CN201405007Y
CN201405007Y CN2009200892785U CN200920089278U CN201405007Y CN 201405007 Y CN201405007 Y CN 201405007Y CN 2009200892785 U CN2009200892785 U CN 2009200892785U CN 200920089278 U CN200920089278 U CN 200920089278U CN 201405007 Y CN201405007 Y CN 201405007Y
Authority
CN
China
Prior art keywords
steel reinforcement
reinforcement cage
bridge pier
ring flange
space regulator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009200892785U
Other languages
Chinese (zh)
Inventor
孙秀国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Tunnel Engineering Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2009200892785U priority Critical patent/CN201405007Y/en
Application granted granted Critical
Publication of CN201405007Y publication Critical patent/CN201405007Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a construction machine, concretely relates to a cage rolling machine of a reinforcing steel framework of bridge pier studs and pile foundations, which is used for winding the reinforcing steel framework of bridge pier studs and pile foundations of large bridges. A small scored pulley (10) is arranged on an electric motor (13) and connected with a large scored pulley (9)which is arranged on a worm wheel-type speed reducing box (12) through a triangular conveying belt (11), an output shaft of the worm wheel-type speed reducing box (12) is connected with a ground shaft (5) through a shaft coupler (14) and a bearing bracket (4), and a roller chain wheel (7) which is arranged on the ground shaft (5) is connected together with a roller chain automatic feeding table (8), and connected with a main flange plate (3) and an attached flange plate (19) through the ground shaft (5). By designing a novel mechanical transmission adjusting mechanism, the cage rolling machine can quickly and accurately wind the reinforcing steels on the reinforcing steel framework of bridge pier studs, has standard and precise installation interval as well as quick speed, lowers the labor intensity of workers, and saves production cost.

Description

Bridge pier post, pile foundation framework of steel reinforcement roll the cage machine
Technical field;
The utility model relates to a kind of building machinery, specifically is that bridge pier post, the pile foundation framework of steel reinforcement that uses when building bridge bridge pier post, the coiling of pile foundation framework of steel reinforcement rolls the cage machine.
Background technology:
After main muscle welds by design length, on reinforcement, mark the spacing of main muscle design, on smooth concrete floor, put two main muscle then earlier, one people picks up reinforcement and is placed on the main muscle, by the spacing that marks, another one welder master worker is reinforcement and main muscle firm welding, makes a concerted effort to lift firm welding on the mark that main muscle is placed on corresponding reinforcement with several workmans then, and whole steel reinforcement cage master muscle root root is so operated.And the obstructed heart of steel reinforcement cage master muscle, not on an axis, there is the quality technology potential safety hazard in separation criteria.Few and the cisco unity malfunction of this technology workman, uneconomical, benefit not, time-consuming.
The utility model content:
The utility model has changed the drawback of former manual coiling framework of steel reinforcement, provides a kind of special bridge pier post, pile foundation framework of steel reinforcement coiling machinery bridge pier post, pile foundation framework of steel reinforcement of utilizing to roll the cage machine.The small grooved wheel device is on motor, be connected with the big grooved wheel of device on the worm-gear type reductor by triangular driving band, the worm-gear type speed reducer output shaft is connected with the earth's axis by shaft coupling, bearing bracket stand, roller chain wheel of installing on the earth's axis and roller chain automatic charging platform link together, and are connected with main ring flange and attached ring flange by the earth's axis.Because the utility model has designed novel mechanical transmission mechanism and master, attached ring flange, utilize the reinforcing bar stabilizing adjusting device, just can be wound on reinforcing bar accurately on bridge pier post, the pile foundation framework of steel reinforcement fast, the installing space standard is accurate, speed is fast, reduce working strength of workers, saved production cost.
Description of drawings:
Fig. 1 is a front view of the present utility model
Fig. 2 is the stable regulation mechanism map of Fig. 1
Fig. 3 is A1-A1 master's flange plate structure figure of Fig. 1
Fig. 4 is the 2-2 vertical view of Fig. 2
Fig. 5 is the 3-3 cutaway view of Fig. 2
Fig. 6 is the attached flange plate structure figure of the A2-A2 of Fig. 1
Fig. 7 is the 4-4 cutaway view of Fig. 6
The specific embodiment:
As shown in Figure 1, small grooved wheel 10 devices are on motor 13, be connected with the big grooved wheel 9 of device on worm-gear type reductor 12 by triangular driving band 11, worm-gear type reductor 12 output shafts are connected with the earth's axis 5 by shaft coupling 14, bearing bracket stand 4, roller chain wheel 7 and the roller chain automatic charging platform 8 installed on the earth's axis 5 link together, and are connected with main ring flange 3 and attached ring flange 19 by the earth's axis 5.
As Fig. 1, shown in Figure 3, main ring flange 3 is installed on the earth's axis 5, and mechanism is connected with stable regulation, four steel reinforcement cage space regulators 17 have been installed with steel reinforcement cage space regulator pilot pin 26 on the main ring flange 3, and installed a steel reinforcement cage space regulator member 23 thereon respectively, steel reinforcement cage space regulator 17 is connected by steel reinforcement cage space regulator axle 18 with main ring flange 3; Torque spring 6 is enclosed within on the steel reinforcement cage space regulator axle 18.
As Fig. 1, Fig. 6, shown in, the attached ring flange steel reinforcement cage of attached ring flange 19 usefulness space regulator 20 is connected with steel reinforcement cage space regulator axle 18, torque spring 6, steel reinforcement cage spacing demodulator pilot pin 26, and device steel reinforcement cage space regulator member 23, steel reinforcement cage space regulator member 23 tops are attached feeding port 21, and the main feeding port 22 of shutoff feeding port member 24 and main ring flange 3 is connected.
As Fig. 1, Fig. 2, Fig. 4, shown in Figure 5, stable regulation mechanism is welded on adjustable angle by the firm fulcrum steel plate 25 of steel reinforcement cage and separates on the steel plate of the firm fulcrum of steel reinforcement cage 15 both sides, and device is on firm platform 16, sprocket wheel by the earth's axis 5 directions one end is connected with firm platform 16 usefulness screws by bearing bracket stand, other end sprocket wheel is connected on the firm platform 16 by the screw on the firm fulcrum lifting regulating rod 27 of steel reinforcement cage, and about in the of 16 both sides at firm platform by chain gear apparatus for extraordinary roller chain 28.
Embodiment: at first set the encrypted section need do steel reinforcement cage or non-encrypted section (for example: steel reinforcement cage is long if any 40 meters, last 20 meters if it is encrypted section that 30 main muscle are arranged, 20 meters as if there being 15 main muscle to be encrypted section not down).Press under the design length after the honest material, material is carried on roller chain automatic charging platform, be placed on above the roller chain V, the main muscle overlap joint of welding section on the roller chain feeding platform.After the welding of main muscle overlap joint section is good, press the startup power knob, the A.C. contactor adhesive, the condenser timing of digital display time is installed in sheave on the motor, is driven by the V-belt and be installed in the running of turbine type reductor sheave.Earth's axis rotation once, roller chain automatic charging platform send a main muscle in feeding port, picks up reinforcement and is placed on perpendicular to master, attached ring flange and adjustable angle and separates above the main muscle of the firm fulcrum of the slidingtype three extraordinary roller chain steel reinforcement cages of row.Main, attached ring flange rotation is once sent a main muscle in this rotation while steel reinforcement cage space regulator, makes main muscle reinforcement rotation.The steel reinforcement cage space regulator has sent after the main muscle, and under the effect of torque spring, the steel reinforcement cage space regulator is still got back to original position, and is adjoint with steel reinforcement cage space regulator pilot pin.Roller chain automatic charging platform send a main muscle simultaneously.Distance between first main muscle and the second main muscle should adhere to specification, if variant, can reconcile steel reinforcement cage space regulator member and meet design requirement.In each reinforcement and main muscle junction firm welding, weld and finish.The main muscle root root in one week of reinforcement is so operated, this construction technology, simple to operate, not the personnel that are subjected to limit, economy again the material benefit.

Claims (4)

1, a kind of bridge pier post, pile foundation framework of steel reinforcement roll the cage machine, it is characterized in that small grooved wheel (10) device is on motor (13), be connected with the big grooved wheel (9) of device on worm-gear type reductor (12) by triangular driving band (11), worm-gear type reductor (12) output shaft is connected with the earth's axis (5) by shaft coupling (14), bearing bracket stand (4), the earth's axis (5) goes up roller chain wheel (7) and the roller chain automatic charging platform (8) installed and links together, and is connected with main ring flange (3) and attached ring flange (19) with the earth's axis (5).
2, bridge pier post according to claim 1, pile foundation framework of steel reinforcement roll the cage machine, it is characterized in that main ring flange (3) is installed on the earth's axis (5), and mechanism is connected with stable regulation, main ring flange (3) is gone up and has been installed four steel reinforcement cage space regulators (17) with steel reinforcement cage space regulator pilot pin (26), and install a steel reinforcement cage space regulator member (23), steel reinforcement cage space regulator (17) is connected by steel reinforcement cage space regulator axle (18) with main ring flange (3); Torque spring (6) is enclosed within on the steel reinforcement cage space regulator axle (18).
3, bridge pier post according to claim 1, pile foundation framework of steel reinforcement roll the cage machine, it is characterized in that attached ring flange (19) is connected with steel reinforcement cage space regulator axle (18), torque spring (6), steel reinforcement cage spacing demodulator pilot pin (26) with attached ring flange steel reinforcement cage space regulator (20), and device steel reinforcement cage space regulator member (23), steel reinforcement cage space regulator member (23) top is attached feeding port (21), and the main feeding port (22) of shutoff feeding port member (24) and main ring flange (3) is connected.
4, bridge pier post according to claim 2, pile foundation framework of steel reinforcement roll the cage machine, it is characterized in that stable regulation mechanism is welded on adjustable angle by the firm fulcrum steel plate of steel reinforcement cage (25) and separates on the steel plate of the firm fulcrum of steel reinforcement cage (15) both sides, and device is on firm platform (16), sprocket wheel by the earth's axis (5) direction one end is connected with screw with firm platform (16) by bearing bracket stand, other end sprocket wheel is connected on the firm platform (16) by the screw on the firm fulcrum lifting regulating rod of steel reinforcement cage (27), extraordinary roller chain (28) by chain gear apparatus in firm platform (16) both sides up and down.
CN2009200892785U 2009-03-22 2009-03-22 Cage Rolling machine of reinforcing steel framework of bridge pier stud and pile foundation Expired - Fee Related CN201405007Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200892785U CN201405007Y (en) 2009-03-22 2009-03-22 Cage Rolling machine of reinforcing steel framework of bridge pier stud and pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200892785U CN201405007Y (en) 2009-03-22 2009-03-22 Cage Rolling machine of reinforcing steel framework of bridge pier stud and pile foundation

Publications (1)

Publication Number Publication Date
CN201405007Y true CN201405007Y (en) 2010-02-17

Family

ID=41675928

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200892785U Expired - Fee Related CN201405007Y (en) 2009-03-22 2009-03-22 Cage Rolling machine of reinforcing steel framework of bridge pier stud and pile foundation

Country Status (1)

Country Link
CN (1) CN201405007Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106541059A (en) * 2016-12-07 2017-03-29 中铁九局集团有限公司 Suitable for the self-positioning colligation frock of high speed railway fragments-free track slab steel reinforcement cage
CN114769471A (en) * 2022-03-23 2022-07-22 中国五冶集团有限公司 Cage rolling machine for steel bar framework

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106541059A (en) * 2016-12-07 2017-03-29 中铁九局集团有限公司 Suitable for the self-positioning colligation frock of high speed railway fragments-free track slab steel reinforcement cage
CN106541059B (en) * 2016-12-07 2018-06-29 中铁九局集团有限公司 Suitable for the self-positioning binding tooling of high speed railway fragments-free track slab steel reinforcement cage
CN114769471A (en) * 2022-03-23 2022-07-22 中国五冶集团有限公司 Cage rolling machine for steel bar framework
US20230302526A1 (en) * 2022-03-23 2023-09-28 China Mcc5 Group Corp. Ltd. Reinforcement Cage Rolling Machine

Similar Documents

Publication Publication Date Title
CN201240810Y (en) Novel manual hoister
CN201405007Y (en) Cage Rolling machine of reinforcing steel framework of bridge pier stud and pile foundation
CN107227686A (en) A kind of tunnel-type anchorage pre-stress system locating support construction method
CN111172892A (en) Bilateral balance traction device and method for steel structure frame bridge
CN103061313B (en) Channel slope concrete plastering troweling machine with vibration and rolling functions
CN201432071Y (en) Cage winding machine for pier column and pile foundation reinforcement cages
CN202490896U (en) Novel efficient web bar bending device in reinforcing steel bar truss welding production line
CN102862925B (en) Automatic pulley aligning and rope releasing preventing device for material hauling engine
CN211848999U (en) Bilateral balanced draw gear of steel structure frame bridge
CN102275829A (en) Frame high-altitude piece mounting method of dry quenching lifter device
CN202897905U (en) Suspension type hoist
CN201442007U (en) Spiral blade rolling mill
CN203887107U (en) Multifunctional rebar bending machine
CN204980997U (en) Portable engineering handling machine
CN108382433A (en) A kind of capacitor maintenance carrying platform and its application process
CN205182871U (en) Mill
CN101524704B (en) Helical blade rolling mill
CN102357766B (en) Steel bar truss feeding step pitch regulation device
CN202753110U (en) Roller exchanging device of belt conveyor
CN214527046U (en) Anti rolling device that pastes processing equipment that splits of bituminous paving
CN201570538U (en) Battery pole piece mill
US20230302526A1 (en) Reinforcement Cage Rolling Machine
CN221700871U (en) Adjustable linear lifting appliance for vertical prefabrication of arch ribs
CN219790254U (en) Auxiliary device for reconstruction of existing industrial building
CN211990333U (en) Reinforcement plate leveling device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CCCC(CHINA COMMUNICATIONS CONSTRUCTION COMPANY) TU

Free format text: FORMER OWNER: SUN XIUGUO

Effective date: 20111116

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 456750 HEBI, HENAN PROVINCE TO: 100088 XICHENG, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20111116

Address after: 100088 Beijing Desheng street, No. 85, Xicheng District

Patentee after: CCCC TUNNEL ENGINEERING Co.,Ltd.

Address before: 456750 Newtown village, Newtown Town, Hebi, Xunxian County, Henan

Patentee before: Sun Xiuguo

DD01 Delivery of document by public notice

Addressee: CCCC TUNNEL ENGINEERING Co.,Ltd.

Document name: Notification to Pay the Fees

DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: CCCC TUNNEL ENGINEERING Co.,Ltd.

Document name: Notification of Termination of Patent Right

DD01 Delivery of document by public notice
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100217

Termination date: 20180322