CN201364374Y - Insulation performance test instrument for power gloves and boots - Google Patents
Insulation performance test instrument for power gloves and boots Download PDFInfo
- Publication number
- CN201364374Y CN201364374Y CNU2009200888737U CN200920088873U CN201364374Y CN 201364374 Y CN201364374 Y CN 201364374Y CN U2009200888737 U CNU2009200888737 U CN U2009200888737U CN 200920088873 U CN200920088873 U CN 200920088873U CN 201364374 Y CN201364374 Y CN 201364374Y
- Authority
- CN
- China
- Prior art keywords
- boots
- test
- reometer
- parallel
- gloves
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009413 insulation Methods 0.000 title claims abstract description 12
- 238000011056 performance test Methods 0.000 title abstract 3
- 238000012360 testing method Methods 0.000 claims abstract description 46
- 230000001012 protector Effects 0.000 claims abstract description 3
- 238000000034 method Methods 0.000 abstract description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract 1
- 230000015556 catabolic process Effects 0.000 description 2
- 238000001514 detection method Methods 0.000 description 2
- 238000005259 measurement Methods 0.000 description 2
- 238000010998 test method Methods 0.000 description 2
- 230000002950 deficient Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000006870 function Effects 0.000 description 1
- 230000009191 jumping Effects 0.000 description 1
Images
Landscapes
- Professional, Industrial, Or Sporting Protective Garments (AREA)
Abstract
The utility model belongs to test instrument field and relates to an insulation performance test instrument for power gloves and boots, which is characterized in that the insulation performance test method for power gloves and boots in prior art is improved; a test control circuit is arranged in a control panel, more than one current input wire are connected with the input wire of an ammeter in parallel, each input wire is connected with a measuring switch in series and is connected with electrode arranged in corresponding insulation water tank, the electrodes are connected with the ground wire of the ammeter through normally-closed switches, protectors are connected with the normally-closed switches in parallel, high voltage output wire electrodes in the same number of input wires of ammeter are connected with high voltage output wire electrodes of transformer; when the model instrument is in use, the test efficiency is improved greatly; the work staff and instruments are all effectively and safely protected.
Description
Technical field
The utility model belongs to field of test instrument, relates to electric insulation apparatus ability meter, is specifically related to a kind of electric power gloves boots insulating property tester.
Background technology
Electric operating is various with insulating protection apparatus kind quantity, and wherein high tension insulating gloves, high-voltage insulating boots account for over halfly, need often do AC voltage withstand test and leakage current test to every apparatus, detect the High-Voltage Insulation security performance of every articles for use.
Traditional detection electric power adopts when test with the method for gloves, boots insulating property always, product to be tested is placed on the insulating mat of interim place mat, utilizes every test product of the manual contact of electrode of reometer.This insulating property method of testing, because means of testing is quite simple and crude, product to be tested quantity is more, and reometer is because of the electrode loose contact sensitive for damages, and transformer easily causes damaging because of frequently opening jumping; Since at every turn can only single-piece test, every/needs 5 minutes, only the test of gloves, boots just needs 6 days a medium electric power inspection center; Because means of testing is simple and crude, current measurement circuit lacks the reliably protecting measure, exists operator safety hidden danger.
The utility model content
The designer is in putting into practice the contact activity, find that existing electric power exists above-mentioned defective with the High-Voltage Insulation Testing Method of Safety of gloves, boots, improve through constantly exploring, purpose is to provide a kind of electric power gloves boots insulating property tester, testing efficiency be can improve, testing equipment and personal safety ensured.
Technical solution adopted in the utility model is a kind of electric power of design gloves boots insulating property tester; its structure comprises: reometer; control desk; in control desk, be connected with test control circuit mutually with reometer; adopt one or more electric current incoming line in parallel with the incoming line of reometer; the measuring switch of connecting on every incoming line; link to each other with electrode in being arranged on corresponding insulation pond by measuring switch; each electrode links to each other with the reometer ground wire by normally closed switch; the protector of establishing in parallel with normally closed switch is same as the high-voltage output line electrode of reometer incoming line with transformer high-voltage output line electrode quantity in parallel.
The utility model is owing to adopt technique scheme and measure, traditional electric power is improved with gloves boots insulating property method of testing, designed this electric power gloves boots insulating property tester, a kind of tester of standard is provided for electric power detection department, both can do the AC voltage withstand test of test product, can do the leakage current test of test product again; In operating process,, can utilize the existing overcurrent protection function of transformer if the test product insulation breakdown takes place, if the test circuit open circuit takes place, loop voltage raises, the breakdown discharge of discharge tube meeting, can guarantee that personnel and instrument and equipment can not be on the hazard, and eliminate safe hidden trouble; When doing AC voltage withstand test, can realize that many test products test simultaneously, saved the time, improved efficient.
Description of drawings
Fig. 1 represents the structural principle synoptic diagram of the utility model electric power with gloves boots insulating property tester.
Embodiment
Reach embodiment in conjunction with the accompanying drawings, further specify the concrete structure of the utility model electric power with gloves boots insulating property tester, its feature and advantage are clearer.
The utility model electric power embodiment of gloves boots insulating property tester, referring to Fig. 1, its structure comprises: control desk 1, reometer A, linking to each other with reometer A in control desk 1 is provided with test control circuit, and test control circuit adopts the electric current incoming line X with reometer A
12 electric current incoming line X in parallel
2, X
3(model machine adopts 7 in parallel) is at every electric current incoming line X
1, X
2, X
3On the keyswitch CK that connects respectively
1, CK
2, CK
3As measuring switch, pass through CK
1, CK
2, CK
3The electrode that is located in the corresponding insulation pond 2.1,2.2,2.3 with spy links to each other, and each electrode is respectively by button normally closed switch DK
1, DK
2, DK
3Link to each other with the ground wire E of reometer A, with DK
1, DK
2, DK
3Difference parallel discharge protection of pipe device F
1, F
2, F
3, with the high-voltage output line electrode Y of transformer B
1Quantity in parallel is same as reometer A incoming line X
12 high-voltage output line electrode Y
2, Y
3
During use, 3 three electric power of test product only are placed in the insulation pond 2.1,2.2,2.3 with gloves or boots branch.With transformer B high-voltage output line electrode Y
1, Y
2, Y
3Insert contact test product 3 memory mediums respectively, normally closed switch DK
1, DK
2, DK
3All be in normally off.B provides high voltage by transformer, and at this moment the shunt current of Chan Shenging electrode and normally closed switch ground connection in test product, pond ensures that the loop is in low (zero) current potential, promptly once finishes many test product AC voltage withstand test; When doing the measurement leakage current test, the closed first via switch CK of elder generation
1, open switch DK
1, ground loop disconnects, and electric current is through switch CK
1, reometer A ground connection, carry out first test product leakage current testing; When testing second test product, closed first via switch DK
1, cut-off switch CK
1, the direct ground connection in loop, the closed second way switch CK
2, open switch DK
2, ground loop disconnects, and electric current is through switch CK
2, reometer A ground connection, carry out second test product leakage current testing....., and the like, whole test finishes, step-down.
Model machine adopts 7 electric current incoming lines in parallel with the incoming line of reometer, and is on probation through contrasting, test product gloves, boots, contrast need be finished test in 6 days, this model machine advances to 1 day and just can finish test, and testing crew can relievedly courageously be operated without scruple in the test process, has guaranteed personal device security.
Claims (1)
1, a kind of electric power gloves boots insulating property tester; comprise reometer; control desk; it is characterized in that in control desk, being connected with test control circuit mutually with reometer; adopt one or more electric current incoming line in parallel with the incoming line of reometer; the measuring switch of connecting on every incoming line; link to each other with electrode in the corresponding insulation pond by measuring switch; each electrode links to each other with the reometer ground wire by normally closed switch; the protector of establishing in parallel with normally closed switch is same as the high-voltage output line electrode of reometer incoming line with transformer high-voltage output line electrode quantity in parallel.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNU2009200888737U CN201364374Y (en) | 2009-03-10 | 2009-03-10 | Insulation performance test instrument for power gloves and boots |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNU2009200888737U CN201364374Y (en) | 2009-03-10 | 2009-03-10 | Insulation performance test instrument for power gloves and boots |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN201364374Y true CN201364374Y (en) | 2009-12-16 |
Family
ID=41475042
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CNU2009200888737U Expired - Fee Related CN201364374Y (en) | 2009-03-10 | 2009-03-10 | Insulation performance test instrument for power gloves and boots |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN201364374Y (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102680865A (en) * | 2012-04-20 | 2012-09-19 | 石家庄供电公司 | All-in-one device for insulating glove insulation test test |
| CN103376393A (en) * | 2012-04-28 | 2013-10-30 | 国家电网公司 | Device for alternating-current voltage withstanding test of transformer with wires led out of cable warehouse |
| CN105067977A (en) * | 2015-08-06 | 2015-11-18 | 中石化炼化工程(集团)股份有限公司 | Withstand voltage test method for combined electrode |
| CN114487717A (en) * | 2020-10-27 | 2022-05-13 | 应城市新都化工有限责任公司 | Factory self-service comprehensive electric power safety tool preventive test platform |
| CN118112381A (en) * | 2024-04-30 | 2024-05-31 | 温州电力建设有限公司 | Insulator string intelligent test system and method |
-
2009
- 2009-03-10 CN CNU2009200888737U patent/CN201364374Y/en not_active Expired - Fee Related
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102680865A (en) * | 2012-04-20 | 2012-09-19 | 石家庄供电公司 | All-in-one device for insulating glove insulation test test |
| CN102680865B (en) * | 2012-04-20 | 2014-08-27 | 国家电网公司 | Integrated device for insulation test of insulation glove |
| CN103376393A (en) * | 2012-04-28 | 2013-10-30 | 国家电网公司 | Device for alternating-current voltage withstanding test of transformer with wires led out of cable warehouse |
| CN103376393B (en) * | 2012-04-28 | 2015-11-04 | 国家电网公司 | AC Voltage Withstanding Test Device for Outgoing Transformer in Cable Warehouse |
| CN105067977A (en) * | 2015-08-06 | 2015-11-18 | 中石化炼化工程(集团)股份有限公司 | Withstand voltage test method for combined electrode |
| CN114487717A (en) * | 2020-10-27 | 2022-05-13 | 应城市新都化工有限责任公司 | Factory self-service comprehensive electric power safety tool preventive test platform |
| CN118112381A (en) * | 2024-04-30 | 2024-05-31 | 温州电力建设有限公司 | Insulator string intelligent test system and method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106463944B (en) | Method for detecting open-phase conditions in transformers | |
| CN103323655B (en) | Non-contact alternating current and direct current crosstalk online detecting device and non-contact alternating current and direct current crosstalk online detecting method | |
| CN201364374Y (en) | Insulation performance test instrument for power gloves and boots | |
| CN105223427B (en) | The detection method and detection device of fault electric arc | |
| CN106124920A (en) | Transformator neutral conductor virtual connection fault detection method | |
| CN201666902U (en) | High-voltage line parameter testing and protecting device | |
| CN104065034A (en) | Low-voltage failure detector | |
| CN202522537U (en) | Insulating tool edge planar defect on-site detection device | |
| CN104360236A (en) | Quick detection complete device and method for electric leakage points of 0.4 kV overhead line | |
| CN203025289U (en) | Comprehensive relay protection tester based on self-protection technology | |
| CN202903864U (en) | Electric leakage current detection device of single-phase AC power supply circuit | |
| CN104183379A (en) | Connecting device for maintenance of secondary side of electric power current transformer | |
| CN105203947A (en) | Performance characteristic testing method of high-voltage circuit breaker | |
| CN206378536U (en) | A high-efficiency electrical safety performance testing equipment | |
| CN203164278U (en) | Transformer substation switch chamber high-voltage equipment grounding step voltage detecting device | |
| CN103197127A (en) | Grounding step voltage detecting method and grounding step voltage detecting device of high-voltage equipment of switch gear room of converting station | |
| CN204882697U (en) | High -voltage live -line detection device | |
| CN204855647U (en) | A discharge device for transformer winding direct current resistance measurement | |
| CN204789785U (en) | Portable intelligent substation relay protection testing arrangement | |
| CN100412556C (en) | Time sequence identification and leakage selection method and protector of mine low-voltage power grid | |
| CN203951163U (en) | Low voltage failure detector | |
| CN204044294U (en) | A kind of insulating tool power frequency withstand test measuring and protecting device | |
| CN206992687U (en) | A kind of electrical management device based on power line communication technology | |
| CN202940561U (en) | Dedicated explosion-proof power supply device for field operation | |
| McDonagh et al. | Use of faulted phase earthing using a custom built earth fault controller |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C17 | Cessation of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |