CN201404604Y - 高危杆塔抢修人员保护装置 - Google Patents
高危杆塔抢修人员保护装置 Download PDFInfo
- Publication number
- CN201404604Y CN201404604Y CN2009200899816U CN200920089981U CN201404604Y CN 201404604 Y CN201404604 Y CN 201404604Y CN 2009200899816 U CN2009200899816 U CN 2009200899816U CN 200920089981 U CN200920089981 U CN 200920089981U CN 201404604 Y CN201404604 Y CN 201404604Y
- Authority
- CN
- China
- Prior art keywords
- shaft tower
- prompt drop
- safety rope
- safe
- tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Emergency Lowering Means (AREA)
Abstract
本实用新型公开一种高危杆塔抢修人员保护装置,连接在杆塔和横担上,主要由第一安全绳、第二安全绳、第一速降组件、第二速降组件及地面固定件构成;杆塔上设有安全连接件,横担上具有安全吊接点;第一安全绳的一端穿接在第二速降组件内,第一安全绳的另一端穿过安全连接件连接在第一速降组件上;第二安全绳吊接在横担上,并穿过第一速降组件垂向地面;第二速降组件连接到地面固定件上。本实用新型巧妙地将攀岩工具合理应用于杆塔登高作业中,可广泛用于电力、通信、广播等高危杆塔的抢修和无爬梯水泥杆的攀登防坠,具有使用成本低、灵活多变、应用范围较广等特点,尤其适用于杆塔出现倾倒可能的工况。
Description
技术领域:
本实用新型涉及一种高空检修人员的救生设备,特别涉及通过绳索和扣环组件来完成人身保护的救生装置。
背景技术:
目前我国电力、通信、广播等杆塔检修人员攀登杆塔防坠落措施,一般都采用轨道或绳索配合人员携带速差保护装置来实现的。但是如果出现杆塔有倾倒的可能时,对杆塔进行抢修的过程中,抢修人员在攀登杆塔时的人身安全就显得尤为突出,对于高危杆塔的抢修人员来说,快速撤离高危杆塔是极其关键的,而现有的杆塔防坠装置都是在人员攀登时防止突然坠落的前提下进行的设计,因此不能满足对高危杆塔抢修时快速撤离的需要。
实用新型内容:
本实用新型所要解决的技术问题就是针对以上不足而提供一种高危杆塔抢修人员保护装置,该装置安全牢靠,成本低,而且安装和使用方便,应用范围广。
本实用新型采用的技术方案是:
一种高危杆塔抢修人员保护装置,连接在杆塔和横担上,主要由第一安全绳、第二安全绳、第一速降组件、第二速降组件及地面固定件构成;杆塔上设有安全连接件,横担上具有安全吊接点;第一安全绳的一端穿接在第二速降组件内,第一安全绳的另一端穿过安全连接件连接在第一速降组件上;第二安全绳吊接在横担上,并穿过第一速降组件垂向地面;第二速降组件连接到地面固定件上。
所述的安全连接件由套接在杆塔杆身或穿接在杆塔攀登架上的套索及套索两端的第一套环、第二套环构成,第一套环绕过杆塔杆身或杆塔攀登架并连接在套索上,第二套环穿接在第一安全绳上。
所述的第一速降组件包括有第一扣环、第一速降器和第二扣环;第一扣环扣接有第一安全绳和第二扣环;第一速降器套接在第二安全绳上,并与第二扣环扣接;第二扣环还与与登杆工作人员身上套穿的安全带扣接。
所述的第二速降组件包括有第二速降器、连接扣环和安全固定带构成,第二速降器套接在第一安全绳上,安全固定带连接在地面固定件上,连接扣环扣接在第二速降器和安全固定带之间。
所述的第一安全绳长度至少2倍于杆塔高度。
所述的第二安全绳长度至少1.1倍于杆塔高度。
所述的地面固定件为地锚或地面固定物或其它满足强度要求的物体。
本实用新型能够达到的有益效果是:
1、本实用新型构思巧妙,使用方便,具有使用成本低、灵活多变、应用范围较广等特点,对杆塔抢修工作时抢修人员的安全保护起到重要作用。
2、本实用新型巧妙地将攀岩工具合理应用于杆塔登高作业中,可广泛用于电力、通信、广播等高危杆塔的抢修和无爬梯水泥杆的攀登防坠,在实际演示操作中,人员从接到下塔命令到安全到达地面的时间在5秒左右,大大提高了抢修人员人身安全系数。
附图说明:
图1为本实用新型使用状态示意图。
图1为安全连接件与杆塔之间的连接示意图。
图2为第一速降组件连接关系示意图。
图3为第二速降组件与地面固定件连接关系示意图。
具体实施方式:
下面结合附图对本实用新型作进一步的描述:
如图1、图2、图3所示,该高危杆塔抢修人员保护装置的工作机理是:首先通过第一速降组件60将抢修人员吊起,抢修人员穿安全带61,通过第二扣环62扣接第一扣环63和第一速降器64,第一扣环63连接有第一安全绳40,第一速降器64套接在第二安全绳50上,第二安全绳50吊接在横担20上,第一安全绳40穿过杆塔10上的安全连接件30与第二速降组件70连接,安全连接件30由套接在杆塔10杆身11或穿接在杆塔10攀登架12上的套索32及套索两端的第一套环31、第二套环33构成,第一套环31绕过杆塔10的杆身11或穿过杆塔10的攀登架12并连接在套索32上,安全连接件30可根据需要设置多个,在抢修人员需要的地方将第一安全绳40穿接在第二套环33上,第一安全绳40通过第二速降组件70与1.5T地锚80通过安全固定带71连接,安全固定带71通过连接扣环72扣接有第二速降器73,第二速降器73上穿接有第一安全绳40,第一速降组件60由抢修人员控制,根据工作需要进行升降,第二速降组件70由地面作业人员控制。一旦发生意外,第一安全绳40、第二安全绳50、第一速降组件60、第二速降组件70及地锚80共同作用,完成对抢修人员的保护,为达到保护要求第一安全绳长度3倍于杆塔高度,第二安全绳长度1.5倍于杆塔高度。
Claims (7)
1、一种高危杆塔抢修人员保护装置,连接在杆塔和横担上,其特征在于:主要由第一安全绳、第二安全绳、第一速降组件、第二速降组件及地面固定件构成;杆塔上设有安全连接件,横担上具有安全吊接点;第一安全绳的一端穿接在第二速降组件内,第一安全绳的另一端穿过安全连接件连接在第一速降组件上;第二安全绳吊接在横担上,并穿过第一速降组件垂向地面;第二速降组件连接到地面固定件上。
2、如权利要求1所述的高危杆塔抢修人员保护装置,其特征在于:安全连接件由套接在杆塔杆身或穿接在杆塔攀登架上的套索及套索两端的第一套环、第二套环构成,第一套环绕过杆塔杆身或杆塔攀登架并连接在套索上,第二套环穿接在第一安全绳上。
3、如权利要求1所述的高危杆塔抢修人员保护装置,其特征在于:第一速降组件包括有第一扣环、第一速降器和第二扣环;第一扣环扣接有第一安全绳和第二扣环;第一速降器套接在第二安全绳上,并与第二扣环扣接;第二扣环还与与登杆工作人员身上套穿的安全带扣接。
4、如权利要求1所述的高危杆塔抢修人员保护装置,其特征在于:第二速降组件包括有第二速降器、连接扣环和安全固定带构成,第二速降器套接在第一安全绳上,安全固定带连接在地面固定件上,连接扣环扣接在第二速降器和安全固定带之间。
5、如权利要求1或2或3或4所述的高危杆塔抢修人员保护装置,其特征在于:第一安全绳长度至少2倍于杆塔高度。
6、如权利要求1或2或3或4所述的高危杆塔抢修人员保护装置,其特征在于:第二安全绳长度至少1.1倍于杆塔高度。
7、如权利要求1或2或3或4所述的高危杆塔抢修人员保护装置,其特征在于:地面固定件为地锚或地面固定物。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009200899816U CN201404604Y (zh) | 2009-05-04 | 2009-05-04 | 高危杆塔抢修人员保护装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009200899816U CN201404604Y (zh) | 2009-05-04 | 2009-05-04 | 高危杆塔抢修人员保护装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201404604Y true CN201404604Y (zh) | 2010-02-17 |
Family
ID=41675521
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009200899816U Expired - Fee Related CN201404604Y (zh) | 2009-05-04 | 2009-05-04 | 高危杆塔抢修人员保护装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201404604Y (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2483974A (en) * | 2010-09-22 | 2012-03-28 | Apollo Cradles Ltd | Fall arrest system with activation indicator |
CN106422107A (zh) * | 2016-10-28 | 2017-02-22 | 宁波天派智能科技有限公司 | 防坠落安全保护装置 |
CN106823184A (zh) * | 2017-01-16 | 2017-06-13 | 广州供电局有限公司 | 杆塔救援工具及方法 |
CN108046180A (zh) * | 2017-12-18 | 2018-05-18 | 国网山东省电力公司滨州市滨城区供电公司 | 一种输电线路杆塔检修防坠落装置及方法 |
CN108492743A (zh) * | 2018-03-20 | 2018-09-04 | 河南城建学院 | 一种城市规划设计用指示牌 |
CN113750380A (zh) * | 2021-09-10 | 2021-12-07 | 广东电网有限责任公司 | 一种电力杆塔 |
-
2009
- 2009-05-04 CN CN2009200899816U patent/CN201404604Y/zh not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2483974A (en) * | 2010-09-22 | 2012-03-28 | Apollo Cradles Ltd | Fall arrest system with activation indicator |
GB2483974B (en) * | 2010-09-22 | 2014-12-10 | Apollo Cradles Ltd | Safety system |
CN106422107A (zh) * | 2016-10-28 | 2017-02-22 | 宁波天派智能科技有限公司 | 防坠落安全保护装置 |
CN106823184A (zh) * | 2017-01-16 | 2017-06-13 | 广州供电局有限公司 | 杆塔救援工具及方法 |
CN108046180A (zh) * | 2017-12-18 | 2018-05-18 | 国网山东省电力公司滨州市滨城区供电公司 | 一种输电线路杆塔检修防坠落装置及方法 |
CN108492743A (zh) * | 2018-03-20 | 2018-09-04 | 河南城建学院 | 一种城市规划设计用指示牌 |
CN113750380A (zh) * | 2021-09-10 | 2021-12-07 | 广东电网有限责任公司 | 一种电力杆塔 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201404604Y (zh) | 高危杆塔抢修人员保护装置 | |
CN101069772B (zh) | 一种输电线路铁塔攀登过程中的防坠方法 | |
CN207518184U (zh) | 高空作业单杆防坠登高装置 | |
CN206910617U (zh) | 高空作业攀爬防坠装置 | |
CN201100002Y (zh) | 自动升降手机信号塔 | |
CN102107071A (zh) | G形手扣 | |
CN203504066U (zh) | 一种高空作业缓冲式保安绳 | |
CN201067590Y (zh) | 输电线路杆塔攀登防护装置 | |
CN210494941U (zh) | 输电线路攀登杆塔时的保护装置 | |
CN208877753U (zh) | 垂直梯攀爬保护器 | |
CN202336164U (zh) | 杆塔攀爬保护装置 | |
CN203050479U (zh) | 一种多功能电力检修梯 | |
CN201307730Y (zh) | 输电线路砼杆安全装置 | |
CN214105625U (zh) | 一种用于攀爬直梯的防坠装置 | |
CN204709673U (zh) | 组装式杆塔攀登防坠落装置 | |
CN201519393U (zh) | 新型登杆防坠带 | |
CN104110155B (zh) | 一种薄壁钢管杆塔及其加工与施工方法 | |
CN103001148A (zh) | 一种330kV双分裂导线单根断裂高空接续方法 | |
CN202474756U (zh) | 跨越网 | |
CN203564663U (zh) | 输电线路简易防坠落装置 | |
CN201596267U (zh) | 一种带有防护功能的防坠落自动锁定安全绳 | |
CN206285372U (zh) | 一种电缆登杆防坠装置 | |
CN202706642U (zh) | 配备防坠落装置的环形混凝土杆塔 | |
CN2915163Y (zh) | 输电线路铁塔防坠落装置 | |
CN201618336U (zh) | 机井救生装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100217 Termination date: 20120504 |