CN201439603U - Flow intercepting steel box structure - Google Patents

Flow intercepting steel box structure Download PDF

Info

Publication number
CN201439603U
CN201439603U CN2008201580945U CN200820158094U CN201439603U CN 201439603 U CN201439603 U CN 201439603U CN 2008201580945 U CN2008201580945 U CN 2008201580945U CN 200820158094 U CN200820158094 U CN 200820158094U CN 201439603 U CN201439603 U CN 201439603U
Authority
CN
China
Prior art keywords
box structure
steel
steel box
layer
sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2008201580945U
Other languages
Chinese (zh)
Inventor
林玉叶
熊江平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Investigation Design and Research Institute Co Ltd SIDRI
Original Assignee
Shanghai Investigation Design and Research Institute Co Ltd SIDRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Investigation Design and Research Institute Co Ltd SIDRI filed Critical Shanghai Investigation Design and Research Institute Co Ltd SIDRI
Priority to CN2008201580945U priority Critical patent/CN201439603U/en
Application granted granted Critical
Publication of CN201439603U publication Critical patent/CN201439603U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a flow intercepting steel box structure which comprises container type steel structural empty boxes, an exhaust hole, a sand removing hole, a blowing filling hole, blowing filling sand and air bags. The two steel structural empty boxes are fixedly connected into integral structures of clamping buckles, the blowing filling sand is filled in the structures of the empty boxes, and the air bags used for leveling and water blocking are fixed at the bottom of the boxes. By adopting the steel box structure, the capability of resisting the flushing of water flow is greatly improved after the sand is filled and compacted. The flow intercepting steel box structure has high safety degree and can adapt to severe hydrologic conditions.

Description

A kind of steel box structure that dams
Technical field
The utility model belongs to the closure work in corral (making ground or the embankment) engineering, is specifically related to a kind of Longkou closure structure and job practices thereof.
Background technology
In the tidal river or marine site when carrying out corral (make ground or embankment) engineering, must be through the most important link of whole engineering-carry out Longkou (mouthful door) closure work.Usually the closure body structure pattern that adopts has hydraulic reclamation packeted soil rib body and rock mound at present.At corral area big (the Longkou Kou Men turnover water yield is bigger), when mouthful door is big, if adopt conventional hydraulic reclamation packeted soil rib body to exist:
(1) no matter adopt flat, upright blocking up, when flow velocity was big, cloth bag was in place, the filling difficulty of construction is big;
When (2) adopting flat blocking up, mouthful door is big, and hydraulic reclamation engineering quantity waterborne is big, and construction and ship organize difficulty big;
(3) when closure requires to carry out in neap season, and must accomplish without any letup, otherwise in entering, spring tide, cloth bag is difficult to bear washing away of high flow rate, and the Longkou engineering is had great risk;
(4) under water during hydraulic reclamation, banketing can't compacting, and unit weight is less, and required section is often bigger, and closure intensity increases suddenly, need organize in a short time than adult, material, machine, and difficulty is bigger.
And adopt common rock mound:
When (1) flow velocity is big, must could satisfy the anti-impact requirement by the boulder particle diameter, strengthen buying, transportation, throw and fill out difficulty;
(2) adopt flatly when stifled, mouthful door is big, and it is big that engineering quantity is filled out in throwing waterborne, and construction and ship organize difficulty big;
(3) in the rock mound closure, before not holding one's breath, there is the problem of seepage stability all the time, in case unstability, the very big risk that there is comprehensive avalanche in the rib body, destroys by rush of water.
The utility model content
Technical problem to be solved in the utility model provides a kind of Longkou closure (damming) structure and job practices thereof, makes that construction adaptability is strong, reusable, easy construction is quick, economical.
In order to solve the problems of the technologies described above, the technical scheme that the utility model adopted is: a kind of steel box structure that dams, be used for Longkou steel case blast lifting closure, it comprises: steel work casing, the gas avert by prayers that is positioned at the some through holes on the steel work casing and is fixed in steel work casing bottom, it is characterized in that: described steel work casing is divided into two-layer up and down, promptly the 1st layer and the 2nd layer, be provided with some through holes on the steel plate between described the 1st layer and the 2nd layer, the relative both sides of described steel work casing are provided with opening.
As one of preferred version of the present utility model, the described steel box structure that dams comprises 2 interconnective steel work casings.
As one of preferred version of the present utility model, described steel work casing adopts buckle structure to connect.
As one of preferred version of the present utility model, the 1st layer and the 2nd layer of described steel work casing is equipped with sand.
Owing to adopted technique scheme, had following advantage:
1, owing to adopt the steel box structure, fill the sand ballast after anti-current scour ability improve greatly, can adapt to more abominable hydrologic condition, the degree of safety height.
2. closure material, one. be the steel case that can reuse, the 2nd, abundant and cheap silt particle, energy-conservation, economize material, environmental protection.
3, the steel box structure can adopt " container-type " empty van structure, is convenient to making, handling and stacking;
4, because the steel box structure can fill the sand ballast, possess stronger self-stability, therefore this novel structure has better compliance and feasibility;
5, adopt this closure steel box structure, the corresponding reduction of difficulty of construction, effective accelerating construction progress, duration shortening.
6, fine-tuning leveling steel case after the filling of gas avert by prayers also can play plugging function, and it is strong therefore to adapt to the out-of-flatness ability, states and can reduce water leakage.
7, after the closure, the recyclable utilization of steel box structure.
Description of drawings
Fig. 1 is the longitudinal cross-section schematic diagram of an embodiment of the present utility model;
Fig. 2 is the steel box structure plan structure schematic diagram that dams of the present utility model.
The critical element explanation
Steel work casing 1 sand 4
Buckle structure 2 gas avert by prayers 5
Through hole 3
The specific embodiment
A kind of as shown in Figure 1 embodiment comprises 2 interconnective steel work casings.
A kind of steel box structure that dams, be used for Longkou steel case blast lifting closure, the gas avert by prayers 5 that the described steel box structure that dams comprises steel work casing 1, is positioned at the some through holes 3 on the steel work casing 1 and is fixed in steel work casing 1 bottom, described steel work casing 1 is divided into two-layer up and down, promptly the 1st layer and the 2nd layer, be provided with some through holes 3 on the steel plate between described the 1st layer and the 2nd layer, described steel work casing 1 relative both sides are provided with opening (not shown).
Described steel work casing adopts buckle structure to connect.The 1st layer and the 2nd layer of described steel work casing is equipped with sand 4.
A kind of job practices of Longkou closure (damming) structure: it comprises the steps:
Step 1, adopt single as required or two steel work empty vans are fixedly connected into integral body;
Step 2, according to the initial stage stability requirement, in empty van, be pre-charged with the sand that satisfies the constant weight requirement;
Step 3, carry out the hoisted in position of empty van body successively;
Step 4, the leveling of filling gas avert by prayers or water blockoff;
Continue the filling sand in step 5, the steel box structure, finish closure;
After step 6, permanent dike construction are finished, open the opening that the relative both sides of steel work casing are provided with, thereby filling sand in the emptying steel case reclaims the steel case, handling is stacked standby to the stockyard.
Owing to adopted technique scheme, had following advantage:
1, owing to adopt the steel box structure, fill the sand ballast after anti-current scour ability improve greatly, can adapt to more abominable hydrologic condition, the degree of safety height.
2. closure material, one. be the steel case that can reuse, the 2nd, abundant and cheap silt particle, energy-conservation, economize material, environmental protection.
3, the steel box structure can adopt " container-type " empty van structure, is convenient to making, handling and stacking;
4, because the steel box structure can fill the sand ballast, possess stronger self-stability, therefore this novel structure has better compliance and feasibility;
5, adopt this closure steel box structure, the corresponding reduction of difficulty of construction, effective accelerating construction progress, duration shortening.
6, fine-tuning leveling steel case after the filling of gas avert by prayers also can play plugging function, and it is strong therefore to adapt to the out-of-flatness ability, also can reduce water leakage.
7, after the closure, the recyclable utilization of steel box structure.
The above-mentioned steel box structure that dams can calculate the steel work casing 1 of respective number as required, also can fill an amount of sand 4 as required, and the sand use amount can be calculated.
Above-mentioned description to embodiment is can understand and use the utility model for ease of those skilled in the art.The person skilled in the art obviously can easily make various modifications to these embodiment, and needn't pass through performing creative labour being applied in the General Principle of this explanation among other embodiment.Therefore, the utility model is not limited to the embodiment here, and those skilled in the art should be within protection domain of the present utility model for improvement and modification that the utility model is made according to announcement of the present utility model.

Claims (4)

1. steel box structure that dams, be used for Longkou steel case blast lifting closure, it comprises: steel work casing (1), the gas avert by prayers (5) that is positioned at the some through holes (3) on the steel work casing (1) and is fixed in steel work casing (1) bottom, it is characterized in that: described steel work casing (1) is divided into two-layer up and down, promptly the 1st layer and the 2nd layer, be provided with some through holes (3) on the steel plate between described the 1st layer and the 2nd layer, the relative both sides of described steel work casing (1) are provided with opening.
2. the steel box structure that dams as claimed in claim 1 is characterized in that: the described steel box structure that dams comprises 2 interconnective steel work casings (1).
3. the steel box structure that dams as claimed in claim 2 is characterized in that: described steel work casing (1) adopts buckle structure (2) to connect.
4. as claim 1 or the 3 described steel box structures that dam, it is characterized in that: the 1st layer and the 2nd layer of described steel work casing (1) is equipped with sand (4).
CN2008201580945U 2008-12-29 2008-12-29 Flow intercepting steel box structure Expired - Fee Related CN201439603U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008201580945U CN201439603U (en) 2008-12-29 2008-12-29 Flow intercepting steel box structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008201580945U CN201439603U (en) 2008-12-29 2008-12-29 Flow intercepting steel box structure

Publications (1)

Publication Number Publication Date
CN201439603U true CN201439603U (en) 2010-04-21

Family

ID=42544272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008201580945U Expired - Fee Related CN201439603U (en) 2008-12-29 2008-12-29 Flow intercepting steel box structure

Country Status (1)

Country Link
CN (1) CN201439603U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101824817A (en) * 2010-05-06 2010-09-08 任再永 Drainage consolidation construction method for treating soft soil foundation by container stacking loading
CN102619194A (en) * 2012-04-17 2012-08-01 上海市水利工程设计研究院 Method for closure of high-flow-rate closure gap by riprapping and frames used in method
CN102747706A (en) * 2011-04-20 2012-10-24 中交上海航道局有限公司 Section steel frame cage stone-dumping closure construction method
CN104120729A (en) * 2014-08-01 2014-10-29 中国铁建大桥工程局集团有限公司 Novel internal supporting structure of large steel suspension box and construction process of novel internal supporting structure of large steel suspension box
CN105839652A (en) * 2016-05-18 2016-08-10 中铁隧道集团二处有限公司 Construction method for stacking containers for silt prevention in immersed tube end foundation trench under inner rock surface of cofferdam
CN111364487A (en) * 2020-03-19 2020-07-03 中铁隧道局集团有限公司 Low-water-level combined cofferdam and construction method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101824817A (en) * 2010-05-06 2010-09-08 任再永 Drainage consolidation construction method for treating soft soil foundation by container stacking loading
CN101824817B (en) * 2010-05-06 2012-04-25 任再永 Drainage consolidation construction method for treating soft soil foundation by container stacking loading
CN102747706A (en) * 2011-04-20 2012-10-24 中交上海航道局有限公司 Section steel frame cage stone-dumping closure construction method
CN102619194A (en) * 2012-04-17 2012-08-01 上海市水利工程设计研究院 Method for closure of high-flow-rate closure gap by riprapping and frames used in method
CN104120729A (en) * 2014-08-01 2014-10-29 中国铁建大桥工程局集团有限公司 Novel internal supporting structure of large steel suspension box and construction process of novel internal supporting structure of large steel suspension box
CN104120729B (en) * 2014-08-01 2015-12-30 中国铁建大桥工程局集团有限公司 A kind of large steel suspension box inner supporting structure and construction technology thereof
CN105839652A (en) * 2016-05-18 2016-08-10 中铁隧道集团二处有限公司 Construction method for stacking containers for silt prevention in immersed tube end foundation trench under inner rock surface of cofferdam
CN105839652B (en) * 2016-05-18 2017-11-28 中铁隧道集团二处有限公司 The anti-silting construction method of stacked containers in scar sinking pipe end foundation trench in cofferdam
CN111364487A (en) * 2020-03-19 2020-07-03 中铁隧道局集团有限公司 Low-water-level combined cofferdam and construction method

Similar Documents

Publication Publication Date Title
CN201439603U (en) Flow intercepting steel box structure
CN109629585B (en) Novel cofferdam structure under weak covering layer and construction method
CN110453643B (en) Plugging device for plugging dike breach by using natural water energy
CN106939587A (en) A kind of power station major river bed river closure construction method
CN203256699U (en) Construction structure for water passing earth-rock dam
CN101691755A (en) Method for constructing liquified discarded soil in construction of subaqueous structure
CN218027769U (en) Combined device of cofferdam and purse net for mangrove planting
CN215367442U (en) Solidified soil riverbed scouring protection structure
CN207919486U (en) A kind of deep water soft soil foundation quay wall structure
CN106836129A (en) A kind of method of disposal of piping
AU2019203298A1 (en) A method and system for underwater scour prevention
CN206956686U (en) A kind of hydraulic reclamation area gabion discharge opening
CN100516367C (en) Geotechnical soil-ballasted sack cofferdam for water piers of river-crossing bridge and its production method
CN206800314U (en) Rubble-mound foundation gravity type quay
CN206538732U (en) A kind of long piled wharf
CN106638478B (en) A kind of construction method for gushing out mouth using the quick containment pipe of waste tire
CN210031724U (en) A absorption field that is used for geomembrane mud field hydraulic reclamation mouth
CN210827315U (en) Plugging device for plugging dike breach by utilizing natural water energy
CN201080616Y (en) River spanning bridge underwater pier earthwork mud-filling bag cofferdam
CN204715304U (en) A kind of cofferdam protective slope structure
CN209538114U (en) Composite foundation structure of the gravity type quay based on sludge solidification technology in situ
CN211938369U (en) Ton package and landfill of soluble waste salt
CN107740381A (en) A kind of opened debris flow blocking dam set based on waste and old Container Reconstruction
CN214460590U (en) Filling type reinforced concrete retaining wall
CN216457451U (en) River channel dredging polluted soil storage and disposal structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100421

Termination date: 20171229

CF01 Termination of patent right due to non-payment of annual fee