 2 is connected with link plate 4 both pins.
In conjunction with the utility model one preferred implementation, the both sides of " U " type connection fastener 3 are provided with the corresponding installation pin-and-hole 8 in position with link plate 4, and " U " type connection fastener 3 adopts pin to be connected with link plate 4.And, be equipped with the corresponding screw hole in position 11 on the back of the body end of " U " type connection fastener 3 and the column 1, be connected with bolt 6 in the screw hole 11, the end of bolt 6 is equipped with nut 7, and connection fastener is connected with column 1 bolt 6.
Shown in Fig. 4,5: be connected with the firm of link plate 4 in order further to guarantee " U " type connection fastener 3, the bottom of " U " type connection fastener 3 is provided with installs salient point 12, corresponding position, link plate 4 bottom is provided with bayonet socket 9, and when column 1, secondary beam 2 combinations, bayonet socket 9 is articulated on the salient point 12.Thus, can further cooperate original pin to connect, make constituting a load-bearing integral body between column 1, the two secondary beam 2.
Shown in 1~5, use performance of the present utility model is roughly as follows: at first the link at secondary beam 2 sets out mounting groove 10, gets out simultaneously pin-and-hole 8 is installed.Afterwards, the link plate 4 of five metals material is added in the mounting grooves 10, order is installed fin and is fully combined with mounting groove 10, and penetrates two alignment pins 5 and reinforce.Thus, can make at least two secondary beams 2 that have link plate 4 carries out standby.Then, on column 1, offer screw hole 11, two " U " type connection fastener 3 usefulness bolts 6 and nut 7 are passed through screw hole 11, be fixed in the both sides of column 1.During this period, salient point 12 is installed to the bottom of " U " type connection fastener 3.At last the secondary beam 2 that link plate 4 is housed is snapped on " U " type connection fastener 3 of column 1, the bayonet socket 9 of link plate 4 bottoms directly snaps into location on the salient point 12 of " U " type connection fastener 3 bottoms, and it is fixing to penetrate three alignment pins 5 then.Other secondary beam 2 is also installed with same way as, can finish the installation of double-secondary beam type combined house beam.
By above-mentioned character express also in conjunction with the accompanying drawings as can be seen, behind employing the utility model, rely on link plate and link to each other, have best load-bearing and anti seismic efficiency when having guaranteed column, secondary beam combination with " U " type connection fastener.And the overall package mode is simple and efficient, is easy to promote in the art.
Certainly; it below only is concrete exemplary applications of the present utility model; protection domain of the present utility model is not constituted any limitation. in addition to the implementation; the utility model can also have other embodiment. and all employings are equal to the technical scheme of replacement or equivalent transformation formation, all drop within the utility model scope required for protection.

Claims (6)

1. upright post type combined beam includes column, and the column both sides are equipped with the secondary beam of position correspondence, it is characterized in that: described column both sides are provided with corresponding " U " type connection fastener that distributes, the link of secondary beam is provided with link plate, and when column, secondary beam combination, link plate links to each other with " U " type connection fastener.
2. upright post type combined beam according to claim 1 is characterized in that: the link of described secondary beam is provided with mounting groove, is extended with the installation fin on the link plate, fin is installed is embedded in the mounting groove.
3. upright post type combined beam according to claim 1 is characterized in that: be equipped with the corresponding installation pin-and-hole in position on the link of described secondary beam and the link plate, install in the pin-and-hole and be equipped with alignment pin, secondary beam is connected with the link plate pin.
4. upright post type combined beam according to claim 1, it is characterized in that: be equipped with the corresponding screw hole in position on the back of the body end of described " U " type connection fastener and the column, be connected with bolt in the screw hole, the end of bolt is equipped with nut, and connection fastener is connected with the column bolt.
5. upright post type combined beam according to claim 1, it is characterized in that: the both sides of described " U " type connection fastener are provided with the corresponding installation pin-and-hole in position with link plate, when column, secondary beam combination, install in the pin-and-hole and be provided with alignment pin, " U " type connection fastener is connected with the mutual pin of link plate.
6. upright post type combined beam according to claim 1 is characterized in that: the bottom of described " U " type connection fastener is provided with the installation salient point, and corresponding position, link plate bottom is provided with bayonet socket, and when column, secondary beam combination, bayonet socket is articulated on the salient point.
CN2009200469343U 2009-07-01 2009-07-01 Column-type combination house beam Expired - Fee Related CN201447767U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200469343U CN201447767U (en) 2009-07-01 2009-07-01 Column-type combination house beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200469343U CN201447767U (en) 2009-07-01 2009-07-01 Column-type combination house beam

Publications (1)

Publication Number Publication Date
CN201447767U true CN201447767U (en) 2010-05-05

Family

ID=42552483

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200469343U Expired - Fee Related CN201447767U (en) 2009-07-01 2009-07-01 Column-type combination house beam

Country Status (1)

Country Link
CN (1) CN201447767U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101624843A (en) * 2009-07-01 2010-01-13 苏州皇家整体住宅系统有限公司 Upright post type combined beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101624843A (en) * 2009-07-01 2010-01-13 苏州皇家整体住宅系统有限公司 Upright post type combined beam

Similar Documents

Publication Publication Date Title
CN102142472A (en) Frame for solar module
CN202416579U (en) Main beam and secondary beam combined roof beam
CN102493557A (en) Combined roof beam of main beam and secondary beam
CN201447769U (en) Cross type column beam
CN201447766U (en) Double-secondary beam type combined house beam
CN201447767U (en) Column-type combination house beam
CN101666119A (en) Double-secondary beam type combined house beam
CN201447768U (en) Combined type house beam with oblique angle
CN101614041A (en) A kind of " ten " font column house beam
CN101624843A (en) Upright post type combined beam
EP3118387B1 (en) Solar roof tile and solar roof tile system
CN201447804U (en) T-shaped combined beam
CN101666121A (en) T-shaped combined house beam
CN101666120A (en) Combined house beam with tilt angle
CN102493555A (en) Vertical column and horizontal beam combined girder
CN202307937U (en) Solar battery pack and aluminium profile
CN204967730U (en) Photovoltaic solar panel frame
CN201695604U (en) Wall protection plate of wooden house
CN206971472U (en) Light gauge cold-formed steel shape steel plate shear force wall
KR200466919Y1 (en) Installarion structure for solar power generator
CN202117177U (en) Steel structure workshop beam column and connection node structure between beams
CN202416578U (en) Upright post-cross beam combination house beam
CN201798306U (en) I-shaped arc support plate for seat
CN215871264U (en) Installation base is used in installation of photovoltaic solar panel
CN219527962U (en) Assembled wall connecting piece

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 215015, Jiangsu, Wuzhong District Province, Taihu Road, Suzhou Lake crossing

Patentee after: Suzhou Crownhomes Co., Ltd.

Address before: 215015, Jiangsu, Wuzhong District Province, Taihu Road, Suzhou Lake crossing

Patentee before: Suzhou Crownhomes Co., Ltd.

C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Ni Jun

Inventor before: Ni Jun

C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: Wuzhong District Xukou Mashe village 215000 Suzhou city of Jiangsu Province along the bridge

Patentee after: SUZHOU CROWNHOMES CO., LTD.

Address before: 215015, Jiangsu, Wuzhong District Province, Taihu Road, Suzhou Lake crossing

Patentee before: Suzhou Crownhomes Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100505

Termination date: 20170701