CN201412067Y - Silt removing pipeline suitable for gas well drilling - Google Patents

Silt removing pipeline suitable for gas well drilling Download PDF

Info

Publication number
CN201412067Y
CN201412067Y CN2009200816495U CN200920081649U CN201412067Y CN 201412067 Y CN201412067 Y CN 201412067Y CN 2009200816495 U CN2009200816495 U CN 2009200816495U CN 200920081649 U CN200920081649 U CN 200920081649U CN 201412067 Y CN201412067 Y CN 201412067Y
Authority
CN
China
Prior art keywords
pipeline
joint
silt removing
catch hoop
lower catch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009200816495U
Other languages
Chinese (zh)
Inventor
徐忠祥
罗整
侯伟
蒋斌
刘云
邓虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Drilling Technology Research Institute of CNPC Chuanqing Drilling Engineering Co Ltd
Original Assignee
Drilling Technology Research Institute of CNPC Chuanqing Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Drilling Technology Research Institute of CNPC Chuanqing Drilling Engineering Co Ltd filed Critical Drilling Technology Research Institute of CNPC Chuanqing Drilling Engineering Co Ltd
Priority to CN2009200816495U priority Critical patent/CN201412067Y/en
Application granted granted Critical
Publication of CN201412067Y publication Critical patent/CN201412067Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Joints Allowing Movement (AREA)

Abstract

The utility model provides a silt removing pipeline suitable for gas well drilling, which belongs to the technical field of manufacturing silt removing equipment in a gas well drilling site. The designed silt removing pipeline suitable for gas well drilling is made of wear-resistant materials and can be quickly connected. The silt removing pipeline comprises a hoop device and a pipeline. Upper andlower hoop arms are respectively arranged at the two ends of upper and lower hoops. The pipeline comprises a pipe body and a joint, and the reverse side of the joint adopts the structure of an inclined plane. The upper and lower hoops are connected by a bolt. The silt removing pipeline solves the problem in the prior art that the installation and preparation of the equipment consume more time. Being quickly connected by the hoops and fixed by the bolt, the silt removing pipeline has the characteristics of simple structure, low cost and convenient processing as well as manufacturing.

Description

Be applicable to row's sand tube line of gas drilling
Technical field:
A kind of row's sand tube line that is applicable to gas drilling is used for adopting gas to implement the discharge of the downhole debris of under balance pressure drilling process, belongs to the manufacturing technology field of gas drilling well site sediment outflow equipment.
Background technology:
In order to accelerate the development rate of petroleum gas, taked a lot of ways in the drilling technology field, wherein under balance pressure drilling is exactly a kind of preferably high-speed drilling technology, in under-balanced drilling technology, adopting gas is a kind of preferably method as the drilling well medium, the advantage of gas drilling is to increase substantially bit speed, owing to do not have under the liquid input well, so the problem of leakage does not take place yet, for the stratum that leakage may take place, administer the good method of leakage beyond doubt, simultaneously, because the proportion of gas is very light, in the process of implementing drilling well, can not invade the stratum, can not damage, so can well protect and find oil-gas Layer layer of oil gas production yet; The shortcoming of prior art is: because what taken out of by gas from the down-hole when implementing gas drilling is not mud, but by chippy rock sand, these rock sands have very big wearing and tearing to the sediment outflow pipe, environment there is bigger harm, in order in the process of implementing gas drilling, to guarantee safety and free from environmental pollution, often before gas drilling, the time that erection equipment and preparation are consumed is longer, wherein, in order to solve the problem that gas drilling row sand tube line is punctured by the rock sand wearing and tearing, very heavy with the sediment outflow pipe design, and the joint of tie point all adopts flange to connect, only be to connect these sediment outflow pipelines just to need 1 day time, what have also needs time of two days, and the heavy and difficulty of connection work.
Summary of the invention:
The purpose of this utility model is the problem that exists at prior art, adopts high-abrasive material to make the sediment outflow pipeline, reduces the weight of row's sand tube line, has designed a kind of row's sand tube line that is applicable to gas drilling that can connect fast.
The utility model is achieved in that the utility model comprises clip device and pipeline, is characterized in that: described clip device comprises front band 1 and lower catch hoop 7, is respectively arranged with upper and lower clip arm at the two ends of front band 1 and lower catch hoop 7; Pipeline comprises pipe shaft 10 and joint 11, and the back side of joint 11 is ramp structures, and front band 1 is connected by bolt 2 with lower catch hoop 7;
Described lower catch hoop arm 5b is provided with the pin hole;
Described front band arm 5a is provided with lock hole 4;
The lower end of described bolt 2 is fixed in the pin hole of lower catch hoop 7 by pin 8;
The interior circle of described front band 1 and lower catch hoop 7 is provided with the groove that the ramp structure with joint 11 back sides adapts;
When making pipeline and joint 11 thereof, adopt the inner surface of high-abrasive material butt joint 11 and sediment outflow pipeline to handle, make joint 11 and sediment outflow pipeline inner surface have the advantages that anti-sand washes away, when the sediment outflow pipeline is installed at the scene, two pipeline front ends are closed up, like this, the ramp structure at two pipe joint 11 back sides that close up has just formed can realize that the protrusion that connects is stupefied, to go up, lower catch hoop 1 and 7 is respectively from protruding stupefied snapping in up and down, to go up by bolt 1 again, lower catch hoop connects, and it is fixing by nut 3, last putting in lock hole 4 locks the connection that card 9 has just been finished one section sediment outflow pipe joint, just can come into effect gas drilling after whole pipe joints connections are finished.
Advantage of the present utility model with beneficial effect is: the ramp structure that is provided with at two pipe joint back sides can form very easily after two pipelines butt joints that to be connected protrusion stupefied, last, on the protrusion that the interior round groove that is provided with of lower catch hoop can be stuck in tie point formation fast is stupefied, and by the quick fixed connection point of bolt, therefore, realized that syndeton is simple, cost is low, and the purpose of convenient processing and manufacture, the cure process of joint and sediment outflow pipeline inner surface can play wear-resisting effect, therefore can reduce the wall thickness of pipeline, the weight of the row's of making sand tube line reduces significantly, move and be connected also just convenient and swiftly, can increase substantially the on-the-spot efficient that connects construction.
Description of drawings:
Fig. 1 is the utility model front broken section structure for amplifying schematic diagram
Fig. 2 is the half section schematic diagram of the utility model syndeton
Fig. 3 is the amplification half section schematic diagram of the utility model pipe shaft and joint
The specific embodiment:
Provide embodiment of the present utility model below in conjunction with accompanying drawing:
The utility model comprises clip device and pipeline, the clip device is two semicircle devices, constitute by front band 1 and lower catch hoop 7, in order to connect the upper and lower clip of two semi-circular structure, two ends at front band 1 and lower catch hoop 7 are respectively arranged with clip arm 5a and 5b, the interior circle of front band 1 and lower catch hoop 7 is provided with groove, and the groove of setting can be stuck on the joint of pipeline easily, is convenient to realize the connection of two pipelines; Pipeline comprises pipe shaft 10 and joint 11, the front of joint 11 is plane structures, be convenient to the butt joint of two pipelines, the back side of joint 11 is ramp structures, the ramp structure that is provided with after two pipelines butt joints, can form with upper and lower clip in the protrusion that adapts of the groove that is provided with on the circle stupefied, be convenient to snapping in of front band 1, lower catch hoop 7; The lower catch hoop arm 5b that is provided with is provided with pin hole 8, is connected with bolt 2 by pin 6 in pin hole 8, and front band 1 is connected by bolt 2 with lower catch hoop 7; For the sake of security, on front band arm 5a, also be provided with lock hole 4 and locking card 9;
When making pipe shaft 10 and joint 11 thereof, can all adopt wear-resisting material, also can butt joint 11 and the inner surface of pipe shaft 10 carry out Wear-resistant Treatment, make the inner surface of joint 11 and pipe shaft 10 have the advantages that anti-sand washes away, when the sediment outflow pipeline is installed at the scene, two pipe shaft 10 front ends are closed up, like this, the ramp structure at two pipe shafts, 10 front tab, 11 back sides that close up has just formed can realize that the protrusion that connects is stupefied, to go up, lower catch hoop 1 and 7 is respectively from protruding stupefied snapping in up and down, to go up by bolt 2 again, lower catch hoop connects, and it is fixing by nut 3, last, after lower catch hoop 1 and 7 installs, to lock card 9 inserts from lock hole 4, can play the problem that prevents that bolt 2 from coming off automatically because of the pipeline vibrations, thereby improved security reliability, when mounted, if the aligning surface of two pipelines differs when a less angle is arranged, can utilize, lower catch hoop 1 and 7 slowly snaps in, calibrate, finally reach the purpose of aiming at fully, thereby it is more convenient that installation is connected, after whole pipe joints connections are finished, just can come into effect gas drilling.

Claims (5)

1. the row's sand tube line that is applicable to gas drilling comprises clip device and pipeline, and it is characterized in that: described clip device comprises front band and lower catch hoop, is respectively arranged with upper and lower clip arm at the two ends of front band and lower catch hoop; Pipeline comprises pipe shaft and joint, and the back side of joint is ramp structure, and front band is connected by bolt with lower catch hoop.
2. the row's sand tube line that is applicable to gas drilling according to claim 1, it is characterized in that: described lower catch hoop arm is provided with the pin hole.
3. the row's sand tube line that is applicable to gas drilling according to claim 1, it is characterized in that: described front band arm is provided with lock hole.
4. the row's sand tube line that is applicable to gas drilling according to claim 1, it is characterized in that: the lower end of described bolt is fixed in the pin hole of lower catch hoop by pin.
5. the row's sand tube line that is applicable to gas drilling according to claim 1 is characterized in that: the interior circle of described front band and lower catch hoop is provided with the groove that the ramp structure with the joint back side adapts.
CN2009200816495U 2009-06-10 2009-06-10 Silt removing pipeline suitable for gas well drilling Expired - Fee Related CN201412067Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200816495U CN201412067Y (en) 2009-06-10 2009-06-10 Silt removing pipeline suitable for gas well drilling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200816495U CN201412067Y (en) 2009-06-10 2009-06-10 Silt removing pipeline suitable for gas well drilling

Publications (1)

Publication Number Publication Date
CN201412067Y true CN201412067Y (en) 2010-02-24

Family

ID=41713953

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200816495U Expired - Fee Related CN201412067Y (en) 2009-06-10 2009-06-10 Silt removing pipeline suitable for gas well drilling

Country Status (1)

Country Link
CN (1) CN201412067Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104066909A (en) * 2011-12-22 2014-09-24 Peri有限公司 Mutual, detachable connection of two support sections of a variable-length construction support

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104066909A (en) * 2011-12-22 2014-09-24 Peri有限公司 Mutual, detachable connection of two support sections of a variable-length construction support
CN104066909B (en) * 2011-12-22 2016-05-25 Peri有限公司 G shape hook and telescopic structure stand
US9926711B2 (en) 2011-12-22 2018-03-27 Peri Gmbh G-hook for mutual releasable connection of two prop portions of a variable length construction prop

Similar Documents

Publication Publication Date Title
CN102720453B (en) Method and device for mechanically removing sand and draining liquid from pit shaft of oil/gas well in underbalanced state
CN102003140A (en) Traversing reverse circulating drilling method of horizontal directional drilling pipeline and special drilling bit
CN104481580B (en) A kind of down-hole coal bed mash gas pumping drilling restorative procedure and the device of use thereof
CN101806196A (en) Compound rotary drilling rig drilling mechanism
WO2019169734A1 (en) Integrated apparatus and method for long-distance downhole drilling and fracturing
CN105201480B (en) Surface well underground long drilled holes pressure break coal seam method
CN201412067Y (en) Silt removing pipeline suitable for gas well drilling
CN201262045Y (en) Hydraulic back-off sub used for oil well water block
CN102392614A (en) Wellhead pressure suction assembly
CN202228029U (en) Sand bailer for down-hole operation of oil field
CN202659194U (en) Novel well wall restoring device with combined sleeve and corrugated pipe
CN204402406U (en) A kind of down-hole coal bed mash gas pumping drilling prosthetic device
CN105019870A (en) Method for sand control of oil well
CN201184135Y (en) Small sleeve pipe pillar restoring sleeve loss well
CN103742095B (en) A kind of straight barrel type gas well surface line catches ball device
CN102758443B (en) Novel enclosing structure applicable to connection change between new pipes and old pipes and construction method thereof
CN206205870U (en) A kind of fluid erosion prevention petroleum pipeline deferent pipe nipple component
CN202300336U (en) Electric pump oil-extracting pipe column with ground hydraulic control oil-pipe injection functions
CN101476444A (en) Horizontal radiation pipe construction equipment for vibration-impact type radiation well
CN2881069Y (en) Prestressed well fixing ground anchor
CN212054705U (en) Novel underground pipeline poling is used in communication device
CN204941579U (en) The pre-buried orifice tube of a kind of pit shaft borehole wall grouting
CN103835295B (en) Petroleum pipeline construction method is worn under a kind of deep basal pit soil pipe
CN107461182A (en) Layering fracturing sand control method
CN201933496U (en) Novel pile tip for soft clay foundation treatment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100224