CN201377124Y - Connecting device between overhanging end of large overhanging truss and temporary support beam - Google Patents

Connecting device between overhanging end of large overhanging truss and temporary support beam Download PDF

Info

Publication number
CN201377124Y
CN201377124Y CN200920115423U CN200920115423U CN201377124Y CN 201377124 Y CN201377124 Y CN 201377124Y CN 200920115423 U CN200920115423 U CN 200920115423U CN 200920115423 U CN200920115423 U CN 200920115423U CN 201377124 Y CN201377124 Y CN 201377124Y
Authority
CN
China
Prior art keywords
wedge shape
temporary support
steel casing
cantilever frame
support columns
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200920115423U
Other languages
Chinese (zh)
Inventor
郭文军
华锦耀
吴佳雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUAFENG CONSTRUCTION CO Ltd
Original Assignee
HUAFENG CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUAFENG CONSTRUCTION CO Ltd filed Critical HUAFENG CONSTRUCTION CO Ltd
Priority to CN200920115423U priority Critical patent/CN201377124Y/en
Application granted granted Critical
Publication of CN201377124Y publication Critical patent/CN201377124Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a connecting device between an overhanging end of a large overhanging truss and a temporary support beam. An unloaderbox (9) is arranged between the overhanging end (1) of a large overhanging truss and a temporary support beam (2), and the unloaderbox (9) comprises a steel box body (3); the bottom plate (3.1) of the steel box body (3) is fixedly provided with a hydraulic jack (4), the top plate (3.2) of the steel box body (3) is provided with a round hole (5) and also provided with wedge-shaped steel subplates (6), and each group of wedge-shaped steel subplates (6) comprises four wedge-shaped steel subplates (6) which are overlapped, and one of the tops of each group of wedge-shaped steel subplates (6) is propped against the overhanging end (1) of the large overhanging truss, and the elevation of the top surface of one of the tops of each group of wedge-shaped steel subplates (6) is equal to the designed elevation of the bottom of the overhanging end (1) of the large overhanging truss. With the connecting device between the overhanging end of a large overhanging truss and the temporary support beam, the temporary support beam can be simply and safely removed.

Description

The linkage between end and the temporary support columns of encorbelmenting of big cantilever frame
Technical field
The utility model relates to a kind of construction work device, specifically be a kind of big cantilever frame encorbelment the end and temporary support columns between linkage.
Background technology
The canopy formula building that the grandstand of large public building is much more general to adopt the big cantilever frame by steel work or reinforced concrete structure to cooperate purlin and roof panel to constitute.Such construction techniques is as follows:
Carry out the construction of single truss structure earlier: the big cantilever frame that prefabrication is good is installed at the scene, and with the bottom and the basic fixed of the big cantilever frame of single Pin, and the middle-end of big cantilever frame is fixed on the frame column.For the stability that guarantees the follow-up construction of truss, prevent single truss structure distortion, also the end of encorbelmenting of big cantilever frame need be supported on the temporary support columns of temporarily constructing.At this moment, single truss structure installation is finished.
Repeat above-mentioned steps again, finish until whole truss installations.
Then, purlin, roof panel are installed on the good big cantilever frame of many Pin of construction, roofing supports and other auxiliary roof structures such as (insulation, waterproofing materialss), the monolithic roof structure.
At last, dismantle the temporary support columns of the big cantilever frame of every Pin.
Direct pressure-bearing contacts between encorbelment end and the temporary support columns (top) of the big cantilever frame of prior art.
There is following defective in the end of encorbelmenting of the big cantilever frame of prior art with syndeton between the temporary support columns: because direct pressure-bearing contacts between encorbelment end and the temporary support columns (top) of big cantilever frame, so when whole roof structures construction finishing needs are dismantled temporary support columns, because the load of roof structure is big, scale error when the normal deformation of big cantilever frame and canopy formula are built each member installation, make encorbelmenting of big cantilever frame produce bigger pressure between end and the temporary support columns, cause the dismounting work of temporary support columns to become very difficult, in addition accidents caused easily.
The utility model content
The technical problems to be solved in the utility model is, a kind of easy separation is provided, makes the linkage between end and the temporary support columns of encorbelmenting of the simple and safe big cantilever frame of temporary support columns dismounting.
Technical solution of the present utility model is, a kind of linkage between end and the temporary support columns of encorbelmenting of the big cantilever frame with following structure is provided, encorbelmenting of described big cantilever frame is provided with unloader box between end and the temporary support columns, described unloader box comprises the steel casing that is fixed on the temporary support columns top, the base plate center fixation of described steel casing has hydraulic jack, the top board center of described steel casing is provided with the circular hole that feed flow presses jack to pass, two groups of wedge shape billets are installed on the top board of described circular hole both sides, every group of wedge shape billet comprises at least four superimposed wedge shape billets, one end face of the top of described every group of wedge shape billet is against the bottom surface of the end of encorbelmenting of big cantilever frame, and the absolute altitude of one end face of the top of described every group of wedge shape billet equals the design elevation of bottom surface of the end of encorbelmenting of big cantilever frame.
After adopting above structure, the big cantilever frame of the utility model encorbelment the end and temporary support columns between linkage compared with prior art, have the following advantages:
Because indirect pressure-bearing contacts between encorbelment end and the temporary support columns (top) of big cantilever frame, be that encorbelmenting of big cantilever frame held two end face of the top that is pressed on two groups of wedge shape billets, so when whole roof structures construction finishing needs are dismantled temporary support columns, though have bigger pressure between the two wedge shape billets of the encorbelment end and the top of big cantilever frame, but the constructor can start hydraulic jack, and begin when encorbelmenting end in contact when the piston of hydraulic jack, just can produce and make the active force of end of encorbelmenting to top offset, continue jigger lifting piston, the slit that both are disengaged appears between end and the wedge shape billet until encorbelmenting, hydraulic jack is kept stable state, extract whole wedge shape billets out, at last hydraulic jack is slowly fallen after rise, the encorbelment bottom of end also is moved to design elevation thereupon, and just making encorbelments holds and unloader box disengages fully.Like this, the unloading process of temporary support columns becomes simply, has also avoided occurring security incident.
As improvement, the base plate center fixation of described steel casing has hydraulic jack to be meant, the base plate of described steel casing is provided with two mounting holes that are symmetrically distributed along diagonal, described hydraulic jack is by on the base plate that is bolted to the steel casing that passes mounting hole, like this, just can be as required in the fixing hydraulic jack of different size of steel box bottom.
As improving again, two groups of wedge shape billets are installed on the top board of described circular hole both sides to be meant, the circular hole both sides are fixed with the cylinder spacer pin of two epireliefs on the top board of described steel casing, the bottom surface of minimum wedge shape billet is provided with the blind hole that cooperates with the cylinder spacer pin in every group of wedge shape billet, this piece wedge shape billet by cylinder spacer pin and steel casing level to spacing, like this, make that fixing of wedge shape billet and steel casing is more firm.
Description of drawings
Fig. 1 is the side-looking structural representation of the linkage between end and the temporary support columns of encorbelmenting of the big cantilever frame of the utility model.
Fig. 2 be the big cantilever frame of the utility model the linkage between end and the temporary support columns of encorbelmenting face part (analysing and observe) structural representation.
Fig. 3 is the positive TV structure cross-sectional schematic of steel casing of the linkage between end and the temporary support columns of encorbelmenting of the big cantilever frame of the utility model.
Fig. 4 is the structural representation of looking up of Fig. 3.
Shown in the figure 1, the end of encorbelmenting of big cantilever frame, 2, temporary support columns, 3, the steel casing, 3.1, base plate, 3.2, top board, 4, hydraulic jack, 5, circular hole, 6, the wedge shape billet, 7, mounting hole, 8, the cylinder spacer pin, 9, unloader box.
The specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments.
As Fig. 1, Fig. 2, Fig. 3, shown in Figure 4, the big cantilever frame of the utility model encorbelment the end and temporary support columns between linkage, described big cantilever frame encorbelment the end 1 and temporary support columns 2 between be provided with unloader box 9.Described unloader box 9 comprises the steel casing 3 that is fixed on temporary support columns 2 tops, base plate 3.1 center fixation of described steel casing 3 have the hydraulic jack 4 of routine techniques, the base plate 3.1 that is described steel casing 3 is provided with two mounting holes 7 that are symmetrically distributed along diagonal, and described hydraulic jack 4 is by on the base plate that is bolted to steel casing 3 3.1 that passes mounting hole 7.Top board 3.2 centers of described steel casing 3 are provided with the circular hole 5 that feed flow presses jack 4 to pass, on the top board 3.2 of described circular hole 5 both sides two groups of wedge shape billets 6 are installed, it is the cylinder spacer pin 8 that circular hole 5 both sides are fixed with two epireliefs on the top board 3.2 of described steel casing 3, the bottom surface of minimum wedge shape billet 6 is provided with the blind hole that cooperates with cylinder spacer pin 8 in every group of wedge shape billet 6, this piece wedge shape billet 6 by cylinder spacer pin 8 and steel casing 3 levels to spacing.Every group of wedge shape billet 6 comprises four superimposed wedge shape billets 6, and one end face of the top of described every group of wedge shape billet 6 is against the bottom surface of the end 1 of encorbelmenting of big cantilever frame.The absolute altitude of one end face of the top of described every group of wedge shape billet 6 equals the design elevation of end 1 the bottom surface of encorbelmenting of big cantilever frame.

Claims (3)

1, a kind of big cantilever frame encorbelment the end and temporary support columns between linkage, it is characterized in that: encorbelmenting of described big cantilever frame is provided with unloader box (9) between end (1) and the temporary support columns (2), described unloader box (9) comprises the steel casing (3) that is fixed on temporary support columns (2) top, base plate (3.1) center fixation of described steel casing (3) has hydraulic jack (4), top board (3.2) center of described steel casing (3) is provided with the circular hole (5) that feed flow presses jack (4) to pass, on the top board (3.2) of described circular hole (5) both sides two groups of wedge shape billets (6) are installed, every group of wedge shape billet (6) comprises at least four superimposed wedge shape billets (6), one end face of the top of described every group of wedge shape billet (6) is against the bottom surface of end (1) of encorbelmenting of big cantilever frame, and the absolute altitude of one end face of the top of described every group of wedge shape billet (6) equals the design elevation of bottom surface of the end (1) of encorbelmenting of big cantilever frame.
2, big cantilever frame according to claim 1 encorbelment the end and temporary support columns between linkage, it is characterized in that: base plate (3.1) center fixation of described steel casing (3) has hydraulic jack (4) to be meant, the base plate (3.1) of described steel casing (3) is provided with two mounting holes (7) that are symmetrically distributed along diagonal, and described hydraulic jack (4) is by on the base plate that is bolted to steel casing (3) (3.1) that passes mounting hole (7).
3, big cantilever frame according to claim 1 encorbelment the end and temporary support columns between linkage, it is characterized in that: on the top board (3.2) of described circular hole (5) both sides two groups of wedge shape billets (6) are installed and are meant, the top board (3.2) of described steel casing (3) is gone up the cylinder spacer pin (8) that circular hole (5) both sides are fixed with two epireliefs, the bottom surface of minimum wedge shape billet (6) is provided with the blind hole that cooperates with cylinder spacer pin (8) in every group of wedge shape billet (6), this piece wedge shape billet (6) by cylinder spacer pin (8) and steel casing (3) level to spacing.
CN200920115423U 2009-03-12 2009-03-12 Connecting device between overhanging end of large overhanging truss and temporary support beam Expired - Fee Related CN201377124Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200920115423U CN201377124Y (en) 2009-03-12 2009-03-12 Connecting device between overhanging end of large overhanging truss and temporary support beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200920115423U CN201377124Y (en) 2009-03-12 2009-03-12 Connecting device between overhanging end of large overhanging truss and temporary support beam

Publications (1)

Publication Number Publication Date
CN201377124Y true CN201377124Y (en) 2010-01-06

Family

ID=41517228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200920115423U Expired - Fee Related CN201377124Y (en) 2009-03-12 2009-03-12 Connecting device between overhanging end of large overhanging truss and temporary support beam

Country Status (1)

Country Link
CN (1) CN201377124Y (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102936962A (en) * 2012-11-20 2013-02-20 永升建设集团有限公司 Construction method of slanting cantilever steel structure supported by temporary steel frame
CN104612409A (en) * 2014-12-25 2015-05-13 安徽伟宏钢结构集团股份有限公司 Pipe truss structure single pipe supporting sorted unloading tool and using method thereof
CN105178614A (en) * 2015-10-14 2015-12-23 中铁十四局集团第三工程有限公司 Jack for steel truss girder upper chord member installation and steel truss girder upper chord member installation process
CN106013840A (en) * 2016-05-16 2016-10-12 中天建设集团有限公司 Unloading steel supporting node constitution of stiffened cantilevered structure and construction method of unloading steel supporting node constitution
CN106836498A (en) * 2016-12-28 2017-06-13 郑州工业应用技术学院 A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN107989196A (en) * 2017-10-23 2018-05-04 中国十七冶集团有限公司 A kind of large-span double-layer overhangs discharging method
CN112392259A (en) * 2020-12-09 2021-02-23 北京建工集团有限责任公司 Synchronous grading unloading method for steel truss with jacking oil cylinder replaced by double supporting points

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102936962A (en) * 2012-11-20 2013-02-20 永升建设集团有限公司 Construction method of slanting cantilever steel structure supported by temporary steel frame
CN104612409A (en) * 2014-12-25 2015-05-13 安徽伟宏钢结构集团股份有限公司 Pipe truss structure single pipe supporting sorted unloading tool and using method thereof
CN105178614A (en) * 2015-10-14 2015-12-23 中铁十四局集团第三工程有限公司 Jack for steel truss girder upper chord member installation and steel truss girder upper chord member installation process
CN106013840A (en) * 2016-05-16 2016-10-12 中天建设集团有限公司 Unloading steel supporting node constitution of stiffened cantilevered structure and construction method of unloading steel supporting node constitution
CN106836498A (en) * 2016-12-28 2017-06-13 郑州工业应用技术学院 A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN106836498B (en) * 2016-12-28 2022-11-29 郑州工业应用技术学院 Hoisting construction method for steel truss of grand stand roof of super-large span stadium
CN107989196A (en) * 2017-10-23 2018-05-04 中国十七冶集团有限公司 A kind of large-span double-layer overhangs discharging method
CN112392259A (en) * 2020-12-09 2021-02-23 北京建工集团有限责任公司 Synchronous grading unloading method for steel truss with jacking oil cylinder replaced by double supporting points
CN112392259B (en) * 2020-12-09 2022-02-01 北京建工集团有限责任公司 Synchronous grading unloading method for steel truss with jacking oil cylinder replaced by double supporting points

Similar Documents

Publication Publication Date Title
CN201377124Y (en) Connecting device between overhanging end of large overhanging truss and temporary support beam
CN102251615B (en) Prestressed metal sheet structural system and construction method thereof
CN103452311B (en) A kind of erection method of shaped steel suspended structural support frame
CN202090433U (en) Rectangular structure using prestress metal plate roof
CN107034790B (en) Method for reducing support internal force during steel beam symmetrical double-cantilever assembly
CN203247868U (en) Large-span steel structure construction temporary supporting frame
CN208907317U (en) A kind of form for construction engineering support device
CN114263377A (en) Steel construction factory building
CN202090483U (en) Round structure with prestressed sheet metal roof
CN217299070U (en) Conversion beam for house deviation correction and deviation correction assembly
CN210562978U (en) External prestressing force structure of building roof beam
CN109296069B (en) Earthquake-resistant energy-consuming connecting node with repairable prefabricated steel structure
CN215561946U (en) Door opening type support for installing and adjusting pre-buried steel plate of arch support
CN220087194U (en) Fixing device of photovoltaic product
CN220468873U (en) Support changing structure for inner support detachment
CN219342853U (en) Pier stud steel template structure
KR200230089Y1 (en) Shifting up and down system of continuous preflex composite girder on temporary support
CN215252993U (en) Construction elevator foundation back-jacking device
CN220814267U (en) Stable and reliable light steel assembled building structure
CN216839066U (en) Assembled T type roof beam jacking auxiliary steel member
CN212078777U (en) Reverse top supporting frame device
CN221030652U (en) Assembled building steel construction beam column connecting element
CN217735014U (en) Back-to-back direct current converter station valve hall structure in coastal region
CN210308373U (en) Assembled curing kiln frame
CN220183821U (en) Deviation correcting device of damping shock insulation rubber support behind case roof beam Cheng Qiao

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
PP01 Preservation of patent right

Effective date of registration: 20130912

Granted publication date: 20100106

RINS Preservation of patent right or utility model and its discharge
PD01 Discharge of preservation of patent

Date of cancellation: 20140310

Granted publication date: 20100106

RINS Preservation of patent right or utility model and its discharge
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100106

Termination date: 20140312